Chapter 15 Cost Control
2
Cost Management Cost estimating Cost accounting Project cash flow
Company cash flow Direct labor costing Overhead rate costing Others, such as incentives, penalties, and profit-sharing
3
Cost Control Requirements
Measure resources consumed Measure status and accomplishments Compare measurements to projections and standards Provide the basis for diagnosis and re-planning
4
Cost Control Requirements (Continued)
Frequent, periodic comparison of actual progress and expenditures to schedules and budgets, both at the time of comparison and at project completion
5
WHEN TO IMPLEMENT A COST MANAGEMENT SYSTEM
Possible cost reductions Cost of change PROJECT COSTS PROJECT LIFE CYCLE PHASES CONCLUSION A cost management system should be implemented right at the beginning of the life cycle of the project.
6
PLANNING AND BUDGETING
WBS Element Work Package Work packages M G R Org WP______ORG_______ Description of task_____ ____________________ Sched: Start____Stop__ Budget:______________ Org Org
7
Sources Of Additional Funding
Funded contract change Management reserve Undistributed budget (money waiting to be allocated)
8
Cost Data Labor Material Other direct charges Overhead
9
VARIABLES FOR VARIANCE ANALYSIS
BUDGETED COST FOR WORKED SCHEDULED (BCWS) IS THE BUDGETED AMOUNT OF COST FOR WORK SCHEDULED TO BE ACCOMPLISHED PLUS THE AMOUNT OF LEVEL OF EFFORT. BUDGETED COST FOR WORK PERFORMED (BCWP) IS THE BUDGETED AMOUNT OF COST FOR COMPLETED WORK, PLUS BUDGETED FOR LEVEL OF EFFORT OR APPORTIONED EFFORT ACTIVITY COMPLETED WITHIN A GIVEN TIME PERIOD. THIS IS SOMETIMES REFERRED TO AS AN “EARNED VALUE.” ACTUAL COST FOR WORK PERFORMED (ACWP) IS THE AMOUNT REPORTED AS ACTUALLY EXPENDED IN COMPLETING THE WORK ACCOMPLISHED WITHIN A GIVEN TIME PERIOD. COST VARIANCE = BCWP – ACWP SCHEDULE/PERFORMANCE VARIANCE = BCWP - BCWS
10
Variances The cost variance compares deviations only from the budget and does not provide a measure of comparison between work scheduled and work accomplished. The scheduling variance provides a comparison between planned and actual performance but does not include costs.
11
Measurements Measurable efforts: discrete increments of work with a definable schedule for accomplishment, whose completion produces tangible results. Level of effort: work that does not lend itself to subdivision into discrete scheduled increments of work, such as project support and project control.
12
COST VARIANCE CALCULATION
CV = BCWP - ACWP A NEGATIVE VARIANCE INDICATES A COST OVERRUN
13
SCHEDULE VARIANCE CALCULATION
SV = BCWP - BCWS A NEGATIVE VARIANCE INDICATES A BEHIND SCHEDULE CONDITION
14
VARIANCE PERCENTS SV SCHEDULE VARIANCE % = X 100 (SVP) BCWS
COST VARIANCE % = (CVP) X 100 BCWS CV X 100 BCWP
15
Project Variance Analysis
VARIANCE UPPER BOUNDARY PROJECTED COST $ ACTUAL COST VARIANCE VARIANCE LOWER BOUNDARY R&D QUALIFICATION DEVELOPMENT PHASE I PHASE II PHASE III TIME
16
Management Reserve CONTRACTED COST MANAGEMENT ACTUAL COST RESERVE $
RELEASED BUDGET TIME
17
Information Requirements
Budgeted cost for work scheduled (BCWS) Budgeted cost for work performed (BCWP) Actual cost for work performed (ACWP) Estimated cost at completion Budgeted cost at completion Cost and schedule variances/explanations Traceability
18
Earned Value Status Reporting
TIME LINE BCWS SV ACWP CV CUMMULATIVE COST, $ BCWP TIME
19
ESTIMATE AT COMPLETION (EAC)
ACWP EAC = X Budget at completion BCWP (BAC) The estimate at completion is the best estimate of the total cost at the completion of the project. The EAC is a periodic evaluation of the status of the project - usually on a monthly basis or until a significant change has been identified.
20
Cost Problems Poor estimating techniques and/or standards, resulting in unrealistic budgets Inadequate work breakdown structure No management policy on reporting and control practices Poor work definition at the lower levels of the organization