Presentation is loading. Please wait.

Presentation is loading. Please wait.

Fire Island Wind CIRI, through its Fire Island Wind LLC subsidiary, is developing Southcentral Alaska’s first utility-scale wind project Aerial view of.

Similar presentations


Presentation on theme: "Fire Island Wind CIRI, through its Fire Island Wind LLC subsidiary, is developing Southcentral Alaska’s first utility-scale wind project Aerial view of."— Presentation transcript:

1

2 Fire Island Wind CIRI, through its Fire Island Wind LLC subsidiary, is developing Southcentral Alaska’s first utility-scale wind project Aerial view of Fire Island photo from fact sheet

3 Project Overview Located on Fire Island, near Railbelt load center, three miles west of Anchorage First power fall 2012 Chugach Electric Association power purchase agreement 25-year term starts Jan. 1, 2013

4 Project description 11 General Electric 1.6 MW XLE wind turbines 17.6 MW capacity 32.8 percent net capacity factor 51,000 MW-hours annually ~ 6,000 households Offset 0.5 bcf natural gas consumption annually On-island infra-structure: roads, electrical collection and transmission systems and operations and maintenance building with overnight facilities Subsequent phases could include up to 33 turbines

5 Project Status Report Chugach is buyer for up to 100 % of first phase power Regulatory Commission of Alaska approved inclusion of cost for FIW power in CEA’s rates Financing complete. All contracts and permits are complete.

6 Transmission Interconnection 12.5 mile double-circuit transmission line $25 million State of Alaska appropriation Construction managed by CIRI Land based construction contractor Submarine based construction contractor Transmission cable and switchgear Chugach to own and maintain line at COD

7 Construction Contractors Delaney Construction Group Northern Powerline Constructors Cruz Construction Local Supplemental Contractors IBEW GMC Spernak Chugach Electric CRW, RSE, EPS, D&L, TBC Hydro Ax, Alaska Structures Carlos Tree Service, NW Landscaping

8 Project Schedule 2011 RCA approval of power purchase agreement Complete all commercial contracts and financing Complete transmission-related construction contracts Complete civil and structural BOP engineering Order long lead-time construction materials Complete transmission-related pre-construction field work

9 Project Schedule

10

11 2012 Complete on-island civil and electrical construction Construct O&M facility Deliver and erect wind turbines Construct transmission interconnection Project commissioning – wind turbines and intertie Commercial operation

12 Project supports Alaska energy goals Sustainable energy project Private investment Creates many local jobs Locally owned and operated Local energy supply diversification Long-term energy price stability Environmentally responsible

13


Download ppt "Fire Island Wind CIRI, through its Fire Island Wind LLC subsidiary, is developing Southcentral Alaska’s first utility-scale wind project Aerial view of."

Similar presentations


Ads by Google