THE I-75 DAYTON RECONSTRUCTION
2
I-75 RECONSTRUCTION RECONSTRUCT I-75 BETWEEN SR 4 AND US 35
THREE MAJOR PROJECTS TO RECONSTRUCT I-75 BETWEEN SR 4 AND US 35 ADD 1 LANE EACH DIRECTION; REDUCE NB 90 DEGREE CURVE; REDUCE NO. OF RAMPS PHASE 1A SPRING 2007 – FALL 2009 PHASE 1B SPRING 2008 – FALL 2009 PHASE 2 SPRING 2011 – FALL 2013
3
SR 4 I-75 IN DOWNTOWN DAYTON PHASES 1A, 1B, 2 1A 2 1B US 35
4
SYSTEM CONFIGURATION 2 DYNAMIC MESSAGE SIGNS 7 CCTV CAMERAS / VEHICLE DETECTION STATIONS 4 HIGHWAY ADVISORY RADIOS 2 CCTV INSTALLED ON ROOF OF MONTGOMERY COUNTY BUILDING
5
FEATURES MOST DEVICES INSTALLED ON TEMPORARY BASIS WIRELESS COMMUNICATIONS FOR ALL DEVICES ONLY DMS WILL BE PERMANENT WEEKDAY/DAYTIME CONTROL FROM D7 OFFICE IN VANDALIA NIGHTTIME/WEEKEND CONTROL FROM ARTIMIS
6
TRAFFIC MANAGEMENT CENTER
7
CCTV LOCATIONS
8
CAMERAS ON ROOF OF THE MONTGOMERY COUNTY BUILDING
9
DYNAMIC MESSAGE SIGNS
10
HAR LOCATIONS
11
TRAVEL TIME WILL BE ACQUIRED
FOR AN 8-MILE SECTION ENCOMPASSING THE WORK ZONES OF ALL 3 CONSTRUCTION PHASES CALCULATION BASED UPON EITHER LICENSE PLATE READERS OR CELLULAR PHONE TRACKING
13
OPPORTUNITIES TO LEVERAGE
INFRASTRUCTURE
14
IN SUMMARY: EARLY DEPLOYMENT OF PORTION OF REGIONAL FMS MAINTENANCE OF TRAFFIC LEVERAGE INFRASTRUCTURE FROM PLANNED ROADWAY PROJECTS