Republic of the Philippines DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
2
ILOILO RIVER BATIANO RIVER CALAJUNAN CREEK DUNGON CREEK MAMBOG CREEK-JIBAO- AN RIVER CABALUAN RIVER Pavia Sta. Barbara San Miguel Oton River Systems Iloilo City Republic of the Philippines DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
3
ILOILO RIVER ILOILO RIVER ILOILO RIVER ILOILO RIVER City Proper Molo Arevalo Oton Carpenter’s Bridge Diversion Bridge Jalandoni Bridge Forbes Bridge Quirino Bridge Sooc Bridge Mohon Bridge Lambuyao Culvert ILOILO RIVER
4
Republic of the Philippines DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS Upstream of Batiano River Poblacion Oton Brgy. Alegre OtonBrgy. San Nicolas Oton Brgy. Sta Cruz Arevalo Brgy. Sto Nino Sur Arevalo Brgy. Sto Nino Sur Arevalo (near JBLMU) Brgy. Sto Nino Norte Arevalo (downstream Yulo Br.) Brgy. Calaparan ArevaloBrgy. Calumpang Molo Brgy. San Juan MoloBrgy. Boulevard Molo (upstream of Batiano Brd.) Brgy. Boulevard Molo (downstream of Batiano Brd.) BATIANO RIVER
5
Republic of the Philippines DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS City Proper Molo Arevalo Oton ILOILO RIVER IMPROVEMENT (Dredging and Excavation) 9.33 Km Quirino Br. Mohon Br. Trenas Boulevard Forbes Br. Jalandoni Br. Carpentr’s Br. Sooc BridgeBr. Lapaz Mandurriao (Dredging and Excavation)
6
SECTION 6 (ILOILO BRIDGE - CARPENTER BRIDGE) Length: 2.26 Volume : 76,640 m 3 SECTION 6 (ILOILO BRIDGE - CARPENTER BRIDGE) Length: 2.26 Volume : 76,640 m 3 SECTION 4 (FORBES BRIDGE - JALANDONI BRIDGE) Length: 1.84 km Volume : 111,420 m 3 SECTION 4 (FORBES BRIDGE - JALANDONI BRIDGE) Length: 1.84 km Volume : 111,420 m 3 SECTION 2 (QUIRINO LOPEZ BR. - MUELLE LONEY BR.) Length: 1.48 km Volume : 51,760 m 3 SECTION 2 (QUIRINO LOPEZ BR. - MUELLE LONEY BR.) Length: 1.48 km Volume : 51,760 m 3 SECTION 1(ARROYO TO QUIRINO LOPEZ BR.) Length: 0.47 Km Volume : 100, 000 m 3 SECTION 1(ARROYO TO QUIRINO LOPEZ BR.) Length: 0.47 Km Volume : 100, 000 m 3 ILOILO – ANTIQUE ROAD GENERAL LUNA STREET ILOILO – ANTIQUE ROAD GENERAL LUNA STREET IZNART STREET ARROYO STREET MUELLE LONEY STREET ILOILO DIVERSION ROAD R. MAPA STREET TREÑAS BOULEVARD ILOILO RIVER ILOILO RIVER ILOILO RIVER ILOILO RIVER ILOILO RIVER DUNGON CREEK Republic of the Philippines DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS REGION VI – WESTERN VISAYAS SECTION 5 (JALANDONI BRIDGE - ILOILO BRIDGE) Length : 0.81 Volume : 89,210 m 3 With exception Volume : 45,492.5 m 3 SECTION 5 (JALANDONI BRIDGE - ILOILO BRIDGE) Length : 0.81 Volume : 89,210 m 3 With exception Volume : 45,492.5 m 3 SECTION 3 (MUELLE LONEY BR. - FORBES BRIDGE) Length: 0.12 km Volume: 8,440 m 3 SECTION 3 (MUELLE LONEY BR. - FORBES BRIDGE) Length: 0.12 km Volume: 8,440 m 3 SECTIONVOLUME OPERATIONAL COST TOTALDURATION DREDGINGHAULING STATION 1TO BE DREDGED BY DREDGE VISAYAS II STATION 251,76001.55 M6.21 M7.76 M5 mo. STATION 38,4400.25 M1.01 M1.26 M1 mo. STATION 4111,4203.34 M13.37 M16.71 M10.5 mo. STATION 543,7201.31 M5.25 M6.56 M4.2 mo. STATION 676,6402.30 M9.20 M11.50 M7.3 mo. T O T A L291,9808.75 M35.04 M43.79 M28 mo.
7
Republic of the Philippines DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS 2.5km Oton CONSTRICTED PORTION FROM MOHON TO MAMBUG OTON Mohon Arevalo Lambuyao Culvert Mohon Bridge San Nicolas Oton San Antonio Oton Mambug Oton
8
Republic of the Philippines DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS Oton DUNGON CREEK IMPROVEMENT (Dredging and Excavation) LAPAZ MANDURRIAO JARO City Proper Molo Arevalo 4.59 Km Unworkable Area Due to presence of Formal and Informal Settlers and Mangrove Vegetation Cuartero Jaro Bolilao Br. Mandurriao Sta Rosa Mandurriao
9
Republic of the Philippines DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS Oton CALAJUNAN CREEK IMPROVEMENT (Dredging and Excavation) LAPAZ MANDURRIAO JARO City Proper Molo Arevalo 5.40 Km Calajunan Mandurriao
10
Republic of the Philippines DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS REGION VI – WESTERN VISAYAS