ATLAS Endcap Muon System WBS 3.5 Frank Taylor MIT M&O Request FY06 Toronto August 3, 2005 V1.1
2
F. E. Taylor - ATLAS Muon System Toronto 3-Aug-05, 2005 2 U.S. Muon Schedule V7.03 Sequence: EIL4-13 EIL4-A&C BW-C SW-A SW-C BW-A
3
F. E. Taylor - ATLAS Muon System Toronto 3-Aug-05, 2005 3 Status-I 30-July-05 MDT Chambers – EIL4+SW+BW complete Phase I Commissioning of all 240 chambers @ CERN complete complete All on-chamber electronics complete Available personnel have largely moved to CERN CSC Chambers – SW 14 of 32 passed Phase I Commissioning @ BNL complete All on-chamber electronics complete Off-chamber RoD & Transition Modules in prototype Will not be finished by CD4A but will be ready for installation Alignment – EIL4+SW+BW+EO complete All in-plane components complete complete All components for alignment bars complete Expect EIL4/BW/SW parts complete by CD4A Except – CSC on-chamber parts (not part of Appendix 3) EO parts will be completed before V7.03 need date
4
F. E. Taylor - ATLAS Muon System Toronto 3-Aug-05, 2005 4 Status-II 30-July-05 -Ready Chamber installation tooling-Ready TIS certified Chamber ‘Verticalizer’, ‘Grabber’ & ‘Wisconsin’ tool TIS certified -Started BW Installation B180-Started Last BT moved from B180 to Point 1 on 29-July-05 Competition for space reduced but share B180 with TGC & ECT BW-Large Sector tooling setup in B180 BW-Sector 9C vertical BW-Small Sector tooling delivered to CERN Except A-frame that will be needed later Remaining BW sector parts delivery Aug. through Nov. from Russia Project tracking difficult -Started EIL4 Installation B180-Started Work area setup in B180 and is operational EIL4-13A installed on frame & integrated with TGCs in B180 SW Installation B191-To Start early 2006 after ECT Assembly SWA & SWC are at CERN Were pre-assembled at Hatehof in Israel
5
F. E. Taylor - ATLAS Muon System Toronto 3-Aug-05, 2005 5 M&O-Installation Locations & Phases MDT Test Station BMC, UM, UW CERN - Bld 184 CSC Test Station BNL - 832 Alignment System Test Station CERN - Bld 180 Commission Big Wheel [BW] Sectors CERN - Bld 180, 185 Commission Small Wheel [SW] CERN - Bld 191 Phase II CY 04 - 06 Phase I CY 04 - 05 Phase III CY 05 - 07 ATLAS UX15 Beam On - CY-07 Installation on Support Structures Complete Partially Complete Started B184 CERN
6
F. E. Taylor - ATLAS Muon System Toronto 3-Aug-05, 2005 6 Installation Pictures Chamber Handling Tooling Installation of 1 st Alignment Bar in Sector 9C BW-L Tooling & Sector 9C EIL4 Work Area in B180 EIL4 A13 TGC+MDT BW Sector 9C @ B180 SW @ Hatehof
7
F. E. Taylor - ATLAS Muon System Toronto 3-Aug-05, 2005 7 Plans for FY06 MDT Chambers Production installation of EIL4 chambers (Operation 1) 16 chambers – 4 are special in Sectors 1 & 9 All 16 installed in UX15 by 15-March-06 Production installation of BW-L & BW-S chambers (Operations 2&3) 16 BW-C Sectors (5 MDT each) by 30-Jan-06 Continue BW-A Sectors finish by Dec-06 Set up SW area in B191 – start by 15-Jan-06 Production installation of EI MDTs on SWs (Operations 4&5) All EI MDTs (64) installed by ~ Oct-06 (Start ASAP – dependent on ECTs) CSC Chambers Ship all CSCs to CERN after Phase I finished @ BNL ~ Oct-05 Setup CSC test area in B184 ~ Nov-Dec-05 Integrate CSCs with support frames & alignment components Installation of CSCs in SWs (Operations 4’&5’) Finish by Oct-06
8
F. E. Taylor - ATLAS Muon System Toronto 3-Aug-05, 2005 8 US Muon Operations in B180 BW-S (O3) EIL4 (O1) BW-L (O2) Small Wheel in B191 O(4&5)
9
F. E. Taylor - ATLAS Muon System Toronto 3-Aug-05, 2005 9 3.5 Budget Profile-Baseline Possible call on Management Reserve FY06,7,8 Phase II & III – Integration & Commissioning in UX15
10
F. E. Taylor - ATLAS Muon System Toronto 3-Aug-05, 2005 10 3.5 Labor Plans-Baseline
11
F. E. Taylor - ATLAS Muon System Toronto 3-Aug-05, 2005 11 Installation Baseline Some carryover expected FY05->FY06 but unknown at this time
12
F. E. Taylor - ATLAS Muon System Toronto 3-Aug-05, 2005 12 FY06 M&O Request Solicited M&O requirements from the 10 Muon Institutes Replies from all 10 received 1 st round of budget scrubbing of requests while trying to maintain essential technical staff support Sum I+M&O = 2,278 Sum M&O = 1,895
13
F. E. Taylor - ATLAS Muon System Toronto 3-Aug-05, 2005 13 M&O Resource Levels Analysis of Jan-05 still holds: Requirements for FY05, 06 & 07 estimated to be roughly same level FY05 M&O Budget 1,887k FY06 M&O Request after PM scrubbing 1,895k Installation in FY06 budget baseline 383k
14
F. E. Taylor - ATLAS Muon System Toronto 3-Aug-05, 2005 14 Management Reserve Anticipate a call on MR ~ $354k in FY06 Scheduled work delayed but end-date fixed BW and SW installations and commissioning will have significant overlap Expect roughly constant M&O resources needed FY05-FY07. During FY06 work will focus on EIL4 & BW and later on SW installation and commissioning in B180 & B191, respectively Installation and commissioning of EIL4-A13 and 1 st BW-L sector should provide a calibration of time & manpower needed Priority for call for MR funding Essential technical & engineering staff @ CERN for installation & commissioning
15
F. E. Taylor - ATLAS Muon System Toronto 3-Aug-05, 2005 15 Summary Many items completed on the CD4A list However significant effort in the US remains until the end of FY05 that has impacted concentrated effort @ CERN Delays BW Installation & Commissioning B180 occupancy, delivery of BW frames & tooling Because Installation in UX15 is fixed, more work will have to be performed in parallel EIL4, BW and SW installation work will overlap in CY06 5 ‘Operations’ simultaneously conducted Share manpower, share tooling, logistical overhead M&O resources will have to support this compressed schedule