Hutch Neilson Princeton Plasma Physics Laboratory K-DEMO Project Meeting 26 June 2013 NFRI-PPPL K-DEMO Project Status and Plans Overview
2
Goals for This Meeting 2 K-DEMO Project Meeting / 26 June 2013 / H. Neilson 1.Updates of operating space, device modeling, structural analyses, blankets and divertor designs. 2.Plans for wrapping up Phase I, and planning for Phase II.
3
Phase I Milestones & Deliverables 3 K-DEMO Project Meeting / 26 June 2013 / H. Neilson Plan (from Nov. 2012 Project Meeting at PPPL): Jan 1, 2013 Start date. Jan. 23, 2013. MT-23 Abstract deadline. Feb. 1, 2013. SOFE-2013 Abstract deadline. Feb. 20-22. Presentation of prelim. TF winding including joint and leads. Feb. 28, 2013 Milestone: Update Design Point and “freeze” for remainder of 2013. (Further updates in the following year are anticipated.) Feb. 28, 2013 Deliverable: A picture of the device including TF, PF, Coil Structure, supported by preliminary analysis. Initial TF structural analysis- This meeting June 10-14, 2013. Several presentations at SOFE-2013, San Francisco July 14-19, 2013 Presentation at MT-23 Conference, Boston July, 2013. Report of progress in Phase I contract performance period. Aug. 2013. Start of Phase II contract performance period Feb 28, 2014. Report of progress in Phase II contract performance period.
4
PPPL Contract Accomplishments in Phase I 4 K-DEMO Project Meeting / 26 June 2013 / H. Neilson Contributions to initial design point selection, e.g., –System code performance analysis –Machine configuration model, based on PPPL AT Pilot Plant –PF coil configuration –Machine picture (shown several times at SOFE-2013) Analyses –Operating space –Structural –Superconductor Papers –C. E. Kessel, et al., “Systems Analysis Exploration of Operating Points for the Korean Demo Program,” SOFE-2013. –T. Brown, et al., “Progress in Developing the K-DEMO Device Configuration,” SOFE- 2013. –K. Kim, et al., “A Preliminary Conceptual Design Study For Korean Fusion DEMO Reactor Magnets,” SOFE-2103 –G. S. Lee, et al., “Korean Fusion Roadmap: K-Demo Design and R&D Plan,” SOFE- 2013. –Y. Zhai, et al., “Performance evaluation of K-DEMO cable-in-conduit conductors using the Florida electro-mechanical cable model,” MT-23.
5
Phase I Records & Documentation 5 K-DEMO Project Meeting / 26 June 2013 / H. Neilson Meeting files and summaries (3 teleconference, 2 “live”): http://advprojects.pppl.gov/Adv_Design/K_DEMO/K-DEMO_meetings.html http://advprojects.pppl.gov/Adv_Design/K_DEMO/K-DEMO_meetings.html SOFE-2013 and MT-23 papers and presentation files. Summary report to NFRI (by 31 July)
6
PPPL Phase II Statement of Work - 1 6 K-DEMO Project Meeting / 26 June 2013 / H. Neilson
7
PPPL Phase II Statement of Work - 2 7 K-DEMO Project Meeting / 26 June 2013 / H. Neilson
8
Schedule & Budget 8 K-DEMO Project Meeting / 26 June 2013 / H. Neilson Budget required: $100k Final report from PPPL: contributions to K-DEMO CSR, draft due 28 Feb. 2014.
9
Plans 9 K-DEMO Project Meeting / 26 June 2013 / H. Neilson Complete administrative reviews of Phase II Research Agreement, and sign. Issue final Phase I report to NFRI within by 31 Aug. Content as discussed at 26 June meeting. Including CD, and substantial report, 3 paper copies. (H. Neilson) Next Meeting: teleconference, August 27-28. –Establish milestones for Phase II.