Redevelopment Grant Program Implementation Workshop Spring 2010
2
Overview Introductions Purpose Agenda –Grant Agreements –Payment Requests –Annual Reports –Monitoring and Closeout
3
Grant Agreements Emailed after receipt of legal description for public portion of project Should be signed and returned in a timely manner Signatures should match authorized parties from resolution submitted with application Examine your budget – it may be different from your application Note all requirements from grant agreement
4
Grant Agreement - Requirements Matching funds requirement –At least 50% match Annual report due date - July 25 Contract start date and term end date –Eligible costs incurred up to 1 year prior to application date can be match –Redevelopment work must begin by start date listed in grant agreement –Private financing must be in place by December 31, 2010
5
Grant Agreement - Requirements Note Section 6.04 Requirements –Recorded Declaration Publicly owned and used for a public purpose in perpetuity –Certified each year in annual report Other general requirements, check with your legal counsel
6
Grant Agreements - Amendments Increase in grant amount –Supplemental award Change in term end date –Extenuating circumstances only Contract language changes
7
Grant Agreements – Adjustments (GAN) Change in budget line item (notify DEED of any significant monetary changes) Reverting unspent funds Change in grant status
8
Grant Agreements – Status Awarded Closed Pending ___________ Closed Pending Development Closed
9
Payment Requests
10
Column 1 Column 2 Column 3 Column 4 Approved Eligible Activities from Grant Agreement (GA) Approved Costs from Grant Agreement Total Eligible Invoices This Draw = 100% DEED Payment Request This Draw ____% Local Match This Draw ____% $ - TOTALS $ - = + ^ ^ ^ ^ If the line items in your Project Budget have changed, call your Rep before submitting this form. Amount should equal the total of all invoices attached to this Payment Request This total amount should reflect DEED's pro-rata share of approved costs This total amount should reflect the Grantee's pro- rata share of approved costs.
11
Payment Requests Column 5Column 6Column 7 Column 8Column 9Column 10 Column 11 Previous Payment Request Information Totals of Previous & Current Draws Remainder Previous DEED Payments To Date Previous Local Match Payments To Date Total Previous Paid To Date DEED Requests: Previous & Current Local Match Amounts: Previous & Current Total of All Previous & Current Funds Remaining Unspent Balance of Project Costs $ - + = $ - Total amount you have previously drawn from DEED. Total amount you have previously paid out of all other local sources. This amount should equal total Amounts from Columns 5 & 6 This amount should equal total Amounts from Columns 3 & 5 This amount should equal total Amounts from Columns 4 & 6 This amount should equal total Amounts from Columns 8 & 9 This amount should subtract Amounts in Columns 10 from Column 1
12
Payment Requests – Eligible costs Eligible costs are the activities listed in the approved budget of the grant agreement Eligible costs incurred within one year prior to application date can be included as match only Eligible costs incurred after award date can be paid with grant funds
13
Payment Requests –Ineligible Costs Meals, excessive travel, hotel, incidentals Program administration costs “In-Kind” costs Landscaping (seeding, sod, trees, etc.) Development-related costs Costs not supported by invoices Costs incurred on private land
14
Payment Requests – Supporting Invoices Provide an outline of invoices that reflects budgeted line items with subtotals. Include subcontractor invoices Invoices must show dates that work was completed Notify DEED of any significant monetary changes in budgeted line item(s)
15
Payment Requests Send requests to your project manager to expedite payment Payments are made on a 2 week schedule Payments are generally wired within a week of processing (once approved)
16
Annual Reports Purpose –Legislative requirements Must be signed (certified) by Grantee Due July 25, annually Level of project completion dictates which sections of the report need submission Report is simple, should not take too long
17
Annual Reports
22
Submit until final development is complete and all final job, tax, and other benefits are reported
23
Monitoring and Closeout When does DEED monitor a project? Who is involved in a monitoring visit? What is inspected at a monitoring visit? –Grant Management –Financial Management –Project Progress
24
Monitoring and Closeout – Grant Management All correspondence relating to the grant must be on file, such as –Grant agreements and GANs –Annual Reports –Other pertinent documents and reports Files should be well organized
25
Monitoring and Closeout – Financial Management Pay Request and backup documentation should be on file Final budget numbers with sources identified Tracking of all revenues and expenditures Match requirements met Approval/financial management process
26
Monitoring and Closeout – Project Progress Status of project and final development –Final jobs and other benefits #s if not previously reported Site visit
27
Monitoring and Closeout Reports are submitted to Grantee within 45 days of monitoring visit Negative findings may be issued, immediate response required Reporting requirements remain in effect until project is closed Grantee files must remain available for 6 years after file is closed
28
General Grant Management Project team: DEED as partner Keep appropriate DEED staff informed throughout the project of any changes –Project schedule –Development changes –Budget changes –other
29
Questions?