1
Alignment (results by Jo van den Brand) Preparing IP 8 Velo arrived at IP 8 Preparing UXA C3 Installation transfer lines for the cooling system Next steps Frans Mul 31 May 2006
2
Drilling holes for the LV - boxes Drilling holes for the service platform Preparing skates Preparing IP 8 Preparing the false floor Frans Mul 31 May 2006
3
Velo arrived at IP 8 In the air On the road Frans Mul 31 May 2006
4
All pictures http://www.nikhef.nl/~fmul/velo/Velo_May 19, 2006, 3:25:56 PM/ Pushing the last meters Velo at IP8 Frans Mul 31 May 2006
5
Preparing UXA C3 Luc, Piet and Jaap started May 29 th cabling the racks. Frans Mul 31 May 2006
6
On the corner Installation transfer lines for the cooling system at IP8 Frans Mul 31 May 2006
7
Next steps: Velo Alignment at IP8 Installation Velo vacuum system Cabling at IP 8 Installation service platform Velo overall test before installation exit window! Frans Mul 31 May 2006