Project Scheduling Tools. There are four possible sequencing modes in MS Project. Suppose B follows A. FS: Finish Start – Start B after A is completed.

Similar presentations


Presentation on theme: "Project Scheduling Tools. There are four possible sequencing modes in MS Project. Suppose B follows A. FS: Finish Start – Start B after A is completed."— Presentation transcript:

1 Project Scheduling Tools

2 There are four possible sequencing modes in MS Project. Suppose B follows A. FS: Finish Start – Start B after A is completed SS: Start Start – Start A and B at same time FF: Finish Finish – Finish A and B at same time SF: Start Finish – Start A after B is completed Lags are delays between work on activities 1. Sequencing

3 FS Sequence - Traditional A B E.g. Sand and Paint A BLag E.g. Sprinklers and Landscape

4 SS Sequence A B E.g. Plant Lawn and Flowers A BLag E.g. Drywall: Hang and Tape

5 FF Sequence A B E.g. Olympics A B Lag E.g. Olympics

6 SF Sequence A B E.g. Not Practical A B Lag E.g. Ocean Cruise

7 2. Activity Uncertainty PERT assumptions (Richard Schonberger and Ken Mac Crimmon) Beta distribution assumption PERT approximation formula for mean and variance Estimates of a, m, and b Errors of above up to 30%, but tend to cancel Worse problem is merge event bias (probability near-critical path becomes critical) – estimates consistently optimistic

8 Example 2.1 A,1 C,3 D,1 B,2 Critical path is ACD but ABD is near critical. Criticality index: probability path critical.

9 Use Simulation or Monte Carlo Analysis Generate random numbers (electronic, formulas, tables, books) i.e. 28 Convert to random probabilities i.e..28 What is probability of probability? Convert random probability to random variate. Follows distribution of say actual activity time.

10 Finding Random Variates, Problem 2.1 BCPMF CDF Mean – 112.3.3 Mean23.4.7 Mean + 134.2.9 Mean + 245.1 1.0 Random probability of.28 gives B random variate of 1;.46 gives C value of 3.

11 Simulation of Problem 2.1 RN B(2) RN C(3)LengthPath.28 1.463 5ACD.97 4.092 6ABD.63 2.333 5ACD.53 2.764 6ACD.73 3.005 7ACD Expected length = 5.8> 5 (merge event bias) Criticality index of ACD = 0.8 or 80%

12 Project Simulation Simulation includes GERT – Graphical Evaluation and Review Technique Crystal Ball – Copy comes with text Simulation includes Probabilistic branching from node – B may follow A Probabilistic times for activities – various distributions Flexibility in node realization – activity time can = 0 Looping permitted – rework Critique of Simulation – R. Schonberger recommends intensive critical path scrutiny

13 3. Limited Resource Scheduling Resources include labor, material, equipment, space, and money Money versus time tradeoffs Methods Crashing – How to shorten activities – cost penalties Resource loading – amount of resource needed per period. Resource leveling or balancing – evening out resource use, reacting to limited resources Simulation programs can help level

14


Download ppt "Project Scheduling Tools. There are four possible sequencing modes in MS Project. Suppose B follows A. FS: Finish Start – Start B after A is completed."