EE/CS 480 Fall 2007 1September, 2007 University of Portland School of Engineering Project Puffins Complex Multivariable Keypad Input Chip Team RuthAnn Gobble Jordan Way Jonathan Wong Advisor Dr. Aziz Inan, Dr. Peter Osterberg Industry Representative Mr. Wes Mickanin October
2
EE/CS 480 Fall 2007 2September, 2007 University of Portland School of Engineering Overview Introduction Scorecard Additional Accomplishments Plans Issues/Concerns Conclusions October
3
EE/CS 480 Fall 2007 3September, 2007 University of Portland School of Engineering Project Puffin will increase security of PIN input devices by exponentially increasing the number of possible PIN combinations. This is done through its use of chorded, synchronous inputs. This will benefit users of ATM’s and other Point of Sale (POS) devices by improving security while increasing pin combinations. Introduction
4
EE/CS 480 Fall 2007 4September, 2007 University of Portland School of Engineering Scorecard Previous month’s plans –Complete version 1.0 of Functional Specs –Have design functional in B2logic –Incorporate possible additions to design Card Reader Auto-lock after x number of incorrect attempts –Complete Project Plan 0.9 Shortcomings –Get Industry Rep to OK our Functional Specs October
5
EE/CS 480 Fall 2007 5September, 2007 University of Portland School of Engineering Additional Accomplishments Circuit Debugged and Imported into LEDIT October
6
EE/CS 480 Fall 2007 6September, 2007 University of Portland School of Engineering Plans List your team’s plans for next month –Complete version 1.0 of Project Plan –Submit Circuit design to MOSIS –Decide on keypad –Get Functional Specifications Approved October
7
EE/CS 480 Fall 2007 7September, 2007 University of Portland School of Engineering Milestones NumberDescriptionOriginal 8/28/07 Previous 8/28/07 Present 9/25/07 1Project Approval9/11/07 2Functional Spec 1.010/05/07 3Project Plan 1.011/09/07 4Funding Approval11/09/07 5Design Review11/30/07 October
8
EE/CS 480 Fall 2007 8September, 2007 University of Portland School of Engineering Concerns/Issues Finding a compatible Keypad –Non-Matrix Keypad required –Separate bus for each key Solutions –Create our own using button switches Not as professional looking, but still adequately displays the potential of our circuit in our MOSIS chip. October
9
EE/CS 480 Fall 2007 9September, 2007 University of Portland School of Engineering Conclusion Introduction Scorecard Additional Accomplishments Plans Issues/Concerns Conclusion October