Subgrade Soil Support and Stabilization
O’HARE Airport Modernization Research Project Co-PIs: Erol Tutumluer Marshall R. Thompson RA: H.S. Brar
2
Introduction Subgrade performance is a key factor in the overall pavement performance P154 P209 National Airport Pavement Test Facility - Atlantic City, NJ Persistence length is the length which the polymer looks like straight. -e : one negative charge This project provides testing and analysis to establish subgrade support and stabilization requirements for O’Hare airport pavements
3
Introduction (cont’d)
The preliminary concrete pavement design for the O’Hare Modernization Program (OMP): 15 – 17 inches of PCC Surface 6-inch Hot Mix Asphalt Base 6-inch Asphalt Treated Permeable Base (!?) “Stabilized” Subgrade Zone (SSZ) Prepared Subgrade North Runway (9L-27R, 7,500 ft) paving is scheduled first for the Spring 2006 (!?) Stockpiles of local soil on runway centerline (excavated from the “Deep Pond” nearby) Primarily fill and cut areas Persistence length is the length which the polymer looks like straight. -e : one negative charge
4
Research Objectives Consider pavement design inputs for subgrade support Modulus of subgrade reaction, k Consider subgrade support and stabilization requirements with respect to: Need for subgrade stabilization Stabilization admixture(s) stabilization Stabilization depth Estimate “subgrade support” for various combinations of subgrade stabilization treatments and prepared subgrade conditions Persistence length is the length which the polymer looks like straight. -e : one negative charge
5
Project Tasks Task 1: Establish the Best Demonstrated Available Technology (BDAT) for subgrade soil evaluation and stabilization (Ongoing) Reports and publications collected & submitted as “Technical Notes” on: Subgrade strength/stiffness evaluation techniques Subgrade stability requirements & IDOT Manual “Working platform” requirements for pavement construction Persistence length is the length which the polymer looks like straight. -e : one negative charge
6
Project Tasks Task 2: Evaluate currently available data for the subgrade test sections constructed in the Fall of 2003 and the necessity/usefulness of constructing additional subgrade treatment test sections at O’Hare (Effort completed) Plate load tests conducted (8/04) on the test sections: Plate 1: 12-inch stabilization/compaction – no admixture Plate 2: 12-inch quicklime fine (40 lb/yd2) & fly ash (80 lb/yd2) stabilization Plate 3: 12-inch quicklime fine stabilization (40 lb/yd2) Plate 4: 12-inch lime kiln dust stabilization (40 lb/yd2) Persistence length is the length which the polymer looks like straight. -e : one negative charge
7
Modulus of Subgrade Reaction, k
Plate Load Tests Persistence length is the length which the polymer looks like straight. -e : one negative charge Modulus of Subgrade Reaction, k
8
Project Tasks Task 3: Advise OMP on current and future test section monitoring and field test evaluation programs (Effort completed) Various field tests may be useful to characterize the treated subgrade (OMP will arrange for testing): Dynamic Cone Penetrometer (8/04) Light-Weight Deflectometer (8/04) Clegg Hammer Geogauge Heavy Weight Deflectometer (HWD) Ground Penetrating Radar (GPR) Seismic Pavement Analyzer, SASW, etc. Persistence length is the length which the polymer looks like straight. -e : one negative charge
9
Dynamic Cone Penetrometer
Light-Weight Deflectometer Persistence length is the length which the polymer looks like straight. -e : one negative charge
10
Project Tasks Task 4: Evaluate currently available geotechnical/subgrade data for the North Runway with emphasis on the stockpiled “Deep Pond” soils. Recommend further soil sampling & testing to be conducted (by an OMP designated testing firm) (Ongoing) Routine tests to establish representative soils existing for the runway subgrade Grain size distribution (including hydrometer) Atterberg limits (LL and PL for PI) Moisture-density-CBR PH value & calcareous content If needed, organic matter content Persistence length is the length which the polymer looks like straight. -e : one negative charge
11
Preliminary Geotechnical Report
Soil sampling & testing conducted by Everest Engineering on OMP Runway 9L-27R - October 2004 Atterberg limits (LL and PL for PI) Persistence length is the length which the polymer looks like straight. -e : one negative charge Boring Logs
12
Preliminary Geotechnical Report
Soil sampling & testing conducted by Everest Engineering on OMP Runway 9L-27R - October 2004 Grain size distribution (including hydrometer) Persistence length is the length which the polymer looks like straight. -e : one negative charge
13
Preliminary Geotechnical Report
Soil sampling & testing conducted by Everest Engineering on OMP Runway 9L-27R - October 2004 Moisture-density-CBR Persistence length is the length which the polymer looks like straight. -e : one negative charge
14
Preliminary Geotechnical Report
Soil sampling & testing conducted by Everest Engineering on OMP Runway 9L-27R - October 2004 Persistence length is the length which the polymer looks like straight. -e : one negative charge Unconfined Compressive Strength, Qu
15
Soil Sampling: Dec. 04 – Feb. 05
Current scheduled soil sampling & testing from the R9L-27R The Drilling Program Auger borings, 17 boreholes, MT-1 to MT-17 10’ to 45’ depths through fill & cut areas All reaching down to elev. 640’ in the natural subgrade 3 North of runway, 3 North edge of runway, 4 under runway, 2 South edge of runway, 2 between runway and taxiway, and 3 under taxiway SPT and soil sampling at 2.5’ Moisture content, LL, PI, grain size distribution (%clay) Shelby tube samples at each location (638’ to 642’) At least 1 bucket for each major soil in each borehole Two 5-gallon buckets (60-70 lbs./bucket) for each representative soil (composite sample) to test at the University of Illinois
16
Soil Sampling: Dec. 04 – Feb. 05
University of Illinois input/review – The Drilling Program Laboratory Testing Needs Check the pH of the soil samples Check the samples for “free carbonates” by squirting with 10% HCl solution How are the SPT samples handled? “N” counts will be helpful in assessing the mobility characteristics (sinkage/rolling resistance) of the stockpiled soils What tests are conducted with the Shelby tube samples? Undisturbed samples obtained from the natural subgrade (finished subgrade elevation) will be best utilized to run unconfined compressive strength and resilient modulus tests
17
Project Tasks Task 5: Based on the data and information gathered in Task 4, select (in consultation with OMP) the identified representative soils and recommend an admixture stabilization program (Ongoing) Tests to be conducted at the UIUC Advanced Transportation Research and Engineering Laboratory (ATREL) on both untreated & treated soils Moisture-Density-CBR Unconfined Compressive Strength Resilient Modulus Permanent 6-psi deviator stress Persistence length is the length which the polymer looks like straight. -e : one negative charge
18
Project Challenges Proper sampling of the R9L-27R stockpiled soils
Selecting & identifying representative soil samples Adequately characterizing the representative soil samples by conducting tests at the UIUC ATREL for Moisture-Density-CBR Unconfined Compressive Strength Resilient Modulus Permanent 6-psi deviator stress Persistence length is the length which the polymer looks like straight. -e : one negative charge
19
University of Illinois Laboratory Testing Program at ATREL
Advanced Transportation Research & Engineering Laboratory (ATREL)
20
Admixture Types / Sources
Carmeuse (potential supplier) South Chicago (dolomitic lime) Buffington, IN (high calcium lime) Lime types Lime Kiln Dust (LKD) Quicklime fines Buffington is the primary source (We will work with this & confirm with S. Chicago)
21
Proctor Compaction (ASTM D698, D1557)
Moisture- Density- CBR CBR (ASTM D1883) Untreated Proctor Compaction (ASTM D698, D1557)
22
Moisture-Density-CBR
Lime treated Lime treated
23
Moisture-Density-CBR
Treated LKD: Lime Kiln Dust
24
Unconfined Compressive Strength
sd = s1 – s3(=0) failure C = (s1f)/2 = Qu/2 s3 = 0 s1 s1f s Cohesive Soils (c, f=0) (ASTM D2166)
25
Typical Unconfined s-e Data
60 Dupont Clay MC = 23 % 50 DD = pcf CBR = 14 Qu = unconfined compressive strength = peak s1 10 20 30 40 MC = 26 % DD = 98 pcf CBR = 8 Axial Stress, psi MC = 28.5 % DD = 93.5 pcf CBR = 4 MC = 30.5 % DD = 92.5 pcf CBR = 2.5 5 10 15 Axial Strain, %
26
Deviator Stress at Failure
27
Deviator Stress at Failure
Effect of Curing
28
Resilient Modulus Testing sd
Unconfined: s3 = 0 2-in. in f MR = resilient modulus = sd / er sd : Deviator stress er : recoverable strain Conditioning: 200 load applications at s3 = 0, sd = 41 kPa Testing: 100 load applications sd = 14, 28, 41, 55, 69, 83, 96, 110 kPa
29
MR Tests – Soil Samples Cylindrical specimens, 2 in. f by 4 in. high
Undisturbed soil samples – Shelby tube (f = 2.8, 4 in.)
30
Typical MR Characterization
Greensboro, NC Airport Subgrade Soils 28 M R = s d 2 = 24 A-4 soil at OMC RESILIENT MODULUS M R (ksi) A-4 soil at OMC+3 20 Bilinear or Arithmetic Model 16 M = s + 1820 R d 2 12 R = 8 4 M = s R d M = s R d R 2 = R 2 = 2 4 6 8 10 12 14 16 18 APPLIED DEVIATOR STRESS s (psi) d
31
Resilient Modulus Testing
32
Resilient Modulus Testing
33
Resilient Modulus Testing
34
Project Deliverables Technical Notes have been / will be prepared and submitted to the OMP throughout the project duration to communicate specific findings and recommendations to OMP engineers Several of the Project Tasks are being pursued simultaneously, and the specific delivery of results will be contingent upon availability of OMP data and other factors that depend on coordination with OMP A Report summarizing the laboratory program will be prepared A Final Report will be prepared at the end of the one-year study (September/October 2005) We will continue to work with OMP on future subgrade soil support and stabilization needs for other runways/taxiways Persistence length is the length which the polymer looks like straight. -e : one negative charge
35
Illini Apparently Have Spent A Little Longer At No. 1 This Time!..
GO ILLINI !..