Hall C Meeting SHMS Magnets and Support Structure Design and Procurement Status Paul Brindza January 26, 2009
2
SHMS Magnets and Support Structure SHMS Spectrometer and Magnets SC Magnet Procurement Status SHMS Magnet Recent Progress SHMS Support Structure Conclusions
3
SHMS TargetBenderQ1Q2Q3DipoleDetectors Electronics Room Cryo Transfer Line Power Supplies Shield House
4
SHMS Q1 Quadrupole Assembly JLAB Cold Iron Quad Design (CIQ) SHMS Horizontal Bend Dipole Warm Iron SC “C” Magnet SHMS Q3 Cosine 2Θ Quadrupole Assembly 60 cm warm bore cryo-stable design SHMS Cosine Θ Dipole Assembly 60 cm warm bore- cryo-stable design
5
Bo/GoApertureJ A/cm^2 Design HB3.10 T35 x 3628,900“C” Type Super Ferric Q110.6 T/m 40 cm23,430JLAB Q1 Cold Iron Q2314.4 T/m 60 cm 5,800 Cosine (2 Θ ) Dip4.76 T 60 cm 5,000Cosine (Θ) SHMS Magnet Designs
6
I (A)L (H)E (MJ)Wt. HB45000.0290.290 3.9 t Q136300.1230.808 15 t Q2358550.63810.94 70 t Dip49401.6319.84163 t SHMS Magnets Stored Energy & Weight
7
SHMS Requirements from Optics and SC Magnet Design Margin MagnetOptics at 11GeV/c Design Maximum Design Margin HB dipole TM 1.9292.34517.7% Q1 Quad (T/M)M 14.75219.90525.9% Q2 Quad (T/M)M 19.42923.21016.3% Q3 Quad (T/M)M 12.91723.21044.3% Dipole TM 11.18913.59117.7%
8
SHMS SC Magnet Procurement Strategy SC Magnets will be built by contractors In a significant departure from HMS we will provide major SC magnet components – Superconductor (SSC surplus) – Cryo-Control Reservoir( same as HMS Design) – DC Power System( same as HMS) – Magnet Control System( Same as HMS) – Warm Yoke Steel
9
Cryogenic Control Reservoir Fabricated Cryostated Magnet RFP Fixed Price Procurement Conductor Processing Testing SC Cable DC Power System Magnet Control System Ship to JLAB On Site Integration & Assembly Acceptance Testing Magnet Support & Alignment Warm Iron Yoke SHMS SC Magnet System Plan
10
Procurement Status of SHMS Magnets Q1 Magnet bids under evaluation- don’t ask/don’t tell Q1 Award plan date is March 15, 2009 Q2Q3 & Dipole RFP released Jan 26, 2009 Q2Q3D Bids due May 2009, Award Dec. 2009 HB magnet design review Feb. 10, 2009 MOU/Contract with NSCL ~ June 2009
11
Horizontal Bend Design by NSCL/MSU Warm Iron SC “C” Magnet
12
HB Coil Drawing and 3D CAD of Winding Tooling
13
HB Coil Winding Tooling
14
1 st Full HB Coil – 90 Turns
15
Q1 Quad 3D CAD Model Cold Iron Quad Design like HMS Q1 Bids are IN!!
16
Q1 Coil winding at SMI
17
First Phase II Q1 Coil
18
Q1 Coil Tests
19
SHMS Support Structure
20
Mechanical Requirements SHMS Minimum Scattering Angle 5.5 degrees SHMS-HMS angle 5.5+12 = 17.5 degrees HMS Minimum Angle (present) 10.5 degrees SHMS Max angle 40 degrees HMS Max Angle(present ) 85 degrees Hall C Radius at SHMS max 73 feet Fit to beam pipe at 5.5 degrees ~ 5 mm Fit to HMS at 17.5 degrees ~ 1 cm
21
SHMS Support Structure Reference Design SHMS Support Structure Preliminary Design completed in 2007 by ALION, a local company with experience in large welded steel structures SHMS Support Structure Reference Design(RD) Completed by ALION January 28, 2009 RD will be the technical elements for the bid packages for the SHMS support structure. SHMS Support Structure RD review was held in December 08 at JLAB
22
SHMS General Arrangement
23
SHMS Support Cross Sections
24
SHMS Structure Preliminary Assembly Plan
25
Top View SHMS & HMS Spectrometers Bender Q1 Q2 Q3 Dipole Target Beamline HMS Spectrometer
26
Bottom View HMS SHMS Beamline stands SHMS wraps around front of HMS
27
Bender fit up to HMS Q1 Bender HMS Q1
28
Q3 & Dipole fit up Beamline Stand SHMS Q3 SHMS Dipole 24” Beamline Q2 Shield House notch
29
Shield House fit up Shield House Beamline Shield House notch Dipole Q3 Q2 Q1 Bender
30
Conclusions SHMS SC Magnet designs are sound, reviewed and procurement has started JLAB is a partner in the SHMS Magnet fabrication Superconductor, Cryogenic Interface, Iron Yokes DC systems and PLC based controls. SHMS Support Structure Reference Design is complete detail design and fabrication begins FY10 Since we haven’t spent a dime yet We are still On time and On budget!!