Download presentation
Presentation is loading. Please wait.
Published byDaisy Norman Modified over 9 years ago
1
ELTON CREEK, DS OF FREEDOM 7 BRIDGE, FREEDOM, NY. Bank erosion is threatening a farm road NRCS –Environmental Quality Incentives Program {EQIP} cost share with landowner Rural (farmland) Bed material: gravel-cobble-sand, incised Pool-riffle-pool regime, slope around 1% Average width 20-30 ft, 10-14 ft tall banks Partially spring fed. High-quality trout stream, not stocked, natural reproduction of Rainbow, Brown, & upstream, Brook Trout
2
ENTITIES INVOLVED NRCS – Area Office, Batavia, NY Cattaraugus County Soil & Water Conservation District, Ellicottville, NY U S Army Corps of Engineers, Engineering Research & Development Center, Vicksburg, MS. NRCS Cattaraugus County Office, Ellicottville, NY
3
THE FIRST SITE VISIT. JANUARY 10, 2007 PANNING US TO DS
4
Looking DS at right eroding bank & exit conditions. PRE-PROJECT-Elton Creek DS of Freedom 7 Bridge-derrick-Jan 10, 2007
5
THE SECOND SITE VISIT. MAY 17, 2007 PANNING US TO DS
6
Looking US at attack angle into eroding bank. PRE-PROJECT-Elton Creek DS of Freedom 7 Bridge-derrick-May 17, 2007
7
Looking US at eroded bank. Bob is 6 ft 4” (for scale). PRE-PROJECT-Elton Creek DS of Freedom 7 Bridge-derrick-May 17, 2007
8
Looking US at eroding bank. Truck on road we are protecting. PRE-PROJECT-Elton Creek DS of Freedom 7 Bridge-derrick-May 17, 2007
9
Looking US at eroding bank & large block failure. PRE-PROJECT-Elton Creek DS of Freedom 7 Bridge-derrick-May 17, 2007
10
Bank is 14 ft tall-toe is clay, gravel-cobble-sand above PRE-PROJECT-Elton Creek DS of Freedom 7 Bridge-derrick-May 17, 2007
11
THE PLAN
12
Drawing by Robert Shenk, Catt County Soil & Water THE PLAN – ELTON CREEK DS OF FREEDOM 7 BRIDGE Project Limits FLOW THE FARM ROAD WE ARE PROTECTING
13
Drawing by Robert Shenk, Catt County Soil & Water THE PLAN – ELTON CREEK DS OF FREEDOM 7 BRIDGE FLOW THE PLAN
14
CONSTRUCTION OCT. 9-12, 2007 CONSTRUCTION CONTRACT & STONE COSTS - APPROX. $16,000. TOTAL
15
Looking US at the constructed bypass channel. We plugged the channel, put all flow in the bypass channel, & worked in the dry during construction. Under construction-Elton Creek DS of Freedom 7 Bridge-derrick-Oct 2007
16
METHODS EMPLOYED 225 ft of self-adjusting & self-filtering Longitudinal Peaked Stone Toe Protection {LPSTP}. Mix of DOT heavy & medium graded stone. All protection is on right bank Curved & vegetated keys on US & DS ends, 1 vegged tieback & key in middle of project A stone check dam at DS end {not enuf stone for an Engineered Rocked Riffle} Boil-Up Pool with curved kicker (Smile) Five Single-Stone Bendway Weirs Many transplanted Streamco Willow shrubs Live Siltation, Pole Plantings, & Live Staking using Streamco & Black Willows, Red Osier & Silky Dogwoods 6 rooted-stock Red Osier Dogwood
17
WE WILL START DOWNSTREAM & WORK UPSTREAM, THEN DO THE GRADE CONTROL @ THE DS END LAST.
18
LONGITUDINAL PEAKED STONE TOE PROTECTION {LPSTP} {Self-adjusting & self-filtering, Longitudinal Peaked Stone Toe Protection. Consists of a mix of DOT “heavy” & “medium” graded stone}
19
Drawing by Robert Shenk, Catt County Soil & Water THE PLAN – ELTON CREEK DS OF FREEDOM 7 BRIDGE THE LONGITUDINAL PEAKED STONE TOE PROTECTION {LPSTP} FLOW DS key
20
Elton Creek near Freedom 7 Bridge, Freedom, NY Typical bank cross-section Farm road Right bank Left bank
21
Looking DS. Laying out the alignment for the LPSTP Construction-Elton Creek DS of Freedom 7-Steve Perschke-NRCS-Oct 07
22
Then place clay dug from thalweg channel at toe of eroding bank Elton Creek near Freedom 7 Bridge, Freedom, NY First pre- dig a thalweg channel
23
Looking DS. Laying out the DS key (red flags). Dug clay placed as substrate fill. Under construction-Elton Creek DS of Freedom 7 Bridge-derrick-Oct 2007
24
Install one-half of the Longitudinal Peaked Stone Toe Protection (LPSTP). Elton Creek near Freedom 7 Bridge, Freedom, NY
25
Install adventitious rooting Willow Poles Elton Creek near Freedom 7 Bridge, Freedom, NY
26
Install remainder of LPSTP. Side slopes will be at the angle of repose Elton Creek near Freedom 7 Bridge, Freedom, NY
27
The stream will adjust to the LPSTP, & the LPSTP will self-adjust to armor the resulting scour hole Toe scour
28
Elton Creek near Freedom 7 Bridge, Freedom, NY The LPSTP has self-adjusted
29
Elton Creek near Freedom 7 Bridge, Freedom, NY Install gravel- cobble from stream
30
Looking DS. Vegetation integrated thru LPSTP. Under construction-Elton Creek DS of Freedom 7 Bridge-derrick-Oct 2007
31
LIVE SILTATION {Willow branches about 1-2 inches in diameter, 6 to 8 ft long, 2/3 in ground, 1/3 out, intermixed with Silky & Red osier Dogwood that is 4 to 6 ft long}
32
Looking US. Dug trench landward of LPSTP. Under construction-Elton Creek DS of Freedom 7 Bridge-derrick-Oct 2007
33
Looking US at installed Live Siltation (willow & dogwood). Under construction-Elton Creek DS of Freedom 7 Bridge-derrick-Oct 2007
34
Looking US at Single Stone Bendway Weirs & veg 8 MONTHS LATER-Elton Cr. DS of Freedom 7 Br.-derrick-JUNE 13, 2008
35
TRANSPLANTING A LARGE CLUMP OF WILLOW Multi-stem (20 to 40 stems) bushes approx. 14 to 24 ft tall, transplanted as a single clump, with roots in trench directly behind the LPSTP. Tops of branches were trimmed & used as Live Poles (6 to 10 ft long).
36
Looking down bank at a dug trench in backfilled bank. Under construction-Elton Creek DS of Freedom 7 Bridge-derrick-Oct 2007
37
Elton Creek near Freedom 7 Bridge, Freedom, NY Dig trenches to receive willow bushes
38
Looking DS at LPSTP, backfilled bank, & dug trench. Under construction-Elton Creek DS of Freedom 7 Bridge-derrick-Oct 2007
39
Elton Creek near Freedom 7 Bridge, Freedom, NY Transplant large multi- stem Willow Bushes
40
Looking DS. Transplanting willow bush in trench Under construction-Elton Creek DS of Freedom 7 Bridge-derrick-Oct 2007
41
Elton Creek near Freedom 7 Bridge, Freedom, NY Then trim long branches from bush & plant as Willow Poles
42
Looking DS. Trim willow & plant poles in trench. Under construction-Elton Creek DS of Freedom 7 Bridge-derrick-Oct 2007
43
Elton Creek near Freedom 7 Bridge, Freedom, NY Water in & backfill
44
Looking DS. Covering willow bush & poles with soil Under construction-Elton Creek DS of Freedom 7 Bridge-derrick-Oct 2007
45
Looking DS. Transplant complete. Under construction-Elton Creek DS of Freedom 7 Bridge-derrick-Oct 2007
46
Drawing by Robert Shenk, Catt County Soil & Water THE PLAN – ELTON CREEK DS OF FREEDOM 7 BRIDGE WILLOW BUSH TRANSPLANTATION FLOW
47
Veg planted on a grid, Live Siltation in front & transplants Under construction-Elton Creek DS of Freedom 7 Bridge-derrick-Oct 2007 Live Siltation Willow shrub transplants & willow poles
48
19 MONTHS LATER-Elton Cr. DS of Freedom 7 Br.-Derrick-June. 9, 2009 1 full growing season and 2 more growing months after completion. From point bar looking @ right bank. This is the 50 ft of Live Siltation & two large willow bush transplants that took 45 minutes to install.
49
PLACING LPSTP IN THE US SECTION OF THE BEND {Self-adjusting & self-filtering, Longitudinal Peaked Stone Toe Protection {LPSTP}. Consists of a mix of DOT “heavy” & “medium” graded stone. }
50
Looking US @ smooth curve in impact area. Under construction-Elton Creek DS of Freedom 7 Bridge-derrick-Oct 2007
51
THE UPSTREAM KEY {Dig curved trench, place willow & dogwood poles on DS side, backfill with graded stone, water in, backfill with soil (overfill for settling), water in again, seed}
52
THE MID-PROJECT TIE-BACK & KEY {Dig straight trench perpendicular to high flow path, place willow & dogwood poles on US side (so that plants will be in compression against the stone during high flow events) backfill with graded stone, water in, backfill with soil (overfill for settling), water in again, seed}
53
Drawing by Robert Shenk, Catt County Soil & Water THE PLAN – ELTON CREEK DS OF FREEDOM 7 BRIDGE MID-PROJECT TIE-BACK & KEY FLOW
54
Looking downhill @ veg on US side of mid-project key. Under construction-Elton Creek DS of Freedom 7 Bridge-derrick-Oct 2007
55
Looking uphill @ key stone & veg. Soil choke next. Under construction-Elton Creek DS of Freedom 7 Bridge-derrick-Oct 2007
56
TRANSPLANTING SEVERAL LARGE MULTI- STEM WILLOW BUSHES IN THE HIGH-FLOW IMPACT ZONE Multi-stem bushes on 15 ft spacing with many Live Poles and Live Siltation (dense plantings on a grid)
57
Drawing by Robert Shenk, Catt County Soil & Water THE PLAN – ELTON CREEK DS OF FREEDOM 7 BRIDGE THE HIGH-FLOW IMPACT ZONE Impact flow
58
Drawing by Robert Shenk, Catt County Soil & Water THE PLAN – ELTON CREEK DS OF FREEDOM 7 BRIDGE WILLOW BUSHES Impact flow
59
Looking US at pre-dug trenches for transplants. Under construction-Elton Creek DS of Freedom 7 Bridge-derrick-Oct 2007
60
Looking US. Veg placed in trenches & watered in. Under construction-Elton Creek DS of Freedom 7 Bridge-derrick-Oct 2007
61
Transplants & poles so dense it is hard to see workers Under construction-Elton Creek DS of Freedom 7 Bridge-derrick-Oct 2007
62
Looking DS at LPSTP & Single Stone Bendway Weirs. Under construction-Elton Creek DS of Freedom 7 Bridge-derrick-Oct 2007
63
Looking across. Bob standing on stone check dam. The check dam controls the thalweg so that nothing is adversely affected downstream of the project. Under construction-Elton Creek DS of Freedom 7 Bridge-derrick-Oct 11, 2007
64
PROJECT CONSTRUCTED IN 3 WORKING DAYS, OCT 9-12, 2007
65
19 MONTHS AFTER CONSTRUCTION (1 full growing season & 2 more growing months after completion) Photos by Dave Derrick JUNE 9, 2009
66
1 growing season and 2 months after completion. Looking downhill @ the Live Siltation (mid-project). 19 MONTHS LATER - Elton Cr. DS of Freedom 7 Br.-Derrick-June. 9, 2009
67
Looking downhill @ one transplanted willow bush. 19 MONTHS LATER - Elton Cr. DS of Freedom 7 Br.-Derrick-June. 9, 2009
68
Looking DS at the bank with transplanted shrub and poles acting as a Living Dike (row of vegetation oriented perpendicular to the direction of high flow) 19 MONTHS LATER - Elton Cr. DS of Freedom 7 Br.-Derrick-June. 9, 2009
69
From top bank, upper end of project. Looking DS at the point bar, channel, LPSTP, & vegetated bank. 19 MONTHS LATER-Elton Cr. DS of Freedom 7 Br.-Derrick-June. 9, 2009
70
The next 16 pix are from in the channel, working from upstream to downstream.
71
From US of project, looking DS. Dead water US of Single Stone Rock Vane. 19 MONTHS LATER-Elton Cr. DS of Freedom 7 Br.-Derrick-June. 9, 2009
72
Looking DS @ LPSTP & upper bend with dead water US & DS of Single Stone Rock Vane. Taller stone protection & heavy veg since this is the “impact zone” of high velocity flow into the project. 19 MONTHS LATER-Elton Cr. DS of Freedom 7 Br.-Derrick-June. 9, 2009
73
Looking DS at the upper bend. Excellent veg (Live Siltation, 4 large willow bush transplants, & many live dogwood & willow poles) on mid & upper bank. 19 MONTHS LATER-Elton Cr. DS of Freedom 7 Br.-Derrick-June. 9, 2009
74
Looking DS at a correctly-shaped point bar. Philosophy on this project was to have the outer bank rough & strong & inner bank smooth & adjustable. 19 MONTHS LATER-Elton Cr. DS of Freedom 7 Br.-Derrick-June. 9, 2009
75
Looking DS at the project. Two deep pools (separated by the Boil-Up pool curved kicker) naturally dissipate stream energy. 19 MONTHS LATER-Elton Cr. DS of Freedom 7 Br.-Derrick-June. 9, 2009 Pool
76
Looking @ the US deep pool. Branches, leaves, & fine sediment on left bank side of pool. 19 MONTHS LATER-Elton Cr. DS of Freedom 7 Br.-Derrick-June. 9, 2009
77
Looking DS at the pool & vegetated bank. High flows on the bank will encounter deep-rooted robust veg. 19 MONTHS LATER-Elton Cr. DS of Freedom 7 Br.-Derrick-June. 9, 2009
78
Looking DS at the second deep pool, LPSTP, & Live Siltation bank veg. DS key veg is visible & robust. 19 MONTHS LATER-Elton Cr. DS of Freedom 7 Br.-Derrick-June. 9, 2009
79
From point bar looking @ right bank. This is the 50 ft of Live Siltation & two large willow bush transplants that took 45 minutes to install. Fantastic growth!! 19 MONTHS LATER-Elton Cr. DS of Freedom 7 Br.-Derrick-June. 9, 2009
80
Looking @ a Single Stone Bendway Weir. 19 MONTHS LATER-Elton Cr. DS of Freedom 7 Br.-Derrick-June. 9, 2009
81
Looking DS at robust Live Siltation & DS key veg at lower end of project. 19 MONTHS LATER-Elton Cr. DS of Freedom 7 Br.-Derrick-June. 9, 2009
82
Looking US @ two deep pools with the Boil-Up Pool curved kicker in between. Base flow thalweg trace in yellow. 19 MONTHS LATER-Elton Cr. DS of Freedom 7 Br.-Derrick-June. 9, 2009
83
Looking DS at exit flow over rock check dam. 19 MONTHS LATER-Elton Cr. DS of Freedom 7 Br.-Derrick-June. 9, 2009
84
Rock check dam at lower end is performing well. 19 MONTHS LATER-Elton Cr. DS of Freedom 7 Br.-Derrick-June. 9, 2009
85
Small gully on upper bank from overbank drainage @ DS end of project. Drainage has been re-routed. 19 MONTHS LATER-Elton Cr. DS of Freedom 7 Br.-Derrick-June. 9, 2009
86
From lower end looking US @ lush bank vegetation. Live Siltation & transplanted willow bushes on bank form a vegetated “grid” (woody veg. both parallel & perpendicular to direction of high flow). 19 MONTHS LATER-Elton Cr. DS of Freedom 7 Br.-Derrick-June. 9, 2009
87
This talk is over, time to relax Double trouble at rest
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.