Copyright 2009 John Wiley & Sons, Inc. Chapter 2 Strategic Management and Project Selection
2
Problems With Multiple Projects 1. Delays in one project delays others 2. Inefficient use of resources 3. Bottlenecks in resource availability
3
Project Results 30 Percent late Over half 190 percent over budget Over half 220 percent late
4
Challenges Making sure projects closely tied to goals and strategy How to handle growing number of projects How to make projects successful
5
Project Management Maturity Project management maturity refers to mastery of skills required to manage project competently Number of ways to measure Most organizations do not do well
6
Project Selection and Criteria of Choice Project selection… – Evaluating – Choosing – Implementing Same process as other business decisions
7
Types of Companies Companies considering projects fall into two broad categories: 1. Companies whose core business is completing projects 2. Companies whose core business is something else They can also be broken down as: 1. Companies looking at projects to do for others 2. Companies looking at projects to do for themselves
8
Project Companies Must select which projects they will bid on Generally based on… – Their expertise – Resource they have availability – Their chance of winning bid Preparing a bid is expensive They do not want to waste that effort on bids where they are unlikely to be successful
9
Non-Project Companies Must decide which potential projects they will pursue Available capital is the major constraint Profitability is often the major criteria Must evaluate approaches when there is more than one project that can accomplish a goal
10
Models Models are used to select projects All models simplify reality That is, they only look at the key variables involved in a decision The more variables included in a model, the more complex it becomes Simpler models usually work better
11
Types of Models Stochastic Model – A model that includes the probabilities of events occurring within the model. In other words, the same inputs might yield different outputs at different runs. Also known as a probabilistic model. Deterministic Model – A model that does not include probabilities. Given the same inputs, the outputs will always be the same.
12
Criteria For Project Selection Models Companies only want to undertake successful projects Projects that fail waste resources and hurt profitability and competitiveness Projects that succeed improve profitability and competitiveness It is not possible to know ahead of time if a project will succeed or fail In fact, there is a continuum of possible results from total success through absolute failure
13
Criteria (Continued) Companies need a way of weeding out the bad projects while keeping the good ones No model can predict with absolute certainty No model could predict – The Exxon Valdez wreck – The explosion of the Challenger What we want is a model with a “good batting average”
14
Model Criteria Realism Capability Flexibility Easy to use Inexpensive Easy to implement
15
Realism Needs to include all objectives of the firm Needs to include the firms expertise as well as its limitations Needs to report results in a fashion that allows different projects to be compared, e.g. how do we compare a project to lower production cost and one to raise market share
16
Capability Model needs to be sophisticated enough to deal with all projects – Varying resource requirements – Varying time periods – Varying probabilities of success Needs to be able to select the optimum projects among all contenders
17
Flexibility Needs to be able to work with all projects Needs to be updated as the firm and its environment evolves
18
Easy to Use Needs to be quick to gather the data and easy to use Easy to be able to “fit” the project in the model
19
Inexpensive Do not want the model to eat up all the savings that result from using the model Expenses include the cost of writing and maintaining the model Also includes the expense of gathering the data needed by the model
20
Easy to Implement This is less of an issue with modern spreadsheets However, a model to be used to evaluate all the firm’s projects should be centrally maintained
21
The Nature of Project Selection Models Models turn inputs into outputs Managers decide on the values for the inputs and evaluate the outputs The inputs never fully describe the situation The outputs never fully describe the expected results Models are tools Managers are the decision makers
22
Different Factors Affecting Outcome Many factors affect the outcome of a project – Some are one-time factors The cost of an item – Others are reoccurring Maintenance Not all factors are equally important Critical factors on one project may be trivial on another project
23
Types of Project Selection Models Nonnumeric models Numeric models
24
Nonnumeric Models Models that do not return a numeric value for a project that can be compared with other projects These are really not “models” but rather justifications for projects Just because they are not true models does not make them all “bad”
25
Types of Nonnumeric Models Sacred Cow – A project, often suggested by top management, that has taken on a life of its own. It continues, not due to any justification, but “just because.” Operating Necessity – A project that is required in order to protect lives or property or to keep the company in operation. Competitive Necessity – A project that is required in order to maintain the company’s position in the marketplace.
26
Types of Nonnumeric Models Continued Product Line Extension – Often, projects to expand a product line are evaluated on how well the new product meshes with the existing product line rather than on overall benefits. Comparative Benefit – Projects are subjectively rank ordered based on their perceived benefit to the company.
27
Numeric Models Models that return a numeric value for a project that can be easily compared with other projects Two major categories: 1. Profit/profitability 2. Scoring
28
Profit/Profitability Models Models that look at costs and revenues – Payback period – Discounted cash flow (NPV) – Internal rate of return (IRR) – Profitability index NPV and IRR are the more common
29
Payback Period The length of time until the original investment has been recouped by the project A shorter payback period is better
30
Payback Period Example
31
Payback Period Drawbacks 1. Does not consider time value of money 2. More difficult to use when cash flows change over time 3. Less meaningful over longer periods of time (due to time value of money)
32
Discounted Cash Flow The value of a stream of cash inflows and outflows in today’s dollars Also know as discounted cash flow or just discounting Widely used to evaluate projects Includes the time value of money Includes all inflows and outflows, not just the ones through payback point
33
Discounted Cash Flow Continued Requires a percentage to use to reduce future cash flows – This is known as the discount rate The discount rate may also be know as a hurdle rate or cutoff rate There will usually be one overall discount rate for the company
34
NPV Formula
35
NPV Formula Terms A 0 Initial cash investment F t The cash flow in time period t (negative for outflows) kThe discount rate TThe number of years of life A higher NPV is better The higher the discount rate, the lower the NPV
36
NPV Example
37
Internal Rate of Return [IRR] The discount rate (k) that causes the NPV to be equal to zero The higher the IRR, the better – While it is technically possible for a series to have multiple IRR’s, this is not a practical issue Finding the IRR requires a financial calculator or computer In Excel “=IRR(Series,Guess)”
38
Profitability Index a.k.a. Benefit cost ratio NPV divided by initial cash investment Ratios greater than 1.0 are good
39
Advantages of Profitability Models Easy to use and understand Based on accounting data and forecasts Familiar and well understood Give a go/no-go indication Can be modified to include risk
40
Disadvantages of Profitability Models Ignore non-monetary factors Some ignore time value of money Discounting models (NPV, IRR) are biased to the short-term Payback models ignore cash flow after payback
41
Scoring Models Unweighted factor model Weighted factor model
42
Unweighted Factor Model Each factor is weighted the same Less important factors are weighted the same as important ones Easy to compute Just total or average the scores
43
Unweighted Factor Model Example Figure 2-2
44
Weighted Factor Model Each factor is weighted relative to its importance – Weighting allows important factors to stand out A good way to include non-numeric data in the analysis Factors need to sum to one All weights must be set up so higher values mean more desirable Small differences in totals are not meaningful
45
Weighted Factor Model Example Figure B
46
Analysis Under Uncertainty—The Management of Risk Everything to do with projects is risky Some projects, like R&D, are more risky than others, like construction Risks include… – The timing of the project and its associated cash flow – Risk regarding the outcome of the project – Risk about the side effects
47
Risk and Uncertainty What the decision maker does What nature does
48
Uncertainty 1. Pro forma financial statements 2. Risk analysis 3. Simulation (requires detailed probability information)
49
Comments on the Information Base for Selection 1. Accounting data 2. Measurements 3. Uncertain information
50
Accounting Data 1. Cost and revenue are linear 2. Cost-revenue data derived using standard cost standardized revenue assumptions 3. Costs may include overhead
51
Measurements 1. Subjective versus objective 2. Quantitative versus qualitative 3. Reliable versus unreliable 4. Valid versus invalid
52
Uncertain Information Must estimate inputs for risk analysis These inputs cannot be known exactly Inputs must be adjusted over time
53
Project Portfolio Process (PPP) Links projects directly to the goals and strategy of the organization Means for monitoring and controlling projects
54
PPP Steps 1. Establish a project council 2. Identify project categories and criteria 3. Collect project data 4. Assess resource availability 5. Reduce the project and criteria set 6. Prioritize the projects within categories 7. Select projects to be funded and held in reserve 8. Implement the process
55
Step 1: Establish a Project Council Senior management The project managers of major projects The head of the Project Management Office Particularly relevant general managers Those who can identify key opportunities and risks facing the organization Anyone who can derail the PPP later on
56
Step 2: Identify Project Categories and Criteria 1. Derivate projects 2. Platform projects 3. Breakthrough projects 4. R&D projects
57
Step 3: Collect Project Data Assemble the data Document assumptions Screen out weaker projects The fewer projects that need to be compared and analyzed, the easier the work
58
Step 4: Assess Resource Availability Assess both internal and external resources Assess labor conservatively Timing is particularly important
59
Step 5: Reduce the Project and Criteria Set Organization’s goals Have competence Market for offering How risky Potential partner Right resources Good fit Use strengths Synergistic Dominated by another Has slipped in desirability
60
Step 6: Prioritize the Projects Within Categories Apply the scores and criterion weights Consider in terms of benefits first, resource costs second Summarize the returns from the projects
61
Step 7: Select the Projects to be Funded and Held in Reserve Determine the mix of projects across the categories Leave some resources free for new opportunities Allocate the categorized projects in rank order
62
Step 8: Implement the Process Communicate results Repeat regularly Improve process
63
Project Proposals The project proposal is essentially a project bid Putting together a project proposal requires a detailed analysis of the project Project proposals can take weeks or months to complete A more detailed analysis may result in not bidding on the project
64
Project Proposal Contents Cover letter Executive summary The technical approach The implementation plan The plan for logistic support and administration Past experience