Published byNathan Palmer Modified over 9 years ago
2
Project Status Project Phasing Questions 2
3
As of Today Project released for Bid February 7, 2011 Notice of Bid sent to 80+ Contractors on February 2, 2011 C&S occupied the field office on January 18, 2011 Architectural Approval from SED on December 17, 2010 3
4
Moving Forward Contractor walk through scheduled for February 22, 2011 Project Bids accepted March 3, 2011 Contractor recommendations to the BOE on March 8, 2011 Contractor mobilization beginning in early April, 2011 4
5
Phasing : Scheduling Goals: Minimize disruption to students / staff during the school year Upgrade HVAC systems by September 2011 Main Campus Overall Staging Area Large Permanent Staging Area in gravel lot below the District Office Summer Lay Down Areas at both the High School and Wheeler Elementary School 5
6
HIGH SCHOOL : TWO PHASES SUMMER 2011 & SUMMER 2012 SUMMER 2011 HVAC UPGRADES MAIN OFFICE/GUIDANCE/HEALTH SUITE FIRST FLOOR CLASSROOM RENOVATIONS SINGLE SCEINCE CLASSROOM RENOVATION ROOFING 6
7
HIGH SCHOOL : SUMMER 2012 TWO SCIENCE CLASSROOMS SECOND FLOOR CLASSROOM RENOVATIONS MEDIA CENTER RENOVATIONS SITEWORK 7
8
TECHNOLOGY BUILDING: UPGRADES COMPLETED BY SEPTEMBER 2011 8
9
WHEELER ELEMENTARY: SUMMER 2011 PROJECT COMPLETED HVAC UPGRADES ROOFING CLASSROOM RENOVATIONS 9
10
ROCKWELL ELEMENTARY: TWO PHASES – SUMMER 2011 & SUMMER 2012 SUMMER LAY DOWN AREA SUMMER 2011 HVAC UPGRADES COMPLETED ROOFING ADMINSTRATIVE AREA SECOND FLOOR WEST WING CLASSROOMS 10
11
ROCKWELL ELEMENTARY: SUMMER 2012 FIRST FLOOR CLASSROOMS SECOND FLOOR EAST CLASSROOMS SITEWORK 11
12
Questions 12