SDC Migration Project Status Report January 2012.

Similar presentations


Presentation on theme: "SDC Migration Project Status Report January 2012."— Presentation transcript:

1 SDC Migration Project Status Report January 2012

2 Status Project funding reduced from $59M to $24M – $24M consists of construction bond fund savings – can only be used for SDC improvements and assets Re-setting project strategy, scope, budget, and schedule to align with new funding constraint – Requires different approach and infrastructure design – All procurements on hold pending new plan and design – Private Cloud procurement on hold pending review by TSB (meeting not yet scheduled)

3 Project Reset Activities Assess priorities and options Identify priorities that can be funded through existing or alternate revenue sources Develop phased migration plan that – Reduces risk and maximizes available funds – Relieves OB2 over-capacity problems – Generates revenue from SDC – Meets minimum facility, security, and network requirements – Supports the State’s IT transformation initiative (Utility Computing) – Positions the SDC as the primary data center anticipating eventual OB2 shutdown – Minimizes disruption and rework over time

4 Next Steps (Jan – Feb 2012) Complete budget analysis Complete migration alternatives analysis Determine migration phases: logical groupings of systems determined by dependencies, risks, benefits, complexity, equipment life-cycle, impact, cost Re-design core network and security to support migration phases Define new schedule, charter, investment plan Restart selected procurements and other activities to implement new plan

5 SDC Migration Project Questions?