Construction Report January 19, 2010
3
Projects Track replacement and turf In Progress Walking tracks: Recommendation Water wells March 2010 Bleachers January 2010 Stadium seats Installed
4
Projects Sheldon ECA In close out Early Learning CenterIn close out M. R. Null Middle SchoolPunch list KMS Phase IIIn close out
5
Crenshaw Stadium
6
Crenshaw Stadium Track
8
Maintenance, Operations & Transportation Complex (Support Services) Property purchased Programming resumed/completed Surveys Design development – final phase Utility Service – in progress Environmental Geotechnical
9
Maintenance, Operations & Transportation Complex (Support Services) Corps of Engineers Wetlands TIA DOT Texas Parks & Wildlife Utilities Harris County (permits) Harris County Flood Control
10
Maintenance, Operations & Transportation Complex (Support Services) Storm water Detention Historical Endangered species
11
Maintenance, Operations & Transportation Complex (Support Services)
12
Detention Basin and Storm Water Pump Station Recommendation
13
Network Operations Center Architect Land Programming – final phase Survey Geotechnical
14
Network Operations Center
16
Proposals February 2010
17
Developments UpdateFeb. 2010 ProjectionsFeb. 2010 Enrollment projections Feb. 2010 Future projectsFeb. 2010
18
Elementary #5 Architect identified Engineer identified Programming Initial design review Plan reuse Sustainability (HVAC) Enrollment projection
19
Elementary #5 Architect Contract –Recommendation
20
Elementary #5
21
Project on hold