1 CCC Commissioning Django Manglunki, AB/OP PS-SPS Days 18/1/2006

2 CCC Commissioning PS-SPS DAYS 18/1/ 2006D. Manglunki, AB/OP2 Outline Constraints and boundary limits Reminder of room and consoles layout Project status as of today Schedule/Resources for TI, PS complex, SPS, Cryogenics, LHC HWC Conclusions

3 CCC Commissioning PS-SPS DAYS 18/1/ 2006D. Manglunki, AB/OP3 Constraints and boundary limits Restart of existing accelerator chain and technical services TI operates 24/7 LEIR early February LHC sector test mid- November

4 CCC Commissioning PS-SPS DAYS 18/1/ 2006D. Manglunki, AB/OP4 Room layout: 4 similar but not identical islets ~50 19”screens for controls, local fixed displays, administration and access on outer tables 4 large 46” screens for general purpose fixed displays 3 19”screens for laptops and mail/web on central tables 19” cabinet for rackable HW (access, intercom, beam inhibits, radiation alarms …) 5 IP-touch phones 1 colour printer

5 CCC Commissioning PS-SPS DAYS 18/1/ 2006D. Manglunki, AB/OP5 Project status as of today TS works finished except: –Finishing paint (27/1) –Heating/AC (27/1?) –Blinds and lighting controls (20/1) –CCC Access control operational but administration needed (cards distribution + EDH authorizations) Picture January 16 th 2006Simulation December 3 rd 2004

6 CCC Commissioning PS-SPS DAYS 18/1/ 2006D. Manglunki, AB/OP6 Project status as of today (2) CO works: –Most hardware installed –Configuration in progress, TI islet will be delivered 19/1 –Other islets to follow; end January 27 th Video signals –Last HW delivery mid February –System operational end February Communications –All phones installed, operational –Server configuration started 13/1, finishing 27/1, tests start with TI 30/1 –SPS intercom February Fast analog signals –First HW batch delivered last week (11/1) –Observation of signals mid-April

7 CCC Commissioning PS-SPS DAYS 18/1/ 2006D. Manglunki, AB/OP7 Project status as of today (3) PS complex access –Configuration and test under way –Switch control from CSA on week-end February 4-5 (LEIR starts February 6 th !) –Radio protection alarms: Hardware being installed SPS Access –racks in 867 for configuration;move to CCC 20/1 –Test access control from CCC 2 nd fortnight March

8 CCC Commissioning PS-SPS DAYS 18/1/ 2006D. Manglunki, AB/OP8 Schedule/resources for TI CCC Cold checkout starts January 23 rd –Configure and test application programs –Configure and test room functions (lighting and blinds controls…) –Configure and test communications (30-31/1) –Additional 2 TI technicians 8 hours/day Move in from MCR on February 1 st –1 TI + 1 PS/PSB 24/7 until PS shifts start

9 CCC Commissioning PS-SPS DAYS 18/1/ 2006D. Manglunki, AB/OP9 Schedule/resources for PS complex CCC Cold checkout starts February 13 th –Configure and test application programs –Configure and test communications –2 PS/PSB technicians 8 hours/day –Until PS/PSB shifts start, access given by PSB technician on TI shift PS magnet tests start 20/2 PSB/PS closed 6/3 –PSB HW tests –Additional 2 PS/PSB tech 8 hours/day PS shifts start 20/3 –3 tech on shift 24/7 –Only 1 TI tech

10 CCC Commissioning PS-SPS DAYS 18/1/ 2006D. Manglunki, AB/OP10 Schedule/resources for SPS CCC Cold checkout starts March 6 th –Configure and test communications –Configure and test application programs –Test access control Give access only during working hours –2 SPS technicians 8 hours/day SPS shifts start 3/4 for HW tests –2 tech on shift 24/7 Request of SPS OP in February –for TI8/CNGS tests!

11 CCC Commissioning PS-SPS DAYS 18/1/ 2006D. Manglunki, AB/OP11 Schedule/resources for Cryogenics CCC Cold checkout starts March 6 th in parallel with operations/tests from local control rooms –Configure and test application programs –Configure and test communications –1 AT/ACR technician + 1 AB/CO 8 hours/day First operation from CCC expected in June

12 CCC Commissioning PS-SPS DAYS 18/1/ 2006D. Manglunki, AB/OP12 Schedule/resources for LHC HWC CCC Cold checkout starts September 4 th –Test access control –Configure and test application programs –Configure and test communications –3 LHC OP or EiC, 16 hours/day HWC gradually moves from FCR to CCC in October/November Sector test from CCC end November

13 CCC Commissioning PS-SPS DAYS 18/1/ 2006D. Manglunki, AB/OP13 Overall schedule January – April 2006

14 CCC Commissioning PS-SPS DAYS 18/1/ 2006D. Manglunki, AB/OP14 Conclusion Good collaboration needed between all parts (AB/OP, AB/CO, TS/CSE, TS/EL, TS/CV, AT/ACR, TS/HDO, IT/CS…) for validation of CCC functionalities So far so good, February 1 st is still the delivery date: 14 days to go!