UCN 2014 Installation Overview/Logistics UCN Monthly Meeting Dec.18, 2013 (L.Lee)
2
UCN 2014 Installation: Schedule 2 UCN 2014 Installation folded into Shutdown Schedule New schedule release today (SAS Committee) UCN SASP0184,185,186,187 Start: January 2 ; Finish: ~ April 10 Shield-Plug reconfiguration: starts in mid-March Work Requests (10) submitted; Not all approved yet. Lift Plan (Jason), Alignment Plan (Dave P.), Dose Analysis (Cam RPG) CNSC Approval of Shield Plug (“in the mail” “OK to proceed” Anne/Jeff)
3
UCN 2014 Installation: Personnel 3.T-B/L (Beamlines) Installation/Alignment of B/L Components Consultation w/ TRIUMF Alignment Group (D.Preddy, B.Gasbarri, M.Vogel) D.Pearce hired on contract direct UCN alignment efforts Hexagon Metrology Engineer (R.Molari) services contract advisory tracker specialist.T-Mech (Mechanical) General removal/assembly of components M.Goyette hired on contract T.Hessels (UCN Designer &.T-Mech) ~ 50% (?) Require 1 more.T-Mech (TRIUMF) 50% Crane Crew At start of shutdown (Jan.2 – 17) remove/excavate shielding blocks Intermittent (Jan.21 – Mar.26) removal/placing of components Near end of shutdown (Mar.27 – Apr.10) restoring shielding+plug Others Contractors: Plumbing (Lockerbie), Electrical (Entech), Coring (West Coast) Safety/RPG, Engineering (Civil, Electrical), Plant Group Intermittent Diagnostics & Controls 1AM5 (best efforts)
4
UCN 2014 Installation: Alignment Plan 4 Alignment Plan & Logistics Plan being developed in consultation w/ Alignment group & D.Pearce Purchase Order for laser-tracker rental from Hexagon Metrology Alignment Plan Overview Fiducialize magnets, frames & other B/L components w/ Laser Tracker - Shoot array of points (upstream/downstream) on each component Shoot Vault & 1A monuments w/ Laser Tracker & establish coord. system Lay down grid of new monuments (Vault & 1A tunnel) & record - Number/Locations of new monuments (consult Bruno/Mike) Paint floor and/or lay down scribe lines Mark drill location (and angle) on Immovable-block for coring Install/Locate frames (Theodolite or Laser Tracker) Install/Align magnets/components according to schedule - Use Laser Tracker to position fiducialized points
5
Meson Hall Clean-up 5 M11 Cleanup Completed Staging area for new Shielding M13 Cleanup Completed Staging area for “removed” blocks Some blocks already moved to M13 Jason’s layout for temp. block storage “Boot-box” area for 1A access M13 Cleanup above BL1A/1B Almost completed (thanks to Ron K.) 46 items removed; ~11 items left to move (this week & after beam OFF) Catalogue of items removed: https://ucn.triumf.ca/triumf/beamline/Catalog-MH-cleanup.pdf Extra Blocks (6’ and smaller) stage to M13 “monolith”
6
Floor Plan (SW Meson Hall) Total number of items: 9 (zone A) + 13 (zone B) + 30 (zone C) = 52 Gateway (From Dec/2012) Cleanup above BL1A/1B
7
Floor Plan (SW Meson Hall) Total number of items: 9 (zone A) + 13 (zone B) + 30 (zone C) = 52 Gateway (From Dec/2012)
8
Floor Plan (SW Meson Hall) Total number of items: 1 (zone A) + 5 (zone B) + 3 (zone C) = 9 (43 objects cleared) Gateway (Dec/2013) Objects rem.
9
Floor Plan (SW Meson Hall) Total number of items: 1 (zone A) + 5 (zone B) + 3 (zone C) = 9 + 5 “New items” Gateway (Dec/2013) Objects added N1 N3 N2 N4 N5
10
Floor Plan (SW Meson Hall) Total number of items: 1 (zone A) + 5 (zone B) + 3 (zone C) = 9 + 2 “New items” Gateway (Dec/2013) Objects added (& removed) N1 N3 N2 N4 N5
11
Remaining items to move
12
To M11: To top of M9, M11, M20 blocks: Beamlines R/H UCN To Storage “Barn”: Beamlines Remaining items to move this week Detector Group
13
To Vault Roof: T2K/Snolab BeamlinesPIENU Outside M11: EWB/Beamlines Remaining items to move after beam OFF
14
FINIS
15
.T-Mech