Good Afternoon!. Construction Update Airside Center Roof Construction began in May Currently 45% complete Scheduled Completion is December.

Similar presentations


Presentation on theme: "Good Afternoon!. Construction Update Airside Center Roof Construction began in May Currently 45% complete Scheduled Completion is December."— Presentation transcript:

1 Good Afternoon!

2 Construction Update

3 Airside Center Roof Construction began in May Currently 45% complete Scheduled Completion is December

4 Notice-To-Proceed May 27 Tower should be completed and operational prior to Sun n Fun 2016 ATCT Construction

5 LLRA received an additional $450,000 grant for gate and access control upgrades Fiber will be run to all of our airfield access gates providing better reliability New power feeds to the south side of the airport Project 90% complete Security and Power Upgrades

6 Paint Hangar Expansion Construction to be complete January 2016

7 LLRA will be a “User Fee” Airport Application along with letter of support from the Governor submitted in February Floor plan review in progress with CBP Funding for the $300,000 renovation in place LLRA will cover the $140,000 officer expense Fees will be charged based on aircraft type Goal is to be operational 2 nd Quarter 2016 U.S. Customs Facility

8 Additional Solar Construction to begin early October

9 Turf Runway 8-26 FAA 7480 for commissioning of the RWY submitted – Last step Environmental approved

10 TWY D Rehab/Extension 2015 FAA/FDOT Projects

11 Airfield Electrical Improvements - Signage 2015 FAA Projects

12 Airfield Electrical Improvements – N1 Circuit 2015 FAA Projects

13 2016 FAA Projects TWY G Rehabilitation and Realignment

14 MRO Development

15 2017 FAA Projects TWY A Rehabilitation Westerly 2,500 feet TWY A Connectors Connector coming off of TWY into MRO

16 Business Update

17 Moving through site plan approval with COL Construction by end of year New Airport Hotel

18 Developers Agreement Plan is to put an RFP on the street in October Requesting qualified developers to help develop 30 plus acres of non-aviation land off of Drane Field Rd. Goal is for selected firm to market development area to prospective tenants and for the developer to lease land from airport and build the development for the end user

19 Oct 1-4 Red Star Warbird Clinic Oct 3 Classroom to the Sky – SNF Oct 3 Pilot Mall Open House - SNF Oct 15-17 12 O'clock High RC Event Oct 23-25Aerospace Discovery Weekend Oct 29-31Red Flag RC Event, New event Nov 6-7When Pigs Fly South BBQ Nov 11-15 Carlisle Auto Fest Nov 16-20CFAA Freshman First Flights - SNF Airport Events

20 Questions?