El Vado Dam Corrective Action Study New Mexico Watershed and Dam Owners Coalition Conference – May 12, 2015 Presented by Mike A. Hamman, Chief Engineer Middle Rio Grande Conservancy District
2
El Vado Dam Quarter Inch Faceplate
3
Early Construction Photo
4
El Vado Dam Spill
5
Intake Structure for SJC Project
6
View of Expansion Joints and Patches looking up to the Crest
7
Expansion Joint Separation
8
Failed Expansion Joint
9
Patched Spillway Wall
10
Failed Bracing on Spillway Wall
11
Backfill Behind Spillway Wall
12
Complete designs for concrete spillway, gate and emergency spillway dike and related reports by 12/2015 Complete abutment and faceplate assessments by 2/2016 NEPA Compliance by 5/2016 Construction start by 2/2017 ?? CAS Status