El Vado Dam Corrective Action Study New Mexico Watershed and Dam Owners Coalition Conference – May 12, 2015 Presented by Mike A. Hamman, Chief Engineer.

Similar presentations


Presentation on theme: "El Vado Dam Corrective Action Study New Mexico Watershed and Dam Owners Coalition Conference – May 12, 2015 Presented by Mike A. Hamman, Chief Engineer."— Presentation transcript:

1 El Vado Dam Corrective Action Study New Mexico Watershed and Dam Owners Coalition Conference – May 12, 2015 Presented by Mike A. Hamman, Chief Engineer Middle Rio Grande Conservancy District

2 El Vado Dam Quarter Inch Faceplate

3 Early Construction Photo

4 El Vado Dam Spill

5 Intake Structure for SJC Project

6 View of Expansion Joints and Patches looking up to the Crest

7 Expansion Joint Separation

8 Failed Expansion Joint

9 Patched Spillway Wall

10 Failed Bracing on Spillway Wall

11 Backfill Behind Spillway Wall

12  Complete designs for concrete spillway, gate and emergency spillway dike and related reports by 12/2015  Complete abutment and faceplate assessments by 2/2016  NEPA Compliance by 5/2016  Construction start by 2/2017 ?? CAS Status

13 Questions?