PUSHKARA LIFT IRRIGATION SCHEME (2 years period)

Similar presentations


Presentation on theme: "PUSHKARA LIFT IRRIGATION SCHEME (2 years period)"— Presentation transcript:

1 PUSHKARA LIFT IRRIGATION SCHEME (2 years period)
PROGRESS Bids under process 0.00 KM GODAVARI RIVER GODAVARI RIVER PUMP HOUSE DELIVERY CISTERN M A I N C A N A L PSC PRESSURE MAINS (2 x 6 Nos.) KM 7.5 L1 KM 40.00 L2 L3 KM 89.50 95.50 KM 4 Nos. of 3,000 HP each for each pump house (2 pump house – 8 Nos. of pmps) (6 Nos. of pressure mains for each pump house) 1 st Pump house : Progress 2nd Pump House : Progress Main Canal : Progress 2nd Lift on canal : bids under finalization Ayacut : 1,86,000 Acres Utilisation : TMC Lift height : 27 M Pumps : 8 Nos. of 3000 HP each Power required : 30 MW Length of canal : KM Tender Amt. : Rs Cr. Target Date for Completion : 7 / 2006

2 PUSHKARA LIFT IRRIGATION SCHEME
1 PROJECT PROFILE : Lift Irrigation Scheme near Purushothapatnam (V) at Km upstream of Godavari Barrage. 2 Administrative Sanction : G. O. Ms. No. 126, I & CAD, Dt: for Rs Crores G.O.Ms.No.167, I&CAD, Dt for Rs Crores. Total: Rs Crs. 3 No. of EPC Packages 2 Nos No. of (old) Packages 2 No. 4 Agreement value of 4 packages Rs ( (2 old), Crs. (2EPC) 5 Budget provision for Rs Crs. 6 Expenditure of the project 2004 – 05 Rs Crs. 2005 – 06 Rs Crs. Cum. Exp. Rs Crs 7 Utilisation 15.6 TMC 8 Ayacut New Ayacut 1,86,000 acres 9 Land Acquisition Required 6272 acres Requisition 1425 acres Acquired 1832 acres 10 Forest land 1 hectare 11 Estimated cost of L.A. Rs.27 Crs 12 Estimated cost of R & R Nil

3 13 Lift-I Lift Height : 27 M No. of Pumps 8 x 3000 HP Total pumps capacity 24000 HPs 14 Lift-II 50 M 17570 HP 15 Lift-III 30 M 2 x 1100 2200 HP 16 Power required 30.00 MW 17 Mob. Advance (Rs. in Crores) Paid Recovered : Total 18 Target date of completion Khariff/2006

4 PUSHKARA LIFT IRRIGATION SCHEME
PKG No. Description Agt. Value & Date Agt. Period Name of the contractor 1 Supply, commissioning of pumping machinery, construction of pump house, delivery cistern etc. Rs Cr. . Dt: 18 Months M/s KBL Limited Pune 2 Supply, commissioning of pumping machinery construction of pump house, delivery cistern etc., Rs Cr. Dt: M/s NCC Limited, Hyderabad 3 Execution of main canal from KM 0.00 to KM to irrigate an ayacut of 1,85,906 acres Rs Cr. Dt: 24 Months M/s Prasad & Co. (PW) Ltd., Hyd. 4 Construction of 3 Nos. of Lift Irrigation Schemes (IInd Lift), supply, commissioning of pumping machinery, construction of pump house pressure main Bids under finalisation

5 PUSHKARA LIFT IRRIGATION SCHEME
Pkg.No. OC (Old) : Construction of Pump House and delivery cistern etc of Pushkara LI Scheme at Km on AGLB near Purushothampatnam Village Name of the Contractor : M/s. Kirloskar Brothers Ltd. Agreement Amount : Rs Crs. Agreement Date : Period of completion : 18 Months (8 milestones) ( ) Target date of completion : 4/2006 Investigation : Completed Designs : Completed Execution (Pressure main laying) : 32 Kms length completed against 40.5 Kms. Qty. of earth work done (pump mains) : 2,10,000 cum against 2,50,000 cum. Qty. of concrete work done : 5900 cum against 7200 cum Laying of Pipe line : 32 Km length against 40.5 Km Pressure mains : 6 Nos against 6 Nos Pump house : 1 Nos against 1 No. Pumps : all 4 Nos. of pumps supplied at site. Expenditure : Rs Crs. Rs Crs. Cum. Inc. Mob. Adv. only - Rs Crs Land Acquisition : Required Ac., Acquired Ac.

6 PUSHKARA LIFT IRRIGATION SCHEME
Pkg.No. OC (Old) : Construction of Pump House and delivery cistern etc of Pushkara LI Scheme 2nd pump house at Km of AGLB near Purushothampatnam Village. Name of the Contractor : M/s. Nagarjuna Const. Co.Ltd. Agreement Amount : Rs Crs. Agreement Date : Period of completion : 18 Months (8 milestones) ( ) Target date of completion : Investigation : Completed Design : Completed Execution (pressure main laying) : Kms length against Kms Qty. of earth work done : Cum against 2,50,000 Cum Qty of concrete work done : 1750 cum against 4500 cum (pump house & pressure mains) Pumps : all 4 Nos. of pumps supplied at site. Cistern: 1 Nos against 1 No; Pressure main : 6 Nos. against 6 Nos.; Pump house: 1 No. against 1 No. Expenditure : Rs Crs. Rs Crs. Cum. Inc. Mob. Adv. only - Rs Crs Land Acquisition : Required Acres, Acquired Acres

7 PUSHKARA LIFT IRRIGATION SCHEME
Pkg.No. 1 : Execution of of Main canal from Km to Km and its distributaries field channels including CM & CD works etc., complete to irrigate an ayacut of 1,85,906 acres for Pushkara Lift Irrigation Scheme in E.G. District Name of the Contractor : M/s. Prasad & Co. (P) Ltd. Agreement Amount : Rs Crs. Agreement Date : Period of completion : 24 Months(8 months) Target date of completion : 9/2005 Investigation : Completed Designs approved : Km length against Km Structures (approved) : 44 Nos. against 157 Nos. Execution (canal) : 44 Km length against Km Qty. of earth work done : 63,40,000 cum against 1,15,60,000 cum Qty. of concrete work done : 16,300 cum against 90,000 cum. Expenditure : Rs Crs. Rs Crs. Cum. Inc. Mob. Adv. only - Rs Crs Land Acquisition : Required 6120 Acres, Acquired 971 Acres Bottlenecks : Land acquisition approvals to approval > HPCL/GAIL line crossing > L & T pipeline crossing


Download ppt "PUSHKARA LIFT IRRIGATION SCHEME (2 years period)"