Model Home Permitting and Temporary Certificates of Occupancy Orange County BCC August 25, 2015
2
Presentation Outline Background Model Home Permits Model Home TCOs Next Steps
3
Presentation Outline Background Model Home Permits Model Home TCOs Next Steps
4
Background Public comment from December 2, 2014 Homebuilders’ draft resolution to allow Temporary CO (TCO) for a model home in limited circumstances BCC Discussion on January 26, 2015 to explain permitting and issues related to model homes BCC direction
5
Model Home Permitting Requirements – Prohibits vertical construction prior to approval of plat – Prohibits erection of building unless access via public street – 1995 resolution to allow model homes to be ready concurrent with final plat / completed infrastructure – Limited to 20%, but no more than 5 Background
6
Background Model Homes Certificate of Occupancy Requirements – No CO (temporary or permanent) prior to plat – No CO (temporary or permanent) prior to Certificate of Completion – Developer acknowledgement via affidavit
7
Background Permitting issues – No address for emergency response – May be no stabilized infrastructure – Inspector access – May be inadequate water supply Clear code requirements – Florida Building Code – Florida Fire Prevention Code – Utilities (water, wastewater, power)
8
Background TCO Issues – Public access to an active construction area – Adequate parking – Completion of infrastructure and utilities Home builders’ draft resolution to allow permitting and TCOs earlier in the process
9
Presentation Outline Background Model Home Permits Model Home TCOs Next Steps
10
Model Home Permits Recommended Building Permit Conditions – Preliminary Plat – Curb and stabilized road base from public ROW to lot – Substantial completion of drainage infrastructure – Accessible, functional fire hydrant within 500’ – Acknowledgement of risk affidavit, Hold Harmless agreement – Limited number of homes – Location of homes in subdivision
11
Presentation Outline Background Model Home Permits Model Home TCOs Next Steps
12
Model Home TCOs Recommended Temporary CO Conditions – Requires final plat – Completion to lot of asphalt, drainage infrastructure, traffic control devices and street signs for emergency response – All building inspections complete – FDEP potable water clearance and wastewater clearance – Permanent public restroom and permanent power Update on current practice – Issued TCOs for model homes approx. 10 communities (3-5 models each) – Requests for amenities such as clubhouses
13
Presentation Outline Background Model Home Permits Model Home TCOs Next Steps
14
Next Steps Incorporate code changes into Chapter 38 update Concurrent amendment to Chapter 30 and 34 LPA Public Hearing 2 BCC Public Hearings Update fee schedule