Configuration Management Non Government Std: EIA Standard-649 “A management process for establishing and maintaining consistency of a product’s performance, functional and physical attributes with its requirements, design and operational information throughout its life.” Identify and document the functional and physical characteristics of configuration items. Control changes to configuration items and their related documentation. Record (or Status Accounting in DoD terms) and report information needed to manage configuration items effectively, including the status of proposed changes and implementation status of approved changes. Audit configuration items to verify conformance to specifications, drawings, interface control documents, and other contract requirements. - Adopted by DoD, 22 Nov 96
2
Configuration Items CONFIGURATION ITEM (CI) - An aggregation of hardware or software that satisfies an end use function and is designated by the Government for separate configuration management. CIs will be directly traceable to WBS. Any item required for logistics support and designated for separate procurement is also a CI. Computer hardware & software will be treated equally as CIs.
3
High risk or safety concern? Readily identifiable physically ? Newly developed? Use new technologies? Interface with item developed under another contract? Interface with other CI’s whose configuration is controlled by someone else? Requirement to know exact configuration during life? Why Designate it as a Configuration Item?
4
Impact of CI Designation Separate specifications. Put under configuration control. Documentation Formal approval of changes Status accounting Configuration Audits Individual design reviews. Separate qualification tests. Separate operating and user manuals.
5
Configuration Baselines Used to ensure an orderly transition from one major commitment point to the next. Three distinct evolutionary increasing levels of detail: Functional configuration documentation. Allocated configuration documentation. Product configuration documentation A baseline plus approved changes from that baseline constitutes the current approved configuration documentation. ECP Baseline ECP + + Approved Configuration = APPROVED
6
IOC BA Single Step or Evolution to Full Capability Concept & Technology Development System Development & Demonstration Production & Deployment Pre-Systems Acquisition Systems Acquisition (Engineering and Manufacturing Development, Demonstration, LRIP & Production) Operations & Support C Technology Opportunities & User Needs Post-Systems Acquisition Process entry at Milestones A, B, or C (or within phases) Program outyear funding when it makes sense, but no later than Milestone B (unless entering at C) Relationship to Requirements Process MNSORD All validated by Requirements Authority or PSA FRP Decision Review BLOCK II BLOCK III FOC IOT&E DESIGN FAB, INTEGRATE & TEST SFR PDR CDR TRR SVR SRR Specification Evolution Across the Life Cycle Specifications - - - - - - - - - - - - ----------------------------------------------------------------------------------------- System Spec - - - - - - - - - - - - - ------------------------------------------------------------------------- Item Performance Spec - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - ------------------------------------------------ Item Detail, Process, Material Specs SFR PDR PCA FCA CDR - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - ------------------------------------------------ - - - - - - - - - - - - - ------------------------------------------------------------------------ - Functional (system) Allocated (design to) Product (build to) Configuration Baselines - - - - - - - - - -----------------------------------------------------------------------------------------
7
Configuration Management Planning The decision as to Which baselines the government should eventually control The data needed When that control should be established are strategic management decisions that involve Acquisition strategies - sources, competition, etc. Logistics support plans - repair levels, data needs, open systems, etc. Technology insertion - stable vs rapidly moving technologies, etc.
8
Configuration Management Strategy Government should control the Functional Baseline (documents system level requirements) DoD PMO’s increasingly choose to leave Allocated Baselines under contractor control until late in development. (Documents the CI level design requirements.) Promotes contractor design flexibility Relieves PMO from administrative burdens of managing design ECPs Requires effective implementation of IPPD When and if to control baselines is dependent on support philosophy and acquisition management strategy.
9
Configuration Identification The selection of the documents to comprise the technical baseline for the system and configuration items involved. Selection of the numbers and other identifiers affixed to the items and documents. Basis for configuration audits, configuration control, and configuration status accounting. s/n xxxxxx s/n yyyyyy ECP DWG Spec’n Dwg no xxx
10
Configuration Control Purpose of configuration control: Provide management visibility. Prevent unnecessary or marginal changes. Establish change priorities. Assure prompt action: Control the change. Document the change. Control the release system. A configuration control board is established to review proposed changes and advise the program manager.
11
CONTRACTING OFFICER Configuration Control Board OTHER IMPLEMENTING ACTIVITIES ENGINEERING CHANGE PROPOSAL (ECP) Alteration in approved CM Doc’s CI (possibly with a spec change) CONFIGURATION CONTROL BOARD DIRECTIVE CCB SECRETARIAT (CONFIG MGR) CHAIRMAN (PM) USING COMMAND TNG COMMAND LOG COMMAND ENGINEERING PROCUREMENT PROGRAM CONTROL TEST CONFIG MGT SAFETY FLT SURGEON MAINTENANCE CONTRACTOR Begins & Ends
12
Configuration Status Accounting Provides a track of configuration identification changes. Documents the configuration of items. Helps ensure on time shipments of change kits. Helps provide proper training. Helps ensure installation of correct items.
13
Configuration Audits Verify and document that the configuration item and its configuration documentation: Agree. Are complete and accurate. Satisfy program requirements. Two types: Functional Configuration Audit Physical Configuration Audit
14
Functional Configuration Audit “AS BUILT” RECORDS TEST PROCEDURES CONFIGURATION IDENTIFICATION CONFIG ITEM SPEC QUALIFICATION TEST REPORTS COMPARED WITH RELEASED ENGINEERING CONFIGURATION QUALIFICATION TESTING INITIAL UNIT OF PRODUCTION HARDWARE AUTHORIZED CHANGES
15
Physical Configuration Audit ACCEPTANCE TEST DATA INTEGRATED RECORDS SYSTEM FORMS INPUT FOR CONFIGURATION STATUS ACCOUNTING REPORT ACCEPTANCE TEST PROCEDURES RELEASE ENGINEERING DATA PHYSICALLY (size, type, dimensions) COMPARED WITH ITEM DETAIL SPECIFI- CATION CONFIGURATION IDENTIFICATION INDEX INITIAL UNIT OF PRODUCTION HARDWARE AUTHORIZED CHANGES COMPLIANCE REPORTED VERIFY
16
Summary Configuration management is essential to control the system design throughout the life cycle. The issue is not whether or not to have a configuration management program, but, rather, how it shall be managed. Configuration management impacts across the technical and business spectrum and requires an integrated (IPPD) approach to ensure that decisions made are well founded and that surprises do not occur.