Presentation is loading. Please wait.

Presentation is loading. Please wait.

10/19/2015 12:26 AM 1 Project Cost Control. 10/19/2015 12:26 AM 2  Controlling involves making sure that the results achieved are in line with the planned.

Similar presentations


Presentation on theme: "10/19/2015 12:26 AM 1 Project Cost Control. 10/19/2015 12:26 AM 2  Controlling involves making sure that the results achieved are in line with the planned."— Presentation transcript:

1 10/19/2015 12:26 AM 1 Project Cost Control

2 10/19/2015 12:26 AM 2  Controlling involves making sure that the results achieved are in line with the planned results.  The main feature of control is action to correct performance deviations and to insure that expected results are forthcoming. Control = Monitor + Compare + Analysis + Action  Controlling involves making sure that the results achieved are in line with the planned results.  The main feature of control is action to correct performance deviations and to insure that expected results are forthcoming. Control = Monitor + Compare + Analysis + Action  Definition: Controlling

3 10/19/2015 12:26 AM 3 1.To identify those work types having excessive costs and to give an indication of how serious those overruns are. 2.To forecast the final total job cost. 3.To indicate the trend for each cost code, that is, whether the unit cost involved has been increasing or decreasing (evaluation of the effectiveness of cost reduction efforts). 4.To update the database of the company that will be used to estimate future works. 1.To identify those work types having excessive costs and to give an indication of how serious those overruns are. 2.To forecast the final total job cost. 3.To indicate the trend for each cost code, that is, whether the unit cost involved has been increasing or decreasing (evaluation of the effectiveness of cost reduction efforts). 4.To update the database of the company that will be used to estimate future works.  Objectives of Project Cost Control System

4 10/19/2015 12:26 AM 4 cost estimate  The cost estimate prepared for the project during the bidding process is the basis for cost control. labor, equipment, materials and site overheads  Cost control for an engineering project is limited to the cost of labor, equipment, materials and site overheads.  Control of cost and time should be linked together. cost estimate  The cost estimate prepared for the project during the bidding process is the basis for cost control. labor, equipment, materials and site overheads  Cost control for an engineering project is limited to the cost of labor, equipment, materials and site overheads.  Control of cost and time should be linked together.  Project Time Control  Project Cost Control System

5 10/19/2015 12:26 AM 5  Three Key Indicators in Performance Measurement 1.Budgeted Cost of Work Scheduled (BCWS) 1.Budgeted Cost of Work Scheduled (BCWS) is the budgeted amount of cost of the work scheduled to be accomplished in a given time period (including support and allocated overhead). 2.Budgeted Cost of Work Performed (BCWP) earned value of work accomplished 2.Budgeted Cost of Work Performed (BCWP) is the budgeted amount of cost for the work completed in a given time period, including support effort and allocated overhead. (This is sometimes referred to as “earned value of work accomplished”.) How to calculate BCWP Budgeted cost for work performed (BCWP) = Earned value of an activity = Percent completed for the activity * the activity budget Percent completed for an activity = [(Projected duration – Remaining duration) / Projected duration] * 100 1.Budgeted Cost of Work Scheduled (BCWS) 1.Budgeted Cost of Work Scheduled (BCWS) is the budgeted amount of cost of the work scheduled to be accomplished in a given time period (including support and allocated overhead). 2.Budgeted Cost of Work Performed (BCWP) earned value of work accomplished 2.Budgeted Cost of Work Performed (BCWP) is the budgeted amount of cost for the work completed in a given time period, including support effort and allocated overhead. (This is sometimes referred to as “earned value of work accomplished”.) How to calculate BCWP Budgeted cost for work performed (BCWP) = Earned value of an activity = Percent completed for the activity * the activity budget Percent completed for an activity = [(Projected duration – Remaining duration) / Projected duration] * 100

6 10/19/2015 12:26 AM 6  Three Key Indicators in Performance Measurement 3.Actual Cost of Work Performed (ACWP) 3.Actual Cost of Work Performed (ACWP) is the amount reported as actually expended in completing the particular work accomplished within a given time period.

7 10/19/2015 12:26 AM 7 Cost Performance 1.Cost Variance (CV) = BCWP  ACWP +ve  Under Budget (cost) Cost Variance Cost Variance0  Within Budget (on cost) - ve  Over Budget (cost) 2.Cost Performance Index (CPI) or Cost Performance Ratio (CPR) = BCWP/ACWP > 1  Under Budget (under cost) = costs below budget CPI CPI= 1  Within Budget (on cost) < 1  Over Budget (over cost) 3.% Cost Overrun/ Underrun = (ACWP – BCWP)/ BCWP where –ve value indicates an underrun has occurred. curve The “Cost Overrun” curve is a plot of the calculated percent over- or underrun at any given time. 1.Cost Variance (CV) = BCWP  ACWP +ve  Under Budget (cost) Cost Variance Cost Variance0  Within Budget (on cost) - ve  Over Budget (cost) 2.Cost Performance Index (CPI) or Cost Performance Ratio (CPR) = BCWP/ACWP > 1  Under Budget (under cost) = costs below budget CPI CPI= 1  Within Budget (on cost) < 1  Over Budget (over cost) 3.% Cost Overrun/ Underrun = (ACWP – BCWP)/ BCWP where –ve value indicates an underrun has occurred. curve The “Cost Overrun” curve is a plot of the calculated percent over- or underrun at any given time.

8 10/19/2015 12:26 AM 8 Schedule (Time) Performance 4.Schedule/ Performance Variance (SV) = BCWP  BCWS +ve  Ahead of Schedule Sch./ Per. Variance Sch./ Per. Variance0  On Schedule -ve  Behind Schedule 5.Schedule Performance Index (SPI) = Schedule Performance ratio (SPR) = BCWP/ BCWS > 1  Ahead of Schedule (completions ahead of schedule) SPI SPI= 1  On Schedule < 1  Behind Schedule 4.Schedule/ Performance Variance (SV) = BCWP  BCWS +ve  Ahead of Schedule Sch./ Per. Variance Sch./ Per. Variance0  On Schedule -ve  Behind Schedule 5.Schedule Performance Index (SPI) = Schedule Performance ratio (SPR) = BCWP/ BCWS > 1  Ahead of Schedule (completions ahead of schedule) SPI SPI= 1  On Schedule < 1  Behind Schedule

9 10/19/2015 12:26 AM 9 Cost Forecasting 6.Budgeted Cost At Completion (BAC) = Budget cost of the project = Budgeted Cost of Work Scheduled at the end of the project (BCWS end ) 7.Estimated Cost At Completion (EAC) = Estimated total final cost = (ACWP to date / BCWP to date ) * BAC More accurate forecast can be reached by using the following formula: 8.Estimated Cost At Completion (EAC) = ACWP to date + [(BAC – BCWP to date ) / CPI this period ] 9.Estimate to complete (ETC) = EAC – ACWP 10.Variance from original budget = EAC - BAC 6.Budgeted Cost At Completion (BAC) = Budget cost of the project = Budgeted Cost of Work Scheduled at the end of the project (BCWS end ) 7.Estimated Cost At Completion (EAC) = Estimated total final cost = (ACWP to date / BCWP to date ) * BAC More accurate forecast can be reached by using the following formula: 8.Estimated Cost At Completion (EAC) = ACWP to date + [(BAC – BCWP to date ) / CPI this period ] 9.Estimate to complete (ETC) = EAC – ACWP 10.Variance from original budget = EAC - BAC

10 10/19/2015 12:26 AM 10 BCWS, BCWP, and ACWP Under budget (costs below budget) & Ahead of schedule (fast)

11 10/19/2015 12:26 AM 11 BCWS, BCWP, and ACWP Over budget (Over costs) & Ahead of schedule (fast)

12 10/19/2015 12:26 AM 12 BCWS, BCWP, and ACWP Under budget (costs below budget) & Behind schedule (Slow)

13 10/19/2015 12:26 AM 13 BCWS, BCWP, and ACWP Over budget (Over cost) & Behind schedule (Slow)

14 10/19/2015 12:26 AM 14 Performance report from integrated time/cost control system BCWS, BCWP, and ACWP

15 10/19/2015 12:26 AM 15  Example The following time-scale diagram represents a small engineering project. The budgeted cost of each activity is shown in the table below. At the end of the 10 th week, the field progress report gives you the following information:  Activity “A” was completed on schedule.  Activity “B” started as planned but it is expected to take four weeks more.  Activity “C” started as planned but finished one week later.  %age of completion of activity “D” is 60%.  ACWP at the end of week 10 = SR 90400 Calculate the CV, SV, BAC, EAC, ETC, and comment on the progress of the work. The following time-scale diagram represents a small engineering project. The budgeted cost of each activity is shown in the table below. At the end of the 10 th week, the field progress report gives you the following information:  Activity “A” was completed on schedule.  Activity “B” started as planned but it is expected to take four weeks more.  Activity “C” started as planned but finished one week later.  %age of completion of activity “D” is 60%.  ACWP at the end of week 10 = SR 90400 Calculate the CV, SV, BAC, EAC, ETC, and comment on the progress of the work. Time (week) 1234567891011121314151617181920212223 A (5 weeks)B (8 weeks)E (7 weeks)F (3 weeks) C (5weeks)D (6 weeks)G (4 weeks) ActivityABCDEFG Budgeted cost (SR)50000120001600024000120002100020000

16 10/19/2015 12:26 AM 16  Example  %age of completion of activity “A” = 100%  Projected duration of activity “B” = 8 + 4 = 12 weeks  %age of completion of activity “B” = 5/12 = 41.666666%  %age of completion of activity “C” = 100%  BCWS 10 = A + C + 5/8*B + 5/6D = 50000 + 16000 + 5/8*12000 + 5/6*24000 = SR 93500  BCWP 10 = A + C + 0.4167*12000 + 0.60*24000 = SR 85400  CV = BCWP – ACWP = 85400 – 90400 = SR -5000 (Over Budget)  SV = BCWP – BCWS = 85400 – 93500 = SR -8100 (Behind Schedule)  BAC = 50000 + 12000 + 16000 + 24000 + 12000 + 21000 + 20000 = SR 155000  EAC = [ACWP/BCWP]*BAC = [90400/85400]*155000 = SR 164075  ETC = EAC – ACWP = 164075 – 90400 = SR 73675  %age of completion of activity “A” = 100%  Projected duration of activity “B” = 8 + 4 = 12 weeks  %age of completion of activity “B” = 5/12 = 41.666666%  %age of completion of activity “C” = 100%  BCWS 10 = A + C + 5/8*B + 5/6D = 50000 + 16000 + 5/8*12000 + 5/6*24000 = SR 93500  BCWP 10 = A + C + 0.4167*12000 + 0.60*24000 = SR 85400  CV = BCWP – ACWP = 85400 – 90400 = SR -5000 (Over Budget)  SV = BCWP – BCWS = 85400 – 93500 = SR -8100 (Behind Schedule)  BAC = 50000 + 12000 + 16000 + 24000 + 12000 + 21000 + 20000 = SR 155000  EAC = [ACWP/BCWP]*BAC = [90400/85400]*155000 = SR 164075  ETC = EAC – ACWP = 164075 – 90400 = SR 73675


Download ppt "10/19/2015 12:26 AM 1 Project Cost Control. 10/19/2015 12:26 AM 2  Controlling involves making sure that the results achieved are in line with the planned."

Similar presentations


Ads by Google