Download presentation
Presentation is loading. Please wait.
Published byBernard Walters Modified over 9 years ago
1
1 PFP MSR, 3/15/2011 Particles and Fields Package Monthly Status Review (MSR) March 15, 2011 Dave Curtis, PFP PM
2
2 PFP MSR, 3/15/2011 SSL Contracting Status Provided estimated cost (in Phase E) for 5 week transition timeline
3
3 PFP MSR, 3/15/2011 Schedule Status EMs have made a lot of progress this month –All EM PWBs in test but ~2 (HVPS boards, in fab) –SEP, LPW, SWEA. MAG mechanical in assembly –STATIC TDC complete acoustics –SWIA/STATIC analyzers final parts out to fab this month EM Package I&T starts March 22 with LPW –Pushing to complete before CDR –Instrument calibrations don’t complete till after Package I&T Adjusted flight electronics test schedule to reflect reality of limited pool of test engineers –Prioritized testing No change to critical path this month –15 weeks margin to delivery –Achieved by starting flight fab prior to EM test completion for selected subsystems Working to improve post-CDR schedule. –Adjust schedule to take advantage of changes to flight software Build 1 design includes less diagnostic code, more code that is useable for Build 2 should get FSW off critical path, improve margin +2-3 weeks.
4
4 PFP MSR, 3/15/2011 Manpower RBSP-EFW instrument still not delivered – this month? –All of the people we need have transitioned 100% –Down to final thermal vac test Solar Probe Plus is starting to impact a few team members –Adding two new people around the time of CDR to make up for one retirement and people split with SPP One from RBSP, one from JDEM We are still under planned FTE rate –but climbing a bit –Mostly due to people splitting time between projects –Plan was based on conservative assumptions about covering people
5
5 PFP MSR, 3/15/2011 Accomplishments All PWBs layed out, most loaded and in test –see below On schedule for start of Package integration –LPW/PFDPU 3/22 –PFDPU/Spacecraft 4/5 Most EM Mechanical parts are in fab, many delivered –MAG sensor Assembled –SEP, LPW boom, STATIC TDC, SWIA & STATIC MCP mounts in assembly –Some part-level design work still in progress on SWIA/STATIC Last analyzer parts out for fab this month –STATIC EM TOF Acoustics Test complete successfully –SEP EM attenuator started life test SWEA FM analyzer mechanical parts delivered to SSL for plating –Forwarded to the plating house More in instrument sections…
6
6 PFP MSR, 3/15/2011 Ongoing Work Supporting Project planning process Supporting EMC, Payload, SDT working groups Completing EM board testing Completing SWIA/STATIC EM mechanical part drawings, getting parts fabricated Start PF Package EM I&T, LM EM I&T Prepare for CDR
7
7 PFP MSR, 3/15/2011 EM Status
8
8 PFP MSR, 3/15/2011 PFP RFA Status All Done!
9
9 PFP MSR, 3/15/2011 Trades, Issues HV801 issue still open –Two options: Amptek HV801, Micropac 66353 –Amptek delivered some EM HV801s Have parts for EM –Current plan is to buy HV801s from LADEE NMS, who has parts on order they no longer need –Also have an offer of some extra parts from LASP Working on an analysis to decide if the PFDPU mechanical design needs to be augmented to support the PWBs to avoid excessive displacements in vibe –MAG EM PWB has option for a center support, others do not –Looks like we can probably eliminate center support, analysis about ready for review –Analysis Submitted to GSFC –Comparing analysis technique to recent flight history.
10
10 PFP MSR, 3/15/2011 Thermal Status Updated Thermal Model delivered –being used by LM to generate thermal environments, due ~3/18 Provided boom deployment heater power requirement –last of the heater requirements Also waiting on deep dip case –Also promised by 3/18
11
11 PFP MSR, 3/15/2011 Top Risks P-21 new
12
12 PFP MSR, 3/15/2011 Risks List
13
13 PFP MSR, 3/15/2011 PFP Mass Small change to MAG sensor and EUV harness CBE this month Submitted CCR262 to reallocate NTE amongst PFP –See ‘New NTE column)
14
14 PFP MSR, 3/15/2011 Mass Tracking Chart
15
15 PFP MSR, 3/15/2011 PFP Power Small increase in EUV heater power Small decrease in LPW operational power.
16
16 PFP MSR, 3/15/2011 PFP Power Trend
17
17 PFP MSR, 3/15/2011 PFP Data Rate Per 2009-6-9 allocations from Bruce
18
18 PFP MSR, 3/15/2011 Requirements Verification Status Submitted a CCR (265) to update PFP Functional Requirements (Level 3) –some old requirements need updating Once updated, will start mapping into Verification matrix Need DOORS verification output for ICD and ERD to include in the matrix –ERD and ICD still evolving –When do we snapshot these? Boot software verification has started –against software level 5 requirements, which link back to FRD and ICD. STATIC TOF EM Acoustics test complete –Waiting on analysis of foils –Will repeat on full EM and FM
19
19 PFP MSR, 3/15/2011 MAVEN Magnetometer Status March 2011 Connerney, Sheppard, Schnurr, Oliversen, Espley, etc.
20
20 PFP MSR, 3/15/2011 GSFC/MAG - Accomplishments Last Month EM sensor assembly and pigtail completed. GSE sensor harness fabrication complete. Hypertronics connectors received; breakout PWBs assembled. Draft MAG Flight Software Requirements Specification (for PFDPU). Completed parts stress analysis for MAD board and ACHE board ( MIS MAVEN-MAG-ANYS-0020, MAVEN-MAG-ANYS-0018) EM magnetometer analog/digital (MAD) board assembly completed. EM Magnetometer board tuned w/nominal scale factors and in test. Completed Parts Control Board meeting (March 2, 2011), parts list dispositioned (XX parts of XXX total) pending meeting minutes. Initiated radiation testing plans for lot of MIL spec CD4066 quad bilateral switches. Completed rev 0 Aeroflex FPGA design; ready to burn.
21
21 PFP MSR, 3/15/2011 GSFC/MAG - Accomplishments Last Month(s) EM Sensor Assembly A/C Heater Electronics (ACHE) Board MAG Analog and Digital (MAD) Board
22
22 PFP MSR, 3/15/2011 GSFC/MAG Near Term Plans & Open Issues Complete MAG software requirements draft and iterate w/UCB. Bench test EM MAD board with FPGA logic installed, UCB simulator. Initial MAG Test Site tests to determine MAD board scale factor resistors. Temperature cycle MAD board and thermal stability tests. Continue winding FM sensor ring cores, feedback/sense bobbins, per technician availability; fabricate sensor assembly terminal boards. Draft worst case analysis of MAD board. Schedule Peer Review (tentative: May 5, 2011 @ GSFC). Workload: RBSP box level thermal vac @ APL, Juno system thermal vac @ LM
23
23 PFP MSR, 3/15/2011 MAVEN PFP SWIA Status March 2011 Jasper Halekas, SWIA Lead
24
24 PFP MSR, 3/15/2011 SWIA Progress Electrical Progress –Anode board tested –Digital board tested –Preamp/MCP loaded on preamp half Testing started, testing with digital next week –LVPS mostly loaded, starting test –Sweep PWB fabricated, being loaded –Sweep and MCP HV waiting for shield walls, cores Mechanical Progress –E-Box parts out for fabrication –Analyzer design finished, parts drawings in progress, final review before sending out for fabrication next week –Attenuator motor design nearing completion –MCP MGSE and MCP clamp stack fabricated and assembled –Manipulator MGSE fixture design in progress (for EM Cal) Detector Progress –MCP testing starting as soon as Hypertronics connectors arrive (scheduled March 14 th ship, overnight delivery)
25
25 PFP MSR, 3/15/2011 SWIA Issues Staffing/Schedule –Up to full speed on staffing –Trying to make up delays due to RBSP ME conflict and limited technician time –Currently planning to integrate and test electronics with PFDPU before testing with analyzer to mitigate schedule delay
26
26 PFP MSR, 3/15/2011 SWIA Hardware MCP Test MGSE Fixture Anode board w/ MCP Clamp Stack (channel plate not loaded, 5” diameter)
27
27 PFP MSR, 3/15/2011 MAVEN PFP SWEA Status March 2011 Dave Mitchell, SWEA Lead
28
28 PFP MSR, 3/15/2011 SWEA Status, EM - CESR Mechanical (FM) –All mechanical parts fabricated and controlled –Hemispheres and top cap sent to Switzerland for Cu 2 S coating –All sensor external parts at SSL for black nickel coating Electrical (EM) –Board assembly started – completion by mid-April Amplifier board SWEA EM disassembled to change STEREO parts for MAVEN parts
29
29 PFP MSR, 3/15/2011 SWEA Status, EM - SSL Mechanical –Pedestal fabrication and test fitting complete, ready to assemble when boards available. –Rest of SSL EM refurbished and tested. –Purge port to be clocked 25 o on FM (no impact to EM or to CESR design) LVPC –Fab complete, Tested. Digital –Fab complete, Tested. SSL EM Ready to assemble SWEA Digital Old PositionNew Position Purge Port Redesign
30
30 PFP MSR, 3/15/2011 MAVEN PFP STATIC Status March 2011 Jim McFadden, STATIC Lead
31
31 PFP MSR, 3/15/2011 STATIC Accomplishments Carbon foils mounted in TOF units survive acoustic test Carbon foils floated successfully from mica slides - improves yield Implemented automated software for analysis of carbon foil defects Completed design for carbon mounting fixtures – design prevents small bits of carbon foil from attaching to the bottom of frame during mounting EM Digital board FPGA program loaded – ready for digital board test EM TDC board loaded (see photo) EM preamp simulated with Spice to determine component value changes needed to reduce gain. EM Anode, Preamp and TDC boards in test EM LVPS loaded – ready for test Mechanical electronics box fabricated/assembled (see photos) 3 TOF units assembled (see photos) and acoustic tests performed Clean-room (320) in service – used during TOF analyzer assembly Helmholtz coil material purchased for fabrication template 3-axis manipulator for calibration being tested and tuned
32
32 PFP MSR, 3/15/2011 STATIC EM TDC
33
33 PFP MSR, 3/15/2011 STATIC TOF Assembly for Acoustics
34
34 PFP MSR, 3/15/2011 STATIC Anode Assembly for Acoustics
35
35 PFP MSR, 3/15/2011 STATIC EM Assembly for Acoustics
36
36 PFP MSR, 3/15/2011 STATIC Open Issues Carbon foil frames need to be remounted in TOF units for vibration test. Mounting fixtures for handling flight carbon foil frames need to be fabricated before additional EM carbon foils are loaded Preamp part changes needed to reduce the gain for optimal dynamic range EM HV Sweep partially loaded – waiting on shield boards (in fab) EM 15kV-MCP board partly loaded - waiting on MCP “stack stick” multiplier to return from paryline coating Waiting on second EM preamp with component changes to optimize gain (improve dynamic range) Analyzer and mechanical attenuator still in development Manipulator fixtures for calibration in development Some test harnesses and test cables still on order New calibration chamber ordered – delivery late May Additional equipment for clean-room 320 ordered (cabinets, tables, etc) Clean-room portable sink in development
37
37 PFP MSR, 3/15/2011 MAVEN PFP SEP Status March, 2011 Davin Larson, SEP Lead
38
38 PFP MSR, 3/15/2011 SEP Accomplishments 2011-03-09 Mechanical attenuator tests started. –First testing using GSE (MISG) – GSE working – but has occasional dropouts (see below). –Initial assembly had micro-switch mis-aligned which resulted in failure on first overnight test because attenuator got caught in a position with both switches open. –Micro-switches re-aligned, ready for retest. –Resolved questions about plunger force. –Performed 24 hour (1000 cycle) test in air. Successfully completed 972/1000 cycles. Failure determined due to loss of TCP/IP connection of MISG – not due to ETU. –Actuator duration vs voltage test in air performed. –First life cycle test in vacuum was incomplete due to MISG disconnects. (~2000 cycles were completed) –Second life cycle test started on 03/09 ETU Silicon detectors are diced and tested. However delivery is overdue (Craig Tindall has been sick). Flight detectors are a few weeks away. DAP board –Stuffed with parts (2 channels only) All parts now installed. –Actel programing delivered, burned and inserted. –Testing underway: Discovered that test pulsers is NOT operating properly due to change from 5V actel to 3.5V actel. Minor x2 error in pulser frequency discrepancy in FPGA (could just change the documentation) All Mechanical parts have arrived. (Baffles finally arrived) DFE light tight Test box/cable in assembly (rework actually)
39
39 PFP MSR, 3/15/2011 SEP EM Attenuator Testing
40
40 PFP MSR, 3/15/2011 SEP Open issues Detectors still needed Test pulser circuitry needs modification One channel DAC threshold level not working properly – still under investigation
41
41 PFP MSR, 3/15/2011 MAVEN PFP DCB, Power Converter & GSE Status March 2011 Dorothy Gordon Timothy Quinn Peter Berg Chris Tiu
42
42 PFP MSR, 3/15/2011 DCB Status (1) DCB ETU Testing FLASH Memory Verified o Both CPU Mode and DMA Mode tested o Bad Blocks for both DCB-ETU #1 FLASH devices logged Test Environment Refined o Simulation and Realtime testing software project consolidated o Shared source code environment used by ModelSim (FPGA Simulator) and DCB-Monitor (DCBMON) (used for bench-testing and system diagnostics) o Subsystem tests have been integrated into DCBMON o DCB ETU integrated with the MISG in Instrument Simulator mode o Instrument commands verified for all 7 interfaces o Next step: Instrument message data reception verification
43
43 PFP MSR, 3/15/2011 DCB Status (2) DCB ETU Build o Parts kitted for the second DCB ETU and associated FLASH Daughter board o Boards are currently being loaded at Digicom DCB FPGA o Design of the major FPGA subsystems is completed o Started timing analysis in preparation for Flight FPGA port o Simulation continues in conjunction with target diagnostic development and verification.
44
44 PFP MSR, 3/15/2011 DCB Test Setups DCB running GSEOS & FSW Boot Code (MISG appears next to GSEOS laptop) DCB running DCB-MON Serial port based communication provides bench test environment
45
45 PFP MSR, 3/15/2011 GSE Software Status Delivered first rev of SEP GSEOS Delivered first rev of SWEA GSEOS Added CCSDS wrapper to SEP, SWEA, SWIA messages –Provides timestamping capability for the MISG Message Data –Next step: STATIC wrapper development Provided support for Instrument and Actuator GSEOS
46
46 PFP MSR, 3/15/2011 Power Converter Status (1) REG board –Currently under test –The 28 V, the 3.3V, the 1.5V, the 5.0V, the ±5V are working and synchronized –The input start-up starts up and the board runs itself after start up In preparation for the upcoming LPW Interface test –The following subsystems need to be verified LPW current monitor Housekeeping addressing LPW ON commanding
47
47 PFP MSR, 3/15/2011 Power Converter Status (2) REG ETU under test
48
48 PFP MSR, 3/15/2011 Power Converter Status (3) IIB board –IIB ETU has been assembled and all magnetics wound –Board is in test, starting with the LPW sections first –Secondary side of LPW converters powered-on but will require some transformer turns adjustments to tune output voltages
49
49 PFP MSR, 3/15/2011 Concerns S/C Interface late changes –DCB FPGA modifications required to coordinate with S/C ICD anticipated changes and clarifications Schedule is tight –Much testing/analysis remains as we approach CDR
50
50 PFP MSR, 3/15/2011 MAVEN PFP Flight Software Status March 1 2011 Peter Harvey
51
51 PFP MSR, 3/15/2011 Boot Status Interface Documents, Meetings Reviewed updated Spacecraft ICD specification 2/9/2011 S/C requirement to Safe after 3 missed TU’s being removed. Reviewed “PDR ICD Requirements for CLFP” ; NB: infinite-reset loop IV&V No IV&V changes to Boot requirements this period FSW Development Added “SafeMe” command to Boot (LM’s request) Boot v1.0 complete Test Status Boot FSW Test Nearing Completion All Boot Packets are Displayed in RealTime, Hot Buttons installed Had to program EEPROM 1 byte at a time Awaited Confirmation that heritage Python functions will be available Retested with DCB FPGA update revision 06 CMD Rate Test Failed due to “Interface Confusion” in GSE GSEOS Status: Generally functional though issues internal error messages, and crashes periodically Draft support functions (log, wait) delivered at end of period Needs APID 11 (Memory Loads) Needs Zone Alerts (for compatibility) Limit checking error messages (uses raw values, not converted) Dates coming up August - PROM Burn
52
52 PFP MSR, 3/15/2011 Boot Status NB: PFDPU is off at this moment causing GSE “sync mark” comments
53
53 PFP MSR, 3/15/2011 Operational Status Interface Documents, Meetings Reviewed updated DFB specification (v 2/10) Alerted LASP that packet definitions do not meet S/C ICD requirement (32-bit bounds) Drafted detailed driver outline. Reviewed with LASP Reviewed updated MAG specification(v.2/22) : OK Reviewed updated S/C Early Payload I&T test description WRITELEDS format uses incorrect command code. IV&V Revisited IV&V comments w.r.t Operational Implemented all Operational-related IV&V actions (All 32 acted upon) FSW Development Transferred Boot FSW to Op FSW (e.g. EXEC, CMD, …, PWR) Removed Boot Restrictions (Turn On, etc) Wrote LPW, SSR (Real-Time) Test Status LPW, SSR in simulation Important Dates coming up March 22 – Interface test with LPW April 5 2011 – Interface test with LM
54
54 PFP MSR, 3/15/2011 Metrics Chart
55
55 PFP MSR, 3/15/2011 Margin Chart
56
56 PFP MSR, 3/15/2011 Fever Chart 1.FSW Requirements changes in the works 2.Telemetry Specification changes in the works 3.DCB ETU board currently in checkout 4.DCB GSE not yet developed
57
57 PFP MSR, 3/15/2011 FSW QA Held a telecon with NASA QA to address differences between NASA Software Assurance Plan and SSL Software Development Plan. –Resulted in a rev to the SAP –Still have a few questions about interpretation, but we are close. Waiting word from Project on how to deal with 7150.2 CMMI issue.
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.