Download presentation
Presentation is loading. Please wait.
Published byDwayne Palmer Modified over 9 years ago
1
Update on FCPS Construction/Renovation Projects March 2009
2
Cassidy Elementary – Renovation Architect: Tate.Hill.Jacobs: Architects General Contractor: D.W. Wilburn, Inc. Substantial Completion Date:August, 2010 Contract Sum:$11,069,360 Change Orders to Date:$0 Current Phase:1 March 2009
3
Cassidy Elementary – Renovation Rendering of Final Façade March 2009
4
Cassidy Elementary – Renovation March 4Pre-construction meeting held at school with Owner, A/E Team and construction personnel March 9Begin on-site staging with setting of office trailer and fencing by GC March 16Site demolition in area of new addition, including removal of existing portable classroom and location of utilities Movement of 4 classrooms to portables March 23Earth excavation for foundation systems of new addition Prepare gym stage area for demolition March 30Demolition of gym stage area over spring break March 2009
5
Cassidy Elementary – Renovation Abatement Issues Asbestos – abatement will begin spring break and continue throughout course of project, as needed Lead – no abatement activities at this time but will be addressed throughout course of project, as needed Information will be sent this week providing parents of younger children with information pertaining to lead abatement ALL abatement work will be conducted when students are NOT present in the building March 2009
6
Cassidy Elementary – Renovation Staging Area View to Portables March 2009 View from PortablesDemo Work
7
Russell Cave Elementary – Renovation Architect: Pearson & Peters Architects General Contractor: Congleton-Hacker Construction Substantial Completion Date:August, 2010 Contract Sum:$5,001,150 Change Orders to Date:$0 Current Phase:1 March 2009
8
Russell Cave Elementary – Renovation Rendering of Final Façade March 2009
9
Arlington Elementary – Renovation Architect: RossTarrant Architects General Contractor: Set to bid on April 21 Substantial Completion Date:August, 2010 Contract Sum:TBD Change Orders Pending:$36,900 (#1) Current Phase:Demolition March 2009
10
Arlington Elementary – Renovation Rendering of Final Façade March 2009
11
Arlington Elementary – Renovation February 2Phase ‘A’ demolition begins at Arlington Elementary School site March 4Phase ‘A’ progress meeting – high water table is documented, demolition scope is 75% complete Excavation of debris continues March 10Demolition of gymnasium is submitted as a change order and pricing approved March 13Gymnasium is taken down and on-site refuse continues to be excavated March 30Phase ‘B’ plans to advertise for bid. Phase ‘B’ includes the remainder of the scope of the addition/renovation project April 3Substantial completion of Phase ‘A’ is set for review April 15Final completion of Phase ‘A’. Site turned over to FCPS until award of Phase ‘B’ contract March 2009
12
Arlington Elementary – Renovation Demo – Main Bldg. March 2009 Demo – Gym
13
Bryan Station Middle – Renovation Architect: Clotfelter-Samokar Architects General Contractor: Preston Construction Group Substantial Completion Date:August, 2010 Contract Sum:$10,769,400 Change Orders to Date:$0 Current Phase:Phase 1 to begin June 1 March 2009
14
Bryan Station Middle – Renovation Rendering of Final Façade March 2009
15
Leestown Middle – Renovation Architect: Lucas/Schwering Architects General Contractor: Set to bid on April 9 Substantial Completion Date:August, 2010 Contract Sum:TBD Change Orders to Date:$0 Current Phase:N/A March 2009
16
Leestown Middle – Renovation Rendering of Final Façade March 2009
17
Lafayette High Stadium – Replacement Architect: Strand & Associates General Contractor: Set to bid mid-July Substantial Completion Date:July, 2010 Contract Sum:TBD Change Orders to Date:$0 Current Phase:Construction Documents March 2009
18
Lafayette High Stadium – Replacement Rendering of Stadium March 2009
19
Central Bus Garage – Adaptive Reuse Architect: Lucas/Schwering Architects General Contractor: Set to bid on April 23 Substantial Completion Date:August, 2009 Contract Sum:TBD Change Orders to Date:$0 Current Phase:Construction Documents March 2009
20
Central Bus Garage – Adaptive Reuse Façade March 2009
21
Central Bus Garage – Adaptive Reuse Proposed Floor Plan March 2009
22
2009 District Facilities Plan Approved by Kentucky Board of Education February 2009 March 2009
23
2009 District Facilities Plan 2009-10 Projects New Elementary @ Keithshire Equine/Agriscience Center Clays Mill Elementary Renovation Tates Creek Middle Renovation Yates Elementary Renovation March 2009
24
2009 District Facilities Plan 2010-11 Projects Breckinridge Elementary Renovation Cardinal Valley Elementary Renovation Mary Todd Elementary Renovation Millcreek Elementary Renovation March 2009
25
Tonight’s Agenda Items Project Agenda Item Clays Mill Elementary Approval of Design Consultant Clotfelter-Samokar Architects Yates Elementary Approval of Design Consultant ShermanCarterBarnhart Architects Tates Creek Middle Approval of Design Consultant RossTarrant Architects Elementary @ Keithshire Approval of Design Consultant GBBN Architects Equine/Agriscience Center Approval of Design Consultant Tate.Hill.Jacobs: Architects Arlington Elementary Approval of Change Order #1—Demolition of Gym $36,900 Central Bus Garage Approval of Construction Documents & Advertisement for Bids $6,039,531 Bryan Station Middle Approval of Bid, Revised BG-1 & GC Contract Preston Construction Group: $10,769,400 Total Project Cost: $13,345,600 March 2009
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.