09/28/07Shutdown’07 Week 8 F.G. Garcia1 MTA beam line installation Weekly Report September 28, 2007 Period covered: September 24 th September 28 th (Week 8) MTA – Week 6
2
09/28/07Shutdown’07 Week 8 F.G. Garcia2 MTA Weekly Report – Week 8 Electrical Work Tunnel Work Termination of load cables 100% complete Termination of the instrumentation 96% complete Vacuum instrumentation is 44% complete thanks to B. Brooker and Rosie T&M pulled a 480VAC 3-wire cable from the Linac panel to the new MTA disconnect box (PEI room) Alignment Awaiting on the surveyors to rechecked the beam line components based on the latest beam sheet Mostly corrections will be elevation related Due to lab priorities, task was delayed a couple of days… AMG accommodated MTA job the best they could Currently a crew is in the Linac enclosure
3
09/28/07Shutdown’07 Week 8 F.G. Garcia3 MTA Weekly Report – Week 8 LCW work 100% complete All magnets connected to the water manifold and valved in. Vacuum work Linac side has priority until Oct 2 nd Coming along very well… 95% spool pieces are made and dry-fit Start immediately connecting the spool pieces after alignment Effort starts today All ion pumps in the Linac side (2) are installed Stand is delivered at the MTA side Instrumentation group installed MW cans on the stands Magnificent help from Instrumentation group Oct 1 st and Oct 2 nd : - Finalize the spool piece connections - Start roughing vacuum as soon as possible - Concentrate in MTA side after Oct 3 rd
4
09/28/07Shutdown’07 Week 8 F.G. Garcia4 MTA Weekly Report – Week 8 Mechanical installation Beam stop assembled, tested and delivered Outstanding group effort to meet the deadline Awaiting the final alignment of the beam pipe thru the shielding wall and installation of the beam valve in order to proceed with the beam stop installation Expect to be complete 9/28 Shielding installation Cable penetration shielding is complete Safety can lock the penetrations To Do: shielding around the beam pipe Awaiting for the beam pipe to be aligned Material is available and procedure has been developed Oct 1 st and Oct 2 nd : Finalize the shielding requirements for beam operation in Linac
5
09/28/07Shutdown’07 Week 8 F.G. Garcia5 Toroid MW (total of 4 MW system) BPM (total of 8 BPM system) MTA Q1 Ion pump #1 Ion pump #2 Linac side Beam Valve #1 Beam Valve #2 MTA Q2 MTA Q3 MTA Q4 MTA Q5 MTA Q6 MTA Q7 MTA Q9 MTA Q8 Beam Stop Today’s activities