Department of Public Works Arroyo Seco Casting Pond Renovations Contract Award to Mallcraft, Inc.
2
Department of Public Works Existing Pond Built in 1955 Asphalt pond about 24” deep Asphalt perimeter for fly casting practice
3
Department of Public Works Need for the Project Existing Pond has substantial leaks Pond floor and perimeter are damaged
4
Department of Public Works Proposed Design Will occupy same footprint About 18-24” deep after renovation Perimeter Improvements
5
Department of Public Works Construction Specifics Original Design Concept Add new surface over existing pond New drainage system Revised Concept Strengthened lining – thicker, more reinforced Strengthened access ramp Enlarged drainage system
6
Department of Public Works Bid Results Engineer’s estimate $309,510 Bid results 12 bids received $283,830 – 8% under Engineer’s Estimate
7
Department of Public Works Finance Original sources ($265,000 total) Prop A-$182,107 Prop 40-$ 57,893 Private -$ 25,000 Project Cost ($438,000 total) Contract Award Not to Exceed Amount-$312,000 Design, Engineering, Administration -$126,000 Shortfall -$173,000
8
Department of Public Works Recommended Funding Sources Shortfall -$173,000 $100,000 from Impact Fee interest $73,000 State Prop ‘A’ funds from Lower Arroyo – Habitat Restoration fund.