Download presentation
Presentation is loading. Please wait.
Published byAndrew Mills Modified over 9 years ago
1
Operator Reports for New Technologies Vanessa Wike, P.E. Statewide Engineering Coordinator (907) 269-7696 555 Cordova St. Anchorage, AK 99501 vanessa.wike@alaska.gov Department of Environmental Conservation Drinking Water Program
2
Overview New rules are placing a greater emphasis on the QA/QC of the treatment processes: – A strong focus is being placed on whether the plant is operating within the approved design/construction specifications. Biggest change will be for UV systems: – Additional training requirements will be included in operational approvals. Manufacturer Training (bulb change-out, etc). Consultant Training (dosage calculations, operator reports). – MOR’s: “Set Point” MOR’s. “Calculated Dose” MOR’s.
3
MOR’s MOR’s for newer Surface Water Treatment technologies will be custom made for each system. The format of the MOR will depend on parameters set during the design of the system. Instead of monitoring to identify when things go wrong, monitoring will now be more important in identifying when things are starting to go wrong. Going > Going > Going > Gone
4
Example “Daily” Report Monthly Operator Report, for “Set Point” Designed UV Treatment Plant
5
Example “Daily” Report Monthly Operator Report, for “Set Point” Designed UV Treatment Plant
6
Example “Daily” Report Monthly Operator Report, for “Set Point” Designed UV Treatment Plant Intensity (Dosage) is set during engineering plan review, for specific flow rate. Every 4 hours: ** Time ** Intensity ** Flow
7
Example “Daily” Report Monthly Operator Report, for “Set Point” Designed UV Treatment Plant Intensity
8
* Chapter 6 EPA UV Guidance Manual, 2006. Example “Daily” Report Monthly Operator Report, for “Set Point” Designed UV Treatment Plant Every MONTH do sensor calibration check. Must Report amount of “Off-Spec” water.
9
Example “Daily” Report Monthly Operator Report, for “Calculated Dose” Designed UV Treatment Plant* * Chapter 6 EPA UV Guidance Manual, 2006.
10
Example “Daily” Report Monthly Operator Report, for “Calculated Dose” Designed UV Treatment Plant* * Chapter 6 EPA UV Guidance Manual, 2006.
11
Example “Daily” Report Monthly Operator Report, for “Calculated Dose” Designed UV Treatment Plant* * Chapter 6 EPA UV Guidance Manual, 2006. A required dose is set during engineering plan review. A “Validated Dose” is then calculated, by dividing the calculated dose by a verification factor and a correction factor. This is done for every recorded dose on the MOR. The “Calculated Dose” approach does not have a single compliance point, but instead has an approved envelope of operational parameters (flow, dose, transmittance).
12
Example “Daily” Report Monthly Operator Report, for “Calculated Dose” Designed UV Treatment Plant* * Chapter 6 EPA UV Guidance Manual, 2006.
13
Example “Daily” Report Monthly Operator Report, for “Calculated Dose” Designed UV Treatment Plant* * Chapter 6 EPA UV Guidance Manual, 2006. Each UV Reactor will have a separate MOR. “Off-Spec” production must be indicated on each report. Separate forms are required for calibration/verification of the sensor, UVT analyzer and flow meter
14
Example “Off-Spec” Report Monthly Operator Report, for “Calculated Dose” Designed UV Treatment Plant* * Chapter 6 EPA UV Guidance Manual, 2006.
15
Example “Off-Spec” Report Monthly Operator Report, for “Calculated Dose” Designed UV Treatment Plant* * Chapter 6 EPA UV Guidance Manual, 2006.
16
Example “Off-Spec” Report Monthly Operator Report, for “Calculated Dose” Designed UV Treatment Plant* * Chapter 6 EPA UV Guidance Manual, 2006. “Off-Spec” operations must be reported (number of events and volume of water produced). “Off-Spec” can occur because: Sensor is not in calibration, or is outside approved limits. Analyzer is not in calibration, or is outside approved limits. Flow meter is not in calibration, or is outside approved limits. To meet LT2, 95% of the water must be treated to validated limits.
17
Keys to Succeeding with New Technologies Monitoring: Residual > Process Control Limits Accurate, Consistent Readings Be Wary of Complacency Don’t let the instruments think for you! Treat your instruments with respect: Calibrate, Verify, Maintain If you have questions, please give us a call.
18
Operator Reports for New Technologies Vanessa Wike, P.E. Statewide Engineering Coordinator (907) 269-7696 555 Cordova St. Anchorage, AK 99501 vanessa.wike@alaska.gov Department of Environmental Conservation Drinking Water Program
Similar presentations
© 2024 SlidePlayer.com. Inc.
All rights reserved.