2
Missoula’s LRTP Process Missoula Growth Workshop Base Case Scenario Envision Missoula Workshops Vision Scenario Envision Missoula Summit Architecture Scenario 2035 Planning Scenario Fiscally Constrained 2035 Planning Scenario 4 Project Lists LRTP Project Report Draft Plan Document Public Survey Ranking Criteria Cost and Revenue Analysis Final Public Review of Plan (Open House) Final Plan Document Modeling Envision Missoula Report Planning Summit Report
3
Public Involvement Visioning workshops November 13, 14, 15 Planning Summit February 13, 14 Explored the land use/transportation relationship
4
Public Survey Conducted by University of Montana Shows key priorities of public What improvements they found most important
5
Public Survey (cont.)
6
What Are the Best Transportation Improvements?
8
Potential Transportation Projects Roadway Expansion Bicycle/Pedestrian Projects Transit Operating and Capital Investments Enhancements for other Modes Operations Maintenance Intersection Improvements ITS
9
Why Are We Here? We are here to define needs for the LRTP in light of what we have learned up to this point. At this point needs may be FUNDED or UNFUNDED. Funding and prioritization will come later in the process What project are defined as “Needs”
10
Project Categories Current Needs (today’s deficiencies) Accruing Needs (things we will need by 2035) Illustrative Needs (things we will need after 2035) “Parking Lot” (things we probably won’t need, given the public visioning process and land use/development directions)
11
Where Do LRTP Projects Come From? Have are derived from multiple sources: –Existing project lists from Public Agencies –Envision Missoula –Needs Created by Future Development –Safety Consultations –Other ideas
12
Project Source – Visioning: “Business as Usual “Future
13
Project Source – Visioning: “Satellite Centers” Future
14
Project Source – Visioning: “Focus Inward” Future
15
Project Source – Future Development (2035)
16
Project Source – Future Development (Next 100,000)
17
Today’s Traffic (2005)
18
Future Traffic 2035
19
Future Traffic (Beyond 2035)
20
Project Source -- Safety Consultations Friday April 4 Missoula County Engineering –Higgins-Hill-Beckwith –Reserve/Mullan Safety & Congestion –Reserve St Corridor Safety & Congestion –Desmet Interchange Safety Improvement –Palmer St Signal –Safety Improvement SW Missoula
21
Project Source -- Safety Consultations Missoula County Education/Behavioral –SKSC Education Programs (DUI & seatbelt focus) –TV & Radio PSAs (designated drivers & buckle up) –Responsible Alcohol Training (servers) –Child Passenger Safety (training & inspection) –Bait & Belt Campaign (seatbelt rewards) –Home Free Missoula (cab rides home) –Your Choice 2007 (DUI re-inactment)
22
Project Source -- Safety Data MT high crash locations include: –US 93 north & south of Missoula –I-90 east and west of Missoula –US 12 from US 93 to Lolo Pass Ped crashes inside city steady to decreasing, outside city trending up Bike crashes inside city steady but high, outside city steady Motorcycle crashes inside and outside city slowly increasing in context of rapid increases statewide
23
Next Steps Needs will be costed against available revenue to define the “funding gap” Needed projects will be prioritized for funding using criteria from the public survey & public involvement Those with the highest score will be recommended for funding Recommended “service package” will be reviewed for key environmental issues Recommended service package will be modeled with respect to travel demand and air quality