OPSM 301 Operations Management Class 19: Project Management: MS Project Koç University Zeynep Aksin

Similar presentations


Presentation on theme: "OPSM 301 Operations Management Class 19: Project Management: MS Project Koç University Zeynep Aksin"— Presentation transcript:

1 OPSM 301 Operations Management Class 19: Project Management: MS Project Koç University Zeynep Aksin zaksin@ku.edu.tr

2 Using Microsoft Project Program 3.1

3 Using Microsoft Project Program 3.2

4 Using Microsoft Project Program 3.3

5 Using Microsoft Project Program 3.4

6 Using Microsoft Project Program 3.5

7 Using Microsoft Project Program 3.6

8 Using Microsoft Project Program 3.7

9 Exercise: Advertising Campaign ActivityPredecessorsTime Resource Progress A. Media bidsnone2 wks Ali100% B. Ad conceptnone6 Veli100% C. Pilot layoutsB3 Veli30% D. Select mediaA8 Ali20% E. Client approvalA,C6 Veli0% F. Pre-productionB8 Ali0% G. Final productionE,F5 Veli0% H. Launch campaignD,G0

10 Advertising Campaign project in MS Project  Open MS Project, Select View-> Gantt which should be the default  Enter task names  Enter durations  Enter precedence relationships, view network  View critical activities: Project>Filtered for:critical  Suppose we assign the above tasks to different people: Ali and Veli (Tools>Assign Resources)  View>Resource Graph  Level resources to alleviate conflict  Track project progress

11 Resource Allocation in Project Management  So far: CPM/PERT methods for scheduling  Ignored resource constraints  In reality, each task requires at least one resource, resources are mostly shared  Resource allocation is assignment of resources to scheduled tasks –Scheduleds may have to be changed to accommodate resource issues

12 Resource Loading  The amount of load on each resource (summation over all tasks which need that resource) on a period-by-period basis  Good tool in early scheduling  A seperate histogram for each resource is developed

13 Resource Leveling Objectives:  Minimize the period-by-period variations in resource loading by shifting tasks within their slack allowances  Minimize over-usage of resources  Create a smoother distribution of resource usage –Reduced set-up costs (hiring, training, laying off) –Improves morale –Needs less hands-on managemet

14 Different Approaches possible  If time constraint is the priority, no adjustments should be made on the critical path  If resource constraint is the priority, project duration can be extended by adjusting critical activities  Earliest and Lates Start Times and Slack information is used in Resource Leveling  MS Project facilitates resource leveling