Download presentation
Presentation is loading. Please wait.
1
Project Update Colorado Esplanade Project
2
Agenda Colorado Esplanade Project Overview Current Work
3
Overview
4
Overview 96 New Trees -71 Mexican Sycamores -13 Kentia Palms
WYNDHAM 96 New Trees -71 Mexican Sycamores -13 Kentia Palms -12 Rainbow Eucalyptus 17 Trees Relocated 23 Trees Protected in Place 5.3 New Trees per 1Tree Removed Bring paver and pass around TONGVA PARK
5
Color Rendering of Proposed Project
Colorado Esplanade Explain paver types, decking, string lights, and trees (type) Colorado Avenue Esplanade project will be complete before Expo begins carrying passengers
6
Color Rendering of Proposed Project
Colorado Esplanade Explain paver types, decking, string lights, and trees (type) Festival lighting will be placed approximately every 25 feet. Outdoor furniture will be added.
7
Schedule Awarded Start Date Duration: 12 months January 27, 2015
March 16, 2015
8
Current Work
9
Current Work Placing structural soil along north sidewalk.
Structural soil supports the sidewalk above it while encouraging root growth. Placing structural soil along north sidewalk.
10
Current Work Elements of the finished project: charcoal concrete
The driveway at 1st Court (alley) and Colorado Avenue will feature the same concrete.
11
Current Work Elements of the finished project: pavers
12
Current Work Elements of the finished project: trees
The 96 new trees will be watered with recycled via drip water systems.
13
Current Work Elements of the finished project: trees
14
Public Outreach Explanation and Way Finding
15
Public Outreach Print material
16
Phasing Northside Colorado Avenue Construction
2 WB traffic lanes will be maintained at all times PHASE A Southside Colorado Avenue Construction -2 WB traffic lanes will be maintained at all times -Main St will be realigned connecting to 2nd St -Lane closures and 1-way for <duration> PHASE B Discuss work on sidewalk, road… Before moving on to Phase B you will see pavers, trees, etc… things looking complete and tidy
17
Phase A Phase B WYNDAM Bring paver and pass around TONGVA PARK
18
Phase A Phase B WYNDAM Bring paver and pass around TONGVA PARK
19
Phase B Phase B will also have a pedestrian walkway and business access Bring paver and pass around
20
Merging 2nd Street and Main Street
Moving of sewer siphon was first step in reconfiguring Main Street; some closures will be necessarily to complete the work.
21
Main Street Before and After Project
22
Intersection & Driveway Work
Will be done at night during both phases
23
Public Outreach Visit businesses within 500-foot radius of project boundaries -Interview for business profiles -Leave project FAQs Distribute contact information - -Hotline:
24
Q&A Colorado Esplanade
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.