1 Questions

2 The use of historical cost data for the prediction of early stage cost estimates is common place, but the reliability and validity of such data, particularly when extracted from contractor's tender documentation, is often questionable. Explain how the difficulties posed by the use of such data may be addressed in a holistic cost planning process.

3 Cost Planning process

4 The principles of elemental cost control
The three basic principles are: Frame of reference the first is a realistic first estimate or cost limit of the overall construction cost of the building. The second is planning how the estimate should be spent among the elements of the building. Method of checking Remedial action.

5 Using wrong data will lead to a wrong estimating and produce wrong cost limit .
This will produce a wrong cost target for all or some elements. Will affect the design, techniques, qualities and quantities of the building.

6 Once a contract has been completed and the Defects Liability Period expired, the Contractor is entitled to be paid the Final Valuation. In order to make this payment, it is necessary to produce a Final Account. Detail the process and information required in order to compile a Final Account, highlighting the difference between ‘Lumpsum Contracts’ and ‘Measured Contracts’. There are two methods of production for a Final Account. Explain the two approaches giving the advantages and disadvantages of both methods.

7 The Detail of the process
The Employer’s QS prepare the account, fully price it, (or give the Contractor an opportunity to provide rates and/or prices where necessary), send a copy to the Contractor for examination. The areas of disagreement requiring the QS and Contractor's surveyor to meet, discuss and negotiate the areas, items or rates in dispute until the whole document is agreed. The Contractor will then sign the summary page to record agreement, The QS will report to the Architect, pass on a copy for the Architect's records and for calculation of post-contract fees. The Final Valuation Certificate will then be prepared using the Final Account total Passed to the Employer for payment.

8 The information required in order to compile a Final Account
The following sections are normally required for Lump Sum contracts: Summary of Account Prime Cost Sums - adjustments Provisional Sums - adjustments Variation accounts Provisional Items - adjustments Fluctuations, i.e. increased costs (labour, materials. statutory contributions, levies and taxes) Contractor’s claims.

9 THE DIFFERENCE BETWEEN ‘LUMPSUM CONTRACTS’ AND ‘MEASURED CONTRACTS
Putting together the final account depends largely on the quantity surveyor but is usually based on the payment mechanism: Lump Sum Contracts The final account will start with that sum, and will proceed to identify the additions and deductions Measured Contracts the final account will be built up from a zero and ‘Ascertained Final Sum’

10 There are two methods of production for Final Account.
Disadvantages Advantages Description Method The account document is likely to be thicker due to repetition of items in different variations and space needed for separate totals. Cost of each variation is obvious showing total values for omissions and additions. Bill omissions and additions are listed separately under each Architect's Instruction 1 The cost of each variation is not individually available Less items, resulting in a compact document that is quicker to prepare and price All omissions can be collected together, and similarly all additions, with each group identified under the appropriate work section or trade heading. 2

11 A construction project client’s interpretation of lifespan is not necessarily the physical life of the building that they commission. Using examples where possible, explain what is meant by lifespan from a client's perspective with reference to the physical, economic and functional interpretations.

12 Definition of a building ‘life’
Long time view Short time view life can be considered to be the lesser of: economic, the value of the land is greater than the building itself complete refurbishment may required, Functional: is the length of time the building fulfils the functional needs of the client’s activities before it becomes obsolete. physical life: lifespan until physical deterioration requires demolition.

13 Many factors affect the ‘service life’ of a building and its constituent components. Identify what these factors are and explain how they affect ‘service life’. ?

14 Factors affecting Life of building
Environmental factors: is the building sheltered spot or exposed Sea air, a polluted industrial atmosphere, exposure to flooding extreme cases earthquake or volcanic activity Design and specification factors Construction factors: the quality of workmanship on site cutting corners to make up time due to delays on-site; product or component substitution due to over-long procurement periods; inadequate knowledge about new products. Organizational /operational factors: the level of wear and tear to which the building or asset is subject in normal use the type of use, hours of use, density of use and so on. The maintenance regime adopted

15 Critically evaluate the need for elemental cost planning within a construction industry that you are familiar with.

16 The principles of elemental cost control
The three basic principles are: There must be a frame of reference There must be a method of checking There must be a means of taking remedial action.

17 The frame of reference Two parameters are set:
the first is a realistic first estimate or cost limit of the overall construction cost of the building. The second is planning how the estimate should be spent among the elements of the building.

18 1- realistic first estimate or cost limit
can be arrived using any of the estimating methods Or, the client can define a cost limit to which the building must be designed. Then, QS breakdown the cost over various parts of the building It makes it much easier to control the overall cost as the design becomes more detailed. the cost of each individual part must be independent Each discrete portion of the building is allocated a cost known as a ‘cost target’.

19 The method of checking In control system terms this is the monitoring stage. As the detail emerges, the quantity surveyor must put an accurate cost against that detail and compare the new figures with the cost targets set in the frame of reference.

20 Remedial action In control system terms this is the ‘action’ stage.
1- design decisions will affect the cost(s) 2- The cost difference between cost target and detail design cost is distributed for the affected element and adjusting the overall cost to keep within the first estimate. 3- If the cost difference is too large then alternative materials or building techniques may have to be considered 4- The client may decide to increase the overall cost rather than change the design.

21 The rules for measurement of external cladding are found in Section H of SMM7, H31 Metal Profiled sheet cladding/covering/siding. From your knowledge of the rules of measurement explain how the following elements would be measured with regards to external cladding: External Cladding in Walls/Roofs/Ceilings/Floors etc. Isolated Beams and Columns Flashings Abutments Finished Angles Holes Firestopping Access Panels

22 “It is not so much a question of how long a building or component may last, but of how long it will be retained” Allan Ashworth Discuss this statement in relation to deterioration and obsolescence of buildings and their constituent components.

23 Uncertainty and service life data
Service life is the period of time during which a building or a constituent part meets the requirements of the client/owner Lifespan or service life prediction required for buildings and all their constituent components There is a lack of factual data concerning component lifespan and durability Although there are a number of sources of published service life and performance data – all imperfect

24 Uncertainty and service life prediction
Notional lifespan vs estimates based on: Published sources Historical expenditure data Empirical data (actual observed) Judgement / ‘best guess’ actual lifespan affected by variability in: Component quality Workmanship In-use conditions/ patterns of use Exposure to external environment – wind, rain, snow, pollutants, sun Level of maintenance “Data at present are rarely available to indicate reliably the degradation of even very similar buildings or components, since in practice there are many variables which affect service life”. BSISO :2000 Buildings and Constructed Assets- Service Life Planning

25 Uncertainty and Sensitivity Analysis
Sensitivity Analysis is a technique used to test the effects of uncertainty and assumptions on the results of WLC exercises Sensitivity Analysis is used to determine how ‘sensitive’ results of a WLC forecast are to changing assumptions about the input variables “During a LCC analysis, a large number of assumptions need to be made, for example the discount rate to be applied and the life of the project and its various components. It is necessary to test the sensitivity of these assumptions in order to avoid any possible error in the overall analysis” [Ashworth] “A way of testing whether the results of the LCC analysis are sound is to repeat the calculations in a methodical manner by changing the values that have been attributed to the assumptions” [Ferry and Brandon]

26 In producing a Cost Value Reconciliation, it is important to establish not only the anticipated final account sum and the gross value of work executed to date, but some contractors will also make use of the net gross value. Detail the significance of the various pieces of information that would be contained in a gross value exercise.

27 The contents of a gross valuation
Completed contractor’s works Preliminaries Unfixed material on and off site Variations Retention Fluctuations Claims Liquidated damages Advanced payments (if applicable)

28 Interim and Final accounts are key cost control mechanisms referred to during and at the completion of any construction project. Prepare a short report to your client explaining the information they contain and why they are key documents.

29 The contents of Interim a gross valuation
Completed contractor’s works Preliminaries Unfixed material on and off site Variations Retention Fluctuations Claims Liquidated damages Advanced payments (if applicable)

30 What are the Contents of the Final Account?
The following sections are normally required for Lump Sum contracts: Summary of Account Prime Cost Sums - adjustments Provisional Sums - adjustments Variation accounts Provisional Items – adjustments (Adjustment of approximate quantities). Fluctuations, i.e. increased costs (labour, materials. statutory contributions, levies and taxes) Contractor’s claims.

31 The cost planning process starts when the client perceives a need for a building.
Discuss the steps the cost planning passed by.

32 No one can forecast the future and hence the true cost of the building will remain unknown until the Final account. Explain this statement and discuss the factor affecting the accuracy What are the factors affecting the selection of forecast cost of a building

33 FACTORS TO IMPROVE THE ACCURACY OF A FIRST ESTIMATE
Quantity Quality Market Building Services Location Design economics Final notes

34 Selecting a method for forecasting costs
depends on several factors: Availability of project information Time Availability of cost data Preference and familiarity

35 Evaluate the contract selection methods.
What is the best method for high raise building?

36 Methods of contract selection
There are Four methods: Open tender Selective tendering Nomination Serial tendering

37 Discuss the elements of Cost/Value Reconciliation

38 Production of Cost/Value data, and the Cost/Value Reconciliation
Dates of interim valuation and CVR Copy of the architect’s interim valuation certificate Analysis of all Bill items claimed broken down into their respective headings All details relating to both the costs and value

39 Analyzing the Value (revenue)
The analysis of value for a CVR can be facilitated by an analysis of all Bill items claimed broken down into their respective headings of Labour Sub-contractor Plant Material Overhead Profit This analysis can be used as part of the process of building up a figure to represent the gross value of executed work to date.

40 Costs Labour Sub-contractors Plant Haulage:
bonuses non-productive overtime ( for accelerated works) Sub-contractors Qs produce a detailed schedule of the contractor’s cost liabilities The value of work invoiced by and paid to the sub-contractor. evaluation of all executed work not yet invoiced, attention to any variations to sub-contractors work Plant Hired, the operating costs, repairs and maintenance, depreciation and residual values. Haulage: haulage and transport charges for transporting plant, materials and personnel (external or internal)

41 Costs …. (cont.) Materials Additional Costs Overheads
Labour and material shortage (brought from other source) Overheads Head office and site office Reserves and Contingencies: If profit margin appears to be higher than original figure Hold profit for heading unprofitable activities create a contingency fund) insert cost reserves against some of the heads Remarks. comments relating to these and the resulting potential financial consequence.