Life Support Capital Project Community Meeting June 17, 2015
2
Agenda for tonight The Project Overview – Where are we at now? – What can we expect in the next 6 months? – Other updates
3
From last Meeting PCL provided all sub contractors with routes to access the site – exit at Carling not Parkdale PCL is installing signs to remind contractors they cannot park in Ruskin lot Submissions to City for traffic calming measures on Melrose – they intend to make the east side of Melrose no stopping for the duration of the re-location ambulance entrance on Melrose
4
What has been done so far? Assessments of houses completed Moving Hydro Duct Bank on campus New ambulance entrance – Melrose New access to 190 Melrose completed Water filtration has started Upgrades to the Power Plant Work has started on Loading Docks
5
New ambulance entrance – Melrose – recent changes made to slope the side walk for easy access by stretche rs
6
New access to 190 Melrose
7
Water Filtration System
8
Reworking TOH Loading Docks
9
And what is next? New Ambulance Entrance in use as of July 2 Work internal to TOH (Linen, Processing) Schedule revisions – Same end dates (Jan 2018 for Tower; Fall 2019 for new entrance and project completion) – But excavation for the Tower will start October 2015.
10
Other Items Parking lot on Ruskin will be resurfaced over the summer – Plan is to close part for 4 weeks and the entire lot for 3 weeks – Will be flag men and others available to direct patients to other parking lots – Start date is June 22, 2015
13
Some things to note Web site for information and email address for issues Regular updates are being provided to the Community Association – how is this working?