THE DONEGAL HIGH SCHOOL PROJECT Lessons Learned from a Referendum Campaign
2
History Then … Focus – “keep taxes low” Decades of deferred maintenance Significant growth in student population Deficit Now … New board – move Donegal forward Major tax increase Develop long-range plan
3
Referendum – Round 1 Comprehensive K-12 Plan Included athletic facilities $117,000,000 Special election Designs and elevations developed “Yes” votes energized … but so were “no” votes Defeated 72% to 28%
4
Referendum – Round 2 Focused on common ground from first referendum … New High School Eliminated “moving parts” Held community forums Acknowledged public input when appropriate: No additional architect fees No special election Eliminated “hot buttons” Modified design Defeated – 52% to 48% (176 votes)
5
Observation Two approaches to referendum: 1. Sell the project board/administration develops to voters, or 2. Ask the voters what they can support and develop project around those expectations
6
Lesson #1 Every decision is impacted when a referendum is pending: Annual budget Contract negotiations Conference attendance Customer service
7
Lesson #2 Keep it simple … Then make it more simple Acronyms, terms, Acts, etc. need to be defined Assume zero knowledge of our world … but don’t “talk down” Minimum information as part of presentation – but: Anticipate questions and have understandable answer ready (state reimbursement, zoning issues, PSERS rate, etc.)
8
Lesson #3 Don’t assume support (or lack thereof) from: Teachers Parents Senior citizens
9
Lesson #4 Consider community standards in your presentations: Too flashy? Too tacky?
10
Lesson #5 Less is more: Remove excess “moving parts” Focus on most important item – example: overcrowded conditions Avoid temptation to answer every question – “I don’t know” or “I can’t predict” is acceptable Ability to say “we haven’t decided … what do you think?”
11
Lesson #6 Stick to the facts, don’t: Embellish Criticize previous board decisions Predict
12
Lesson #7 Remove reasons to vote “no:” Athletics Impact to low-income tax payers Perceptions of excess (“weight room” vs. “fitness center;” “art classroom” vs. “art studio,” etc.) Architect fees
13
Lesson #8 Consider “customer service” impact when developing procedures: Right to Know requests “Live” person vs. automated attendant Board meetings
14
Lesson #9 Recognize that matters beyond your control may occur: Poor economy Election day weather Stealth campaign Placement of question on ballot
15
Lesson #10 Consider “lessons learned” – even if no referendum on the horizon; never too early to: Listen Give credit to community, others Improve relations Build community support/understanding Identify key communicators – including opposition: Civic organizations, seniors, realtors, developers, municipal authorities, ministerium, parents, staff Develop communication links: E-mail list, breakfasts, community events
16
Lesson #11 If you anticipate referendum - plan early Develop strategy: Sell vs. listen Large vs. small Once vs. multiple Prepare to modify plans – incorporate ideas because “we heard you say …” Communicate message – then repeat Develop back up plan
17
Summary Voter support of a referendum for building projects is possible: As referendum becomes more common Where public trust is in place As districts develop and implement PR strategies
18
Contact information: Amy J. Swartz, PRSBA Business Administrator Donegal School District 1051 Koser Road Mount Joy, PA 17552 (717) 492-1305 amy.swartz@donegal.k12.pa.us