Load Management SMUD & Demand Response Jim Parks CEC Load Management Standards Scoping Workshop March 3, 2008.

Similar presentations


Presentation on theme: "Load Management SMUD & Demand Response Jim Parks CEC Load Management Standards Scoping Workshop March 3, 2008."— Presentation transcript:

1 Load Management SMUD & Demand Response Jim Parks CEC Load Management Standards Scoping Workshop March 3, 2008

2 SMUD SMUD System Load Highest 50 hours responsible for 500 MW System load projected to grow by 15% over next 10 years (including EE) Resource gap projected in 2012 and beyond due to expiring bilateral and renewable contracts

3 SMUD SMUD Customer Policies Preservation of local decision-making and control are vital to ensure public power systems can provide solutions that best meet the needs of their customers  The District is primarily accountable to its customer-owners  Community citizens have a direct voice in utility decisions Compact with the Customer ―To meet anticipated load growth while balancing environmental and customer service goals, SMUD must implement:  Integrated EE programs which focus on peak  A robust AMI infrastructure  Rates which reflect time-differentiated costs  Strong and active dispatchable LM programs  Construction of clean, renewable plant Held series of ~40 focus groups around compact with customer concepts with all customer classes August – November 2007

4 SMUD AMI Activities December 2005: Completed initial AMI Business Case March 2006: Presented AMR drive-by strategy December 2006: Board approved AMR contract January 2007: Began converting routes to AMR January 2007: Board requested AMI Business Case Update May 2008: Presented AMI Business Case Update May 2008: SMUD embarked on AMI project

5 SMUD AMI Requirements Two-way communications Communications protocol agnostic Robust, secure, and scalable Interval data and TOU capabilities Home Area Network agnostic Enables programmable communicating thermostat control and in home displays Enables end-to-end system efficiencies―from generator to end use

6 SMUD AMI Project Timeline AMI RFP – 2 nd Quarter 2008 AMI Selection – 4 th Quarter 2008 AMI Acceptance Test – 2 nd Quarter 2009 Full Deployment – 2009 - 2012

7 SMUD SMUD Rates Policy District’s rates will be designed to balance and achieve the following goals:  Reflect the cost of energy when it is used  Reduce use on peak  Encourage energy efficiency and conservation  Minimize “sticker” shock in the transition from one rate design to another  Offer flexibility and options  Be simple and easy to understand  Meet the needs of people with fixed incomes and severe medical conditions  Equitably allocate costs across customer classes

8 SMUD Rate Concepts Under Consideration Large Commercial (1> MW)  Basic TOU – 4-month summer, 3 pricing period TOU rate that is energy only  TOU Demand – Same as Basic TOU with addition of a super-peak demand charge  Critical Peak Pricing – Basic TOU with a risk discount and a critical peak price on call days  Real Time Pricing – Hourly energy prices on a day-ahead basis Medium Commercial (300 kW – 999 kW)  Basic TOU  TOU Demand  Critical Peak Pricing Small Commercial (<300 kW)  Basic TOU  Critical Peak Pricing Residential  3-Tier Increasing Block – Standard rate with price risk premium  TOU/Tier – Standard tier rate with 3-hour super peak period  Critical Peak Pricing – TOU/Tier with risk discount and critical peak price on call days

9 SMUD Focus Group Findings on Rates General:  Customers readily understood that SMUD’s cost of supplying energy is higher in the summer, especially in very hot weather  Customers understood that they would pay higher rates over fewer summer months and lower rates over more winter months  Most like a narrow (3-hour) super peak period Commercial:  Customers who find it difficult to shift load and/or have flat load prefer a demand charge, and vice versa  Customers want a minimum of 24-hour notice for CPP  Prefer fewer CPP hours with higher prices vs. more hours with lower prices Residential:  Customers with flexible lifestyles said they will shift activities off peak  Want energy savings (from TOU vs. Tier) shown on bill  Basically like the idea of having pricing choices

10 SMUD Focus Group Findings on LM/DR General:  Most customers said they would respond to public pleas for energy conservation during periods of peak demand  Customers want the ability to override DR events  Generally more receptive to temperature reset than to AC cycling Commercial:  Small and medium customers want education on DR—more likely to participate in DR when it was explained to them  Some find it challenging to curtail/shift energy usage during peak periods due to industry type or business situation  Customers were creative in finding ways to adjust their business operations around peak periods  Many want event notification by cell phone or email Residential:  Households with ill or elderly members said personal control of their AC is critical  Renters find DR challenging because they don’t own the AC or have window AC units  Responses were mixed regarding preference for manual controls vs. “set it and forget it” controls

11 SMUD Current LM and DR Programs Curtailment contracts―14 MW Temperature-Dependent Rate―8 MW Demand Bid―5 MW Used only in emergencies:  Voluntary Emergency Curtailment Program―~45 MW  Peak Corps (residential AC cycling)―97 MW cycling, 135 MW shed Total dispatchable load = 111 to 149 MW  Using AC cycling, and special curtailment contracts Total non-dispatchable load = 0 to 58 MW  Using Temperature-Dependent Rate, Demand Bid and VECP

12 SMUD Proposed LM and DR Offerings Currently being evaluated in IRP process Designed to be used for active LM and DR Residential Customers  Air conditioning cycling  Air conditioning temperature reset  Choice of time-of-use rates, critical peak pricing  Public appeal to reduce electrical load Commercial Customers  Air conditioning temperature reset (<300 kW)  Aggregator program (300 kW – 999 kW)  Special curtailable contacts with the largest accounts (1> MW)  Choice of time-of-use rates, critical peak pricing, real time pricing  Technical assistance to evaluate demand response potential  Technology incentives for enabling equipment  Public appeal to reduce electrical load

13 SMUD LM/DR Program Redesign Timeline Develop new program concepts – 4 th Quarter 2007 Initial program screening – 1 st Quarter 2008 Evaluate programs through resource planning model – 3 rd Quarter 2008 Determine LM/DR resource mix and goals for next 10 years – 4 th Quarter 2008 Implement programs – 2009 - 2012

14 SMUD SMUD Position on PCT Standard Participation in programs should be voluntary (opt-in and/or opt-out) Override capability should be offered to participants in cycling and temperature reset programs SMUD prefers PCT standard because:  Offers customers more energy control options  Reduces costs of SMUD’s t-stat programs  Provides potential for greater participation with temperature reset option  Grows programs faster with opt-out for new construction and dwellings/buildings with existing equipment Opt-out retention rate of 60%-70% over 3 years Opt-in growth rate of 1.5%-2.5% annually, total of 5%-8% over 3 years  Reduces price of t-stats with bulk purchase power and lower installation costs in new construction  Increases control functionality and integration through greater sales  Grows DR infrastructure faster