Download presentation
Presentation is loading. Please wait.
Published byBernard Rose Modified over 9 years ago
1
PACS IHDR 12/13 Nov 2003 IBDR Close-out1 Close-out of IBDR Recommendations A. Poglitsch
2
PACS IHDR 12/13 Nov 2003 IBDR Close-out2 IBDR Board Conclusions Instrument Design and Internal Interfaces –The Board considers the instrument design and internal interfaces as consolidated and under basic configuration control for the FPU with the exception of the bolometer chain (in particular BOLA) –The status of the Warm Boxes is less satisfactory (in particular DEC/MEC and OBSW documentation). EMC and grounding scheme need to be addressed with no delay. Reliability analyses are still missing External Interfaces –The Board does not consider the interfaces to the spacecraft fully consolidated, however it sees these issues properly identified and expects industry to take the lead and to close out the pending issues with no delay
3
PACS IHDR 12/13 Nov 2003 IBDR Close-out3 IBDR Board Conclusions AIV and GSE –The model philosophy and verification approach need to be consolidated. Manufacturing flow charts need to be issued Schedule –The Schedule remains highly critical and PACS needs to establish means to ensure close monitoring and follow-up with subsystems Summary –While the Board considers that formally not all objectives of the IBDR have been fully met, it sees no need for a delta review –The Board expects the issues raised in the recommendations in this report, as well as in the comments transmitted to PACS prior to the review, to be addressed and resolved in the timeframe given in the recommendations, and … well in advance of the next review
4
PACS IHDR 12/13 Nov 2003 IBDR Close-out4 Board Recommendations R1: To ensure a coherent system approach, an agreed set of documents and a documentation tree shall be established between PACS system and subsystems and with ESA and Industry in the timeframe of the spacecraft PDR. We did our best – but far away from perfect
5
PACS IHDR 12/13 Nov 2003 IBDR Close-out5 Board Recommendations R2: Ensure schedule stability and close monitoring of subsystem activities to retain, and possibly advance delivery dates. In particular, test sequences need to be optimised while still ensuring full characterisation. As much as possible overall logistics/transportation shall be optimised. Procurement of long lead and/or single supplier items shall be monitored carefully. This is regarded as ongoing work. Schedule stability hard to achieve (no margins allowed), advance of delivery dates impossible Duration of ILT cut to absolute minimum (6 months)
6
PACS IHDR 12/13 Nov 2003 IBDR Close-out6 Board Recommendations R3: Provide all means to close out open interface issues, and to freeze the interfaces with the spacecraft before the PDR. Requirements defined from PACS side. Frequent communication with S/C contractor, progress has been made Still some important I/F requirements not agreed at time when PACS QM hardware has already been built!
7
PACS IHDR 12/13 Nov 2003 IBDR Close-out7 Board Recommendations R4: Ensure that a Derating and Worst Case Analysis has been properly conducted prior to manufacturing. Input for some subunits available Open – system approach not achieved; for some subunits only foreseen for QM/FM (contract constraints)
8
PACS IHDR 12/13 Nov 2003 IBDR Close-out8 Board Recommendations R5: System analyses, FMECA and FDIR should be performed jointly by system engineering with PA Based on available FMECA (input from subsystems), first version of system FDIR available Input from some subsystems only after AVM (see R4)
9
PACS IHDR 12/13 Nov 2003 IBDR Close-out9 Board Recommendations R6: Ensure and closely monitor appropriate PA approach at subsystem level and close communications between system and subsystem PA. Investigate ways of optimising/(re)distributing the PA work between system and subsystems. Progress made with some subsystem suppliers System-wide approach not yet achieved Some partners still have to be convinced – we’ll try again for FM
10
PACS IHDR 12/13 Nov 2003 IBDR Close-out10 Board Recommendations R7: Perform full signal detector (bolometer/ photoconductor + electronics) chain performance measurements as early as practically possible. This is considered normal work of highest priority Operation of photometer chain demonstrated –Bolometer focal plane array + multiplexer + buffer + BOLC –No meaningful noise measurements due to contact problem in 2K buffer unit Progress in spectrometer chain –Parallel operation of 7 photoconductor modules with CREs and active shield drivers in lab electronics achieved –Verification of full chain (including DECMEC) only at IL tests possible –Noise of QM CREs above spec (at least for blue array)
11
PACS IHDR 12/13 Nov 2003 IBDR Close-out11 Board Recommendations R8: Ensure early QM tests to feed back into FM programme. Perform low temperature testing as earlier as possible. Investigate ways to test the 48- hour baseline autonomy and cooler recycling in view of the PACS cryostat hold time limitation of 10 hours. The planning should be completed in the timeframe of the spacecraft PDR Qualification at QM subunit level advanced –Operation/characterisation of detector chains –Cryo-qualification of mechanism, mechanism control Test cryostat design modified for extended operation Planning complete, but subject to shifts/delays due to highly success-oriented schedule Feedback for FM limited by schedule constraints
12
PACS IHDR 12/13 Nov 2003 IBDR Close-out12 Board Recommendations R9: Identify a clear model philosophy and FPU simulators to support coherently the development of the instrument from unit to system level, and ensure that all AVM units will be form fit and function for the AVM and EQM system level tests Closed – SPU, DECMEC, BOLC only fit and function (RFD). Simulation modes built into DECMEC and BOLC
13
PACS IHDR 12/13 Nov 2003 IBDR Close-out13 Board Recommendations R10: Ensure proper documentation of OBSW for DPU, SPU and DEC/MEC. In particular the Software Specification Document (SSD) shall be updated to reflect the actual status of development and testing. This should be completed in the timeframe of the relevant tests Closed –SSDs available –SVVPs available for SPU, DPU Open – DECMEC SVVP
14
PACS IHDR 12/13 Nov 2003 IBDR Close-out14 Board Recommendations R11: Assess the thermal impact of cooler recycling operations Closed – thermal model of photometer unit including cooler available, input provided to S/C thermal model Results of thermal modeling by S/C contractor alarming – not only L1 but also L0 show noticeable variability over days after recycling / instrument switching
15
PACS IHDR 12/13 Nov 2003 IBDR Close-out15 Board Recommendations R12: Define and include into the overall test plan a few sensible “degraded” modes of operations in order to provide some level of insurance in case of post- launch failure of a major unit/component Closed – integrated in Operational Modes Document –Chopper –Grating –Filter wheels Open – inclusion in test plan
16
PACS IHDR 12/13 Nov 2003 IBDR Close-out16 Board Recommendations R13: Define and plan OBSW (DPU, SPU, DEC/MEC) performance tests in order to supplement the functional tests currently carried out Ongoing work – all nominal data rate modes tested Final test of burst mode pending
17
PACS IHDR 12/13 Nov 2003 IBDR Close-out17 Board Recommendations R14: Assess impact of microvibrations on the grating assembly Progress – bearings show now degradation after cryovibration, in fact, friction torque reduced Impact of microvibrations on position accuracy still to be evaluated quantitatively. (Performance tests on lab bench without vibration isolation are within spec)
18
PACS IHDR 12/13 Nov 2003 IBDR Close-out18 Board Recommendations R15: Assess all the implications (instrument design, OBSW and ground processing) of the implementation of the PACS-SPIRE parallel mode; in particular a full assessment of the impact on autonomy and FDIR should be performed. PACS is operating as prime instrument and requires no service from S/C other than in regular prime mode No additional OBSW or ground processing capabilities needed FDIR of PACS as prime instrument fully applicable
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.