Carbon Critical Design: Comparison of RE wall and RC viaduct on the Benz Circle Flyover, Andhra Pradesh Adrian Anderson, General Manager Nehemiah Reinforced Soils (India) Pvt Ltd.
2
Introduction The design decision The calculation The results Conclusion
3
Introduction
4
The design decision
6
The calculation Reinforced Concrete Viaduct (RC) Flyover Reinforced Soil (RS) Wall Flyover Tonnes of MaterialT CO 2 e/TTonnes of materialT CO 2 e/T M20 Mass Concrete 24 T (Footings)0.113 73T (Footings and anchor blocks) 0.113 M35 Reinforced Concrete 1014 T (Pre stressed beams 1.25% reinforcement by volume) 0.223 82 T (Facia panels - 0.48% reinforcement by volume) 0.121 M40 Reinforced concrete 643 (pre- stressed beams and crash barrier) 0.30824 (crash barrier)0.308 Compacted Aggregate 381 T0.00515,675 T0.005 Steel (excluding concrete reinforcement) 48 T (Post Tensioned Cables) 2.83014 T (soil reinforcing bars within backfill) 2.68
7
The Results RS=0.36xRC
8
Conclusions Move from Cost Critical to Carbon Critical Design Informed Design decisions Simple calculation to make Some local adaption required
9
Thank you Adrian Anderson, General Manager Nehemiah Reinforced Soils (India) Pvt Ltd.