Presentation is loading. Please wait.

Presentation is loading. Please wait.

PILE FOUNDATION Session 17 – 26

Similar presentations


Presentation on theme: "PILE FOUNDATION Session 17 – 26"— Presentation transcript:

1 PILE FOUNDATION Session 17 – 26
Course : S0825/Foundation Engineering Year : 2009 PILE FOUNDATION Session 17 – 26

2 PILE FOUNDATIONS SESSION 17 – 20 Topic: Types of pile foundation
Point bearing capacity of single pile Friction bearing capacity of single pile Allowable bearing capacity of single pile Bina Nusantara

3 INTRODUCTION Bina Nusantara

4 TYPES OF PILE FOUNDATION
STEEL PILE Bina Nusantara

5 TYPES OF PILE FOUNDATION
CONCRETE PILE Bina Nusantara

6 TYPES OF PILE FOUNDATION
CONCRETE PILE Bina Nusantara

7 TYPES OF PILE FOUNDATION
Bina Nusantara

8 TYPES OF PILE FOUNDATION
WOODEN PILE Bina Nusantara

9 TYPES OF PILE FOUNDATION
COMPOSITE PILE COMBINATION OF: STEEL AND CONCRETE WOODEN AND CONCRETE ETC Bina Nusantara

10 PILE CATEGORIES END BEARING PILES
Classification of pile with respect to load transmission and functional behaviour: END BEARING PILES These piles transfer their load on to a firm stratum located at a considerable depth below the base of the structure and they derive most of their carrying capacity from the penetration resistance of the soil at the toe of the pile FRICTION PILES Carrying capacity is derived mainly from the adhesion or friction of the soil in contact with the shaft of the pile COMPACTION PILES These piles transmit most of their load to the soil through skin friction. This process of driving such piles close to each other in groups greatly reduces the porosity and compressibility of the soil within and around the groups. Bina Nusantara

11 PILE CATEGORIES END BEARING PILE Bina Nusantara

12 PILE CATEGORIES FRICTION PILE Bina Nusantara

13 PILE CATEGORIES Classification of pile with respect to effect on the soil Driven Pile Driven piles are considered to be displacement piles. In the process of driving the pile into the ground, soil is moved radially as the pile shaft enters the ground. There may also be a component of movement of the soil in the vertical direction. Bina Nusantara

14 PILE CATEGORIES Classification of pile with respect to effect on the soil Bored Pile Bored piles(Replacement piles) are generally considered to be non-displacement piles a void is formed by boring or excavation before piles is produced. There are three non-displacement methods: bored cast- in - place piles, particularly pre-formed piles and grout or concrete intruded piles. Bina Nusantara

15 PILE CATEGORIES Bina Nusantara

16 DETERMINATION OF PILE LENGTH
Bina Nusantara

17 BEARING CAPACITY OF PILE
Two components of pile bearing capacity: Point bearing capacity (QP) Friction bearing capacity (QS) Bina Nusantara

18 BEARING CAPACITY OF PILE
Bina Nusantara

19 POINT BEARING CAPACITY
For Shallow Foundation - TERZAGHI SQUARE FOUNDATION qu = 1,3.c.Nc + q.Nq + 0,4..B.N CIRCULAR FOUNDATION qu = 1,3.c.Nc + q.Nq + 0,3..B.N - GENERAL EQUATION Where D is pile diameter, the 3rd term of equation is neglected due to its small contribution Deep Foundation qu = qP = c.Nc* + q.Nq* + .D.N* qu = qP = c.Nc* + q’.Nq* ; QP = Ap .qp = Ap (c.Nc* + q’.Nq*) Nc* & Nq* : bearing capacity factor by Meyerhof, Vesic and Janbu Ap : section area of pile Bina Nusantara

20 POINT BEARING CAPACITY MEYERHOF
PILE FOUNDATION AT UNIFORM SAND LAYER (c = 0) QP = Ap .qP = Ap.q’.Nq*  Ap.ql ql = 50 . Nq* . tan  (kN/m2) Base on the value of N-SPT : qP = 40NL/D  400N (kN/m2) Where: N = the average value of N-SPT near the pile point (about 10D above and 4D below the pile point) Bina Nusantara

21 POINT BEARING CAPACITY MEYERHOF
Bina Nusantara

22 POINT BEARING CAPACITY MEYERHOF
PILE FOUNDATION AT MULTIPLE SAND LAYER (c = 0) QP = Ap .qP Where: ql(l) : point bearing at loose sand layer (use loose sand parameter) ql(d) : point bearing at dense sand layer (use dense sand parameter) Lb = depth of penetration pile on dense sand layer ql(l) = ql(d) = 50 . Nq* . tan  (kN/m2) Bina Nusantara

23 POINT BEARING CAPACITY MEYERHOF
PILE FOUNDATION AT SATURATED CLAY LAYER (c  0) QP = Ap (c.Nc* + q’.Nq*) For saturated clay ( = 0), from the curve we get: Nq* = 0.0 Nc* = 9.0 and QP = 9 . cu . Ap Bina Nusantara

24 POINT BEARING CAPACITY VESIC
BASE ON THEORY OF VOID/SPACE EXPANSION PARAMETER DESIGN IS EFFECTIVE CONDITION QP = Ap .qP = Ap (c.Nc* + o’.N*) Where: o’ = effective stress of soil at pile point Ko = soil lateral coefficient at rest = 1 – sin  Nc*, N* = bearing capacity factors Bina Nusantara

25 POINT BEARING CAPACITY VESIC
According to Vesic’s theory N* = f (Irr) where Irr = Reduced rigidity index for the soil Ir = Rigidity index Es = Modulus of elasticity of soil s = Poisson’s ratio of soil Gs = Shear modulus of soil  = Average volumetric strain in the plastic zone below the pile point Bina Nusantara

26 POINT BEARING CAPACITY VESIC
For condition of no volume change (dense sand or saturated clay):  = 0  Ir = Irr For undrained conditon,  = 0 The value of Ir could be estimated from laboratory tests i.e.: consolidation and triaxial Initial estimation for several type of soil as follow: Type of soil Ir Sand 70 – 150 Silt and clay (drained) 50 – 100 Clay (undrained) 100 – 200 Bina Nusantara

27 POINT BEARING CAPACITY JANBU
QP = Ap (c.Nc* + q’.Nq*) Bina Nusantara

28 POINT BEARING CAPACITY BORED PILE
QP =  . Ap . Nc . Cp Where:  = correction factor = 0.8 for D ≤ 1m = 0.75 for D > 1m Ap = section area of pile cp = undrained cohesion at pile point Nc = bearing capacity factor (Nc = 9) Bina Nusantara

29 FRICTION RESISTANCE Where: p = pile perimeter
L = incremental pile length over which p and f are taken constant f = unit friction resistance at any depth z Bina Nusantara

30 FRICTION RESISTANCE SAND
Where: K = effective earth coefficient = Ko = 1 – sin  (bored pile) = Ko to 1.4Ko (low displacement driven pile) = Ko to 1.8Ko (high displacement driven pile) v’ = effective vertical stress at the depth under consideration = soil-pile friction angle = (0.5 – 0.8) Bina Nusantara

31 FRICTION RESISTANCE CLAY
Three of the presently accepted procedures are:  method This method was proposed by Vijayvergiya and Focht (1972), based on the assumption that the displacement of soil caused by pile driving results in a passive lateral pressure at any depth.  method (Tomlinson)  method Bina Nusantara

32 FRICTION RESISTANCE CLAY -  METHOD
Where: v’= mean effective vertical stress for the entire embedment length cu = mean undrained shear strength ( = 0) VALID ONLY FOR ONE LAYER OF HOMOGEN CLAY Bina Nusantara

33 FRICTION RESISTANCE CLAY -  METHOD
FOR LAYERED SOIL Bina Nusantara

34 FRICTION RESISTANCE CLAY -  METHOD
For cu  50 kN/m2   = 1 Bina Nusantara

35 FRICTION RESISTANCE CLAY -  METHOD
Where: v’= vertical effective stress  = K.tanR R = drained friction angle of remolded clay K = earth pressure coefficient at rest = 1 – sin R (for normally consolidated clays) = (1 – sin R) . OCR (for overconsolidated clays) Bina Nusantara

36 FRICTION RESISTANCE BORED PILE
Where: cu = mean undrained shear strength p = pile perimeter L = incremental pile length over which p is taken constant Bina Nusantara

37 ULTIMATE AND ALLOWABLE BEARING CAPACITY
DRIVEN PILE FS= BORED PILE D < 2 m and with expanded at pile point no expanded at pile point Bina Nusantara

38 EXAMPLE A pile with 50 cm diameter is penetrated into clay soil as shown in the following figure: GWL 5 m 20 m NC clay  = 18 kN/m3 cu = 30 kN/m2 R = 30o OC clay (OCR = 2)  = 19.6 kN/m3 cu = 100 kN/m2 Determine: End bearing of pile Friction resistance by , , and  methods Allowable bearing capacity of pile (use FS = 4) Bina Nusantara

39 PILE FOUNDATIONS SESSION 21 – 22 Topic: Settlement of Piles
Laterally Loaded Piles Pull Out Resistance of Piles Pile Driving Formula Negative Skin Friction Bina Nusantara

40 SETTLEMENT OF PILES S = S1 + S2 + S3 Where: S = total pile settlement
S1 = elastic settlement of pile S2 = settlement of pile caused by the load at the pile tip S3 = settlement of pile caused by the load transmitted along the pile shaft Bina Nusantara

41 SETTLEMENT OF PILES Where:
Qwp = load carried at the pile point under working load condition Qws = load carried by frictional (skin) resistance under working load condition Ap = area of pile cross section Ep = modulus of elasticity of the pile material L = length of pile  = the magnitude which depend on the nature of unit friction (skin) resistance distribution along the pile shaft. Bina Nusantara

42 SETTLEMENT OF PILES Where:
qwp = point load per unit area at the pile point = Qwp/Ap D = width or diameter of pile Es = modulus of elasticity of soil at or below the pile point s = poisson’s ratio of soil Iwp = influence factor = r Bina Nusantara

43 SETTLEMENT OF PILES Where: Qws = friction resistance of pile
L = embedment length of pile p = perimeter of the pile Iws = influence factor Bina Nusantara

44 EXAMPLE The allowable working load on a prestressed concrete pile 21 m long that has been driven into sand is 502 kN. The pile data are as follow: - Diameter (D) = 356 mm The area of cross section (Ap) = 1045 cm2 Perimeter (p) = m Skin resistance carries 350 kN of the allowable load, and point bearing carries the rest. Use Ep = 21 x 106 kN/m2, Es = 25,000 kN/m2, s = 0.35 and  = 0.62) Determine the settlement of the pile. Bina Nusantara

45 EXAMPLE S = S1 + S2 + S3 = 3.35 + 15.5 + 0.84 = 19.69 mm
Bina Nusantara

46 LATERALLY LOADED PILE Bina Nusantara

47 LATERALLY LOADED PILE ELASTIC SOLUTION – EMBEDDED IN GRANULAR SOIL
Bina Nusantara

48 LATERALLY LOADED PILE Bina Nusantara

49 LATERALLY LOADED PILE For L/T  5 Bina Nusantara

50 LATERALLY LOADED PILE Bina Nusantara

51 LATERALLY LOADED PILE Bina Nusantara

52 LATERALLY LOADED PILE ELASTIC SOLUTION – EMBEDDED IN COHESIVE SOIL
Bina Nusantara

53 LATERALLY LOADED PILE Bina Nusantara

54 LATERALLY LOADED PILE ULTIMATE LOAD ANALYSIS – MEYERHOF – PILES IN SAND ULTIMATE LOAD RESISTANCE (Qu(g)) Bina Nusantara

55 LATERALLY LOADED PILE MAXIMUM MOMENT, Mmax DUE TO THE LATERAL LOAD Qu(g) For long (flexible) piles in sand MAXIMUM MOMENT, Mmax DUE TO THE LATERAL LOAD Qg Bina Nusantara

56 LATERALLY LOADED PILE ULTIMATE LOAD ANALYSIS – MEYERHOF – PILES IN CLAY ULTIMATE LOAD RESISTANCE (Qu(g)) Bina Nusantara

57 LATERALLY LOADED PILE MAXIMUM MOMENT, Mmax DUE TO THE LATERAL LOAD Qu(g) For long (flexible) piles MAXIMUM MOMENT, Mmax DUE TO THE LATERAL LOAD Qg Bina Nusantara

58 PULL OUT RESISTANCE OF PILES
Bina Nusantara

59 PULL OUT RESISTANCE OF PILES
Bina Nusantara

60 PULL OUT RESISTANCE OF PILES
EXAMPLE: A concrete pile 50 long is embedded in a saturated clay with cu = 850 lb/ft2. The pile is 12 in. x 12 in. in cross section. Use FS = 4 and determine the allowable pullout capacity of the pile Solution Given cu = 850 lb/ft2  kN/m2 ’ = 0.9 – cu = 0.9 – ( )(40.73) = 0.645 Bina Nusantara

61 PULL OUT RESISTANCE OF PILES
Bina Nusantara

62 PULL OUT RESISTANCE OF PILES
For dry soils, the equation simplifies to Determine the value of Ku and  from figure 9.36b and 9.36c. Where Tun(all) = allowable uplift capacity and FS is Factor of Safety (a value of 2 – 3 is recommended) Bina Nusantara

63 PULL OUT RESISTANCE OF PILES
EXAMPLE: a precast concrete pile with a cross section 350 mm x 350 mm is embedded in sand. The length of pile is 15 m. Assume that sand = 15.8 kN/m3, sand = 35o, and the relative density of sand = 70%. Estimate the allowable pullout capacity of the pile (FS = 4) Solution From figure 9.36, for  = 35o and relative density = 70% Bina Nusantara

64 PILE DRIVING FORMULA Bina Nusantara

65 NEGATIVE SKIN FRICTION
Can occur under condition such as: If a fill of clay soil is placed over a granular soil layer into which a pile is driven, the fill will gradually consolidate. This consolidation process will exert a downward drag force on the pile during a period of consolidation If a fill of granular soil is placed over a layer of soft clay. It will induce the process of consolidation in the clay layer and thus exert a downward drag on the pile Bina Nusantara

66 NEGATIVE SKIN FRICTION
CLAY FILL OVER GRANULAR SOIL Bina Nusantara

67 NEGATIVE SKIN FRICTION
GRANULAR SOIL FILL OVER CLAY THE UNIT NEGATIVE SKIN FRICTION AT ANY DEPTH FROM z = 0 TO z = L1 Bina Nusantara

68 NEGATIVE SKIN FRICTION
Bina Nusantara

69 GROUP PILES SESSION 23 – 24 Topic: Bearing Capacity of Group Piles
Group Efficiency Piles in Rock Consolidation settlement of Group Piles Bina Nusantara

70 GROUP PILES Where: D = pile diameter
Lg = (n1 – 1)d + 2(D/2) Bg = (n2 – 1)d + 2(D/2) Where: D = pile diameter d = spacing of pile (center to center) Bina Nusantara

71 GROUP PILES Bina Nusantara

72 GROUP EFFICIENCY Where: = group efficiency
Qg(u) = ultimate load bearing capacity of the group pile Qu = ultimate load bearing capacity of each pile without the group effect Bina Nusantara

73 GROUP PILES IN SAND If  < 1  Qg(u) = .Qu If  1  Qg(u) = Qu
Bina Nusantara

74 GROUP PILES IN SAND Bina Nusantara

75 GROUP PILES IN SAND Bina Nusantara

76 GROUP PILES IN SAND Bina Nusantara

77 GROUP PILES IN SAND Summary:
For driven group piles in sand with d  3D, Qu(g) may be taken to be Qu, which includes the frictional and the point bearing capacities of individual piles. For bored group piles in sand at conventional spacings (d  3D), Qg(u) may be taken to be 2/3 to 3/4 times Qu (frictional and point bearing capacities of individual piles) Bina Nusantara

78 GROUP PILES IN SATURATED CLAY
Bina Nusantara

79 GROUP PILES IN SATURATED CLAY
Calculation steps: Determine Qu = n1.n2 (Qp + Qs) where: QP = 9 . cu . Ap (ultimate end bearing capacity of single pile) QS = (.p.cu.L) (skin resistance of single pile) Determine the ultimate capacity by assuming that the piles in the group act as a block with dimensional Lg x Bg x L as follow : - end bearing capacity of the block QP’ = Ap . qp = Ap . cu . Nc* with Ap = Lg . Bg - Skin resistance of the block QS’= (pg.cu.L) = 2.(Lg+Bg).cu.L - Ultimate bearing capacity o pile group Qu = QP’ + QS’ Qu = (Lg . Bg) . cu . Nc* + 2.(Lg+Bg).cu.L Compare the values obtained in step 1 and 2  the lower of the two values is Qg(u) Bina Nusantara

80 GROUP PILES IN SATURATED CLAY
Bina Nusantara

81 GROUP PILES IN SATURATED CLAY
Problem: The section of a 3 x 4 group pile layered saturated clay. The piles are square in cross section (14 in. x 14 in.). The center to center spacing, d, of the piles is 35 in. Determine the allowable load bearing capacity of the pile group. USE FS = 4 Bina Nusantara

82 GROUP PILES IN SATURATED CLAY
Bina Nusantara

83 PILES IN ROCK For point bearing piles resting on rock, most building codes specify that Qq(u) = Qu, provided that the minimum center to center spacing of piles is D mm. For H-Piles and piles with square cross sections, the magnitude of D is equal to the diagonal dimension of the pile cross section. Bina Nusantara

84 CONSOLIDATION SETTLEMENT OF GROUP PILES
The Terzaghi formula is valid with some rules: The consolidation settlement is occurred from the depth of 2/3 of pile length. The stress increase caused at the middle of each soil layer by using 2:1 method Bina Nusantara

85 CONSOLIDATION SETTLEMENT OF GROUP PILES
sat = 18,9 kN/m3 Cc = 0,2 eo = 0,7 sat = 19 kN/m3 Cc = 0,25 eo = 0,75 Problem: A group pile with Lg = 3.3 m and Bg = 2.2 m as shown in the figure. Determine the consolidation settlement of the pile groups. All clays are normally consolidated. sat = 18 kN/m3 Cc = 0,3 eo = 0,82 Bina Nusantara

86 ELASTIC SETTLEMENT OF GROUP PILES
VESIC Bina Nusantara

87 ELASTIC SETTLEMENT OF GROUP PILES
MEYERHOF (Pile groups in sand and gravel) Bina Nusantara

88 ELASTIC SETTLEMENT OF GROUP PILES
PILE GROUP SETTLEMENT RELATED TO THE CONE PENETRATION RESISTANCE Bina Nusantara

89 UPLIFT CAPACITY OF GROUP PILES
Bina Nusantara

90 UPLIFT CAPACITY OF GROUP PILES
Bina Nusantara

91 PILE INSTALLATION AND LOADING TEST
SESSION 25 – 26 Topic: Installation Method of Driven Pile Installation Method of Bored Pile Loading Test by Static Method Loading Test by Dynamic Method Bina Nusantara

92 INSTALLATION METHOD Pile Installation Equipment
The primary tools used in the actual driving (installing) of piles are : Impact Hammers, Vibrator Driver / Extractors Special Hydraulic Presses Supporting Equipment – power sources, hoisting & material handling equipment, etc. Bina Nusantara

93 PILE INSTALLATION EQUIPMENTS
Types of Impact Hammers Impact Hammers are identified by their method of operation or the motive force employed. They are generally identified as : Drop Hammers Air or Steam Hammers Diesel Hammers Hydraulic Impact Hammers Bina Nusantara

94 PILE INSTALLATION EQUIPMENTS
Drop Hammers Bina Nusantara

95 PILE INSTALLATION EQUIPMENTS
Air (or Steam) Hammers Bina Nusantara

96 PILE INSTALLATION EQUIPMENTS
Air (or Steam) Hammers Bina Nusantara

97 PILE INSTALLATION EQUIPMENTS
Diesel Hammers Bina Nusantara

98 PILE INSTALLATION EQUIPMENTS
Diesel Hammers Bina Nusantara

99 PILE INSTALLATION EQUIPMENTS
Hydraulic Impact Hammers Bina Nusantara

100 PILE INSTALLATION EQUIPMENTS
Hydraulic Impact Hammers Bina Nusantara

101 PILE INSTALLATION EQUIPMENTS
Vibro Driver/Extractors Bina Nusantara

102 PILE INSTALLATION EQUIPMENTS
Vibro Driver/Extractors Bina Nusantara

103 PILE INSTALLATION EQUIPMENTS
Hydraulic Press Installer Bina Nusantara

104 PILE INSTALLATION EQUIPMENTS
Hydraulic Press Installer Bina Nusantara

105 PILE INSTALLATION EQUIPMENTS
Land Based Rigs Cantilever Fixed Lead Bina Nusantara (With Fixed Bottom Brace) (With Spotter)

106 PILE INSTALLATION EQUIPMENTS
Land Based Rigs Under slung Swinging Lead Bina Nusantara (With Fixed Bottom Brace) (With stabbing points)

107 PILE INSTALLATION EQUIPMENTS
Land Based Rigs European Style, Fixed Lead with Fixed Bottom Brace Bina Nusantara (Driving Aft Batter with Hydraulic Hammer)

108 PILE INSTALLATION EQUIPMENTS
Land Based Rigs European Style, Fixed Lead on Crawler Lower Bina Nusantara

109 DRIVEN PILE INSTALLATION
Bina Nusantara

110 BORED PILE INSTALLATION
Bina Nusantara

111 PILE QUALITY Two aspects of final quality of pile:
Structural integrity of pile. Pile ability to support external load, consist of strength of structure element and relationship load-settlement between pile and soil support Bina Nusantara

112 STATIC LOADING TEST TEST METHODS Use Static Load
The load is 200% of working load Preparation before testing Loading Measurement of pile movement Instrumentation Bina Nusantara

113 STATIC LOADING TEST Loading Methods
Standard Method of Loading‑SML, Monotonic Standard Method of Loading‑SML, cyclic Quick Load Test (Quick ML) Constant Rate of Penetration Method (CRP) Bina Nusantara Sumber : Manual Pondasi Tiang, GEC

114 Typical arrangements for axial compressive load test
Anchor Pile Dead Load Bina Nusantara

115 STATIC LOADING TEST Bina Nusantara

116 STATIC LOADING TEST Test load arrangement using kentledge
Bina Nusantara

117 DYNAMIC LOADING TEST PDA (Pile Driving Analyzer)
DLT (Dynamic Load Test), TNO Theory of wave propagation Bina Nusantara Sumber : Manual Pondasi Tiang, GEC

118 Strain gauge and accelerometer Interpretation of PDA result
PDA computer Strain gauge and accelerometer Interpretation of PDA result Bina Nusantara

119 PULL OUT TESTS Pullout load by using hydraulic jack between beam and reaction frame (ASTM D , 1989) Bina Nusantara Sumber : Manual Pondasi Tiang, GEC

120 PULL OUT TESTS Pullout load by using hydraulic jack, one at each end of the beam (ASTM D , 1989) Bina Nusantara

121 LATERAL LOADING TEST Bina Nusantara Sumber : Manual Pondasi Tiang, GEC

122 LATERAL LOADING TEST Bina Nusantara

123 PILE INTEGRITY TEST This test is needed to check the integrity of bored pile or driven pile. Some methods generally adopted is by using the principle of wave propagation. The test is carried out by applying vibration and evaluating its reflection. Through this test, the defect on pile will be able to detect. Bina Nusantara Sumber : Manual Pondasi Tiang, GEC


Download ppt "PILE FOUNDATION Session 17 – 26"

Similar presentations


Ads by Google