Download presentation
1
PILE FOUNDATION Session 17 – 26
Course : S0825/Foundation Engineering Year : 2009 PILE FOUNDATION Session 17 – 26
2
PILE FOUNDATIONS SESSION 17 – 20 Topic: Types of pile foundation
Point bearing capacity of single pile Friction bearing capacity of single pile Allowable bearing capacity of single pile Bina Nusantara
3
INTRODUCTION Bina Nusantara
4
TYPES OF PILE FOUNDATION
STEEL PILE Bina Nusantara
5
TYPES OF PILE FOUNDATION
CONCRETE PILE Bina Nusantara
6
TYPES OF PILE FOUNDATION
CONCRETE PILE Bina Nusantara
7
TYPES OF PILE FOUNDATION
Bina Nusantara
8
TYPES OF PILE FOUNDATION
WOODEN PILE Bina Nusantara
9
TYPES OF PILE FOUNDATION
COMPOSITE PILE COMBINATION OF: STEEL AND CONCRETE WOODEN AND CONCRETE ETC Bina Nusantara
10
PILE CATEGORIES END BEARING PILES
Classification of pile with respect to load transmission and functional behaviour: END BEARING PILES These piles transfer their load on to a firm stratum located at a considerable depth below the base of the structure and they derive most of their carrying capacity from the penetration resistance of the soil at the toe of the pile FRICTION PILES Carrying capacity is derived mainly from the adhesion or friction of the soil in contact with the shaft of the pile COMPACTION PILES These piles transmit most of their load to the soil through skin friction. This process of driving such piles close to each other in groups greatly reduces the porosity and compressibility of the soil within and around the groups. Bina Nusantara
11
PILE CATEGORIES END BEARING PILE Bina Nusantara
12
PILE CATEGORIES FRICTION PILE Bina Nusantara
13
PILE CATEGORIES Classification of pile with respect to effect on the soil Driven Pile Driven piles are considered to be displacement piles. In the process of driving the pile into the ground, soil is moved radially as the pile shaft enters the ground. There may also be a component of movement of the soil in the vertical direction. Bina Nusantara
14
PILE CATEGORIES Classification of pile with respect to effect on the soil Bored Pile Bored piles(Replacement piles) are generally considered to be non-displacement piles a void is formed by boring or excavation before piles is produced. There are three non-displacement methods: bored cast- in - place piles, particularly pre-formed piles and grout or concrete intruded piles. Bina Nusantara
15
PILE CATEGORIES Bina Nusantara
16
DETERMINATION OF PILE LENGTH
Bina Nusantara
17
BEARING CAPACITY OF PILE
Two components of pile bearing capacity: Point bearing capacity (QP) Friction bearing capacity (QS) Bina Nusantara
18
BEARING CAPACITY OF PILE
Bina Nusantara
19
POINT BEARING CAPACITY
For Shallow Foundation - TERZAGHI SQUARE FOUNDATION qu = 1,3.c.Nc + q.Nq + 0,4..B.N CIRCULAR FOUNDATION qu = 1,3.c.Nc + q.Nq + 0,3..B.N - GENERAL EQUATION Where D is pile diameter, the 3rd term of equation is neglected due to its small contribution Deep Foundation qu = qP = c.Nc* + q.Nq* + .D.N* qu = qP = c.Nc* + q’.Nq* ; QP = Ap .qp = Ap (c.Nc* + q’.Nq*) Nc* & Nq* : bearing capacity factor by Meyerhof, Vesic and Janbu Ap : section area of pile Bina Nusantara
20
POINT BEARING CAPACITY MEYERHOF
PILE FOUNDATION AT UNIFORM SAND LAYER (c = 0) QP = Ap .qP = Ap.q’.Nq* Ap.ql ql = 50 . Nq* . tan (kN/m2) Base on the value of N-SPT : qP = 40NL/D 400N (kN/m2) Where: N = the average value of N-SPT near the pile point (about 10D above and 4D below the pile point) Bina Nusantara
21
POINT BEARING CAPACITY MEYERHOF
Bina Nusantara
22
POINT BEARING CAPACITY MEYERHOF
PILE FOUNDATION AT MULTIPLE SAND LAYER (c = 0) QP = Ap .qP Where: ql(l) : point bearing at loose sand layer (use loose sand parameter) ql(d) : point bearing at dense sand layer (use dense sand parameter) Lb = depth of penetration pile on dense sand layer ql(l) = ql(d) = 50 . Nq* . tan (kN/m2) Bina Nusantara
23
POINT BEARING CAPACITY MEYERHOF
PILE FOUNDATION AT SATURATED CLAY LAYER (c 0) QP = Ap (c.Nc* + q’.Nq*) For saturated clay ( = 0), from the curve we get: Nq* = 0.0 Nc* = 9.0 and QP = 9 . cu . Ap Bina Nusantara
24
POINT BEARING CAPACITY VESIC
BASE ON THEORY OF VOID/SPACE EXPANSION PARAMETER DESIGN IS EFFECTIVE CONDITION QP = Ap .qP = Ap (c.Nc* + o’.N*) Where: o’ = effective stress of soil at pile point Ko = soil lateral coefficient at rest = 1 – sin Nc*, N* = bearing capacity factors Bina Nusantara
25
POINT BEARING CAPACITY VESIC
According to Vesic’s theory N* = f (Irr) where Irr = Reduced rigidity index for the soil Ir = Rigidity index Es = Modulus of elasticity of soil s = Poisson’s ratio of soil Gs = Shear modulus of soil = Average volumetric strain in the plastic zone below the pile point Bina Nusantara
26
POINT BEARING CAPACITY VESIC
For condition of no volume change (dense sand or saturated clay): = 0 Ir = Irr For undrained conditon, = 0 The value of Ir could be estimated from laboratory tests i.e.: consolidation and triaxial Initial estimation for several type of soil as follow: Type of soil Ir Sand 70 – 150 Silt and clay (drained) 50 – 100 Clay (undrained) 100 – 200 Bina Nusantara
27
POINT BEARING CAPACITY JANBU
QP = Ap (c.Nc* + q’.Nq*) Bina Nusantara
28
POINT BEARING CAPACITY BORED PILE
QP = . Ap . Nc . Cp Where: = correction factor = 0.8 for D ≤ 1m = 0.75 for D > 1m Ap = section area of pile cp = undrained cohesion at pile point Nc = bearing capacity factor (Nc = 9) Bina Nusantara
29
FRICTION RESISTANCE Where: p = pile perimeter
L = incremental pile length over which p and f are taken constant f = unit friction resistance at any depth z Bina Nusantara
30
FRICTION RESISTANCE SAND
Where: K = effective earth coefficient = Ko = 1 – sin (bored pile) = Ko to 1.4Ko (low displacement driven pile) = Ko to 1.8Ko (high displacement driven pile) v’ = effective vertical stress at the depth under consideration = soil-pile friction angle = (0.5 – 0.8) Bina Nusantara
31
FRICTION RESISTANCE CLAY
Three of the presently accepted procedures are: method This method was proposed by Vijayvergiya and Focht (1972), based on the assumption that the displacement of soil caused by pile driving results in a passive lateral pressure at any depth. method (Tomlinson) method Bina Nusantara
32
FRICTION RESISTANCE CLAY - METHOD
Where: v’= mean effective vertical stress for the entire embedment length cu = mean undrained shear strength ( = 0) VALID ONLY FOR ONE LAYER OF HOMOGEN CLAY Bina Nusantara
33
FRICTION RESISTANCE CLAY - METHOD
FOR LAYERED SOIL Bina Nusantara
34
FRICTION RESISTANCE CLAY - METHOD
For cu 50 kN/m2 = 1 Bina Nusantara
35
FRICTION RESISTANCE CLAY - METHOD
Where: v’= vertical effective stress = K.tanR R = drained friction angle of remolded clay K = earth pressure coefficient at rest = 1 – sin R (for normally consolidated clays) = (1 – sin R) . OCR (for overconsolidated clays) Bina Nusantara
36
FRICTION RESISTANCE BORED PILE
Where: cu = mean undrained shear strength p = pile perimeter L = incremental pile length over which p is taken constant Bina Nusantara
37
ULTIMATE AND ALLOWABLE BEARING CAPACITY
DRIVEN PILE FS= BORED PILE D < 2 m and with expanded at pile point no expanded at pile point Bina Nusantara
38
EXAMPLE A pile with 50 cm diameter is penetrated into clay soil as shown in the following figure: GWL 5 m 20 m NC clay = 18 kN/m3 cu = 30 kN/m2 R = 30o OC clay (OCR = 2) = 19.6 kN/m3 cu = 100 kN/m2 Determine: End bearing of pile Friction resistance by , , and methods Allowable bearing capacity of pile (use FS = 4) Bina Nusantara
39
PILE FOUNDATIONS SESSION 21 – 22 Topic: Settlement of Piles
Laterally Loaded Piles Pull Out Resistance of Piles Pile Driving Formula Negative Skin Friction Bina Nusantara
40
SETTLEMENT OF PILES S = S1 + S2 + S3 Where: S = total pile settlement
S1 = elastic settlement of pile S2 = settlement of pile caused by the load at the pile tip S3 = settlement of pile caused by the load transmitted along the pile shaft Bina Nusantara
41
SETTLEMENT OF PILES Where:
Qwp = load carried at the pile point under working load condition Qws = load carried by frictional (skin) resistance under working load condition Ap = area of pile cross section Ep = modulus of elasticity of the pile material L = length of pile = the magnitude which depend on the nature of unit friction (skin) resistance distribution along the pile shaft. Bina Nusantara
42
SETTLEMENT OF PILES Where:
qwp = point load per unit area at the pile point = Qwp/Ap D = width or diameter of pile Es = modulus of elasticity of soil at or below the pile point s = poisson’s ratio of soil Iwp = influence factor = r Bina Nusantara
43
SETTLEMENT OF PILES Where: Qws = friction resistance of pile
L = embedment length of pile p = perimeter of the pile Iws = influence factor Bina Nusantara
44
EXAMPLE The allowable working load on a prestressed concrete pile 21 m long that has been driven into sand is 502 kN. The pile data are as follow: - Diameter (D) = 356 mm The area of cross section (Ap) = 1045 cm2 Perimeter (p) = m Skin resistance carries 350 kN of the allowable load, and point bearing carries the rest. Use Ep = 21 x 106 kN/m2, Es = 25,000 kN/m2, s = 0.35 and = 0.62) Determine the settlement of the pile. Bina Nusantara
45
EXAMPLE S = S1 + S2 + S3 = 3.35 + 15.5 + 0.84 = 19.69 mm
Bina Nusantara
46
LATERALLY LOADED PILE Bina Nusantara
47
LATERALLY LOADED PILE ELASTIC SOLUTION – EMBEDDED IN GRANULAR SOIL
Bina Nusantara
48
LATERALLY LOADED PILE Bina Nusantara
49
LATERALLY LOADED PILE For L/T 5 Bina Nusantara
50
LATERALLY LOADED PILE Bina Nusantara
51
LATERALLY LOADED PILE Bina Nusantara
52
LATERALLY LOADED PILE ELASTIC SOLUTION – EMBEDDED IN COHESIVE SOIL
Bina Nusantara
53
LATERALLY LOADED PILE Bina Nusantara
54
LATERALLY LOADED PILE ULTIMATE LOAD ANALYSIS – MEYERHOF – PILES IN SAND ULTIMATE LOAD RESISTANCE (Qu(g)) Bina Nusantara
55
LATERALLY LOADED PILE MAXIMUM MOMENT, Mmax DUE TO THE LATERAL LOAD Qu(g) For long (flexible) piles in sand MAXIMUM MOMENT, Mmax DUE TO THE LATERAL LOAD Qg Bina Nusantara
56
LATERALLY LOADED PILE ULTIMATE LOAD ANALYSIS – MEYERHOF – PILES IN CLAY ULTIMATE LOAD RESISTANCE (Qu(g)) Bina Nusantara
57
LATERALLY LOADED PILE MAXIMUM MOMENT, Mmax DUE TO THE LATERAL LOAD Qu(g) For long (flexible) piles MAXIMUM MOMENT, Mmax DUE TO THE LATERAL LOAD Qg Bina Nusantara
58
PULL OUT RESISTANCE OF PILES
Bina Nusantara
59
PULL OUT RESISTANCE OF PILES
Bina Nusantara
60
PULL OUT RESISTANCE OF PILES
EXAMPLE: A concrete pile 50 long is embedded in a saturated clay with cu = 850 lb/ft2. The pile is 12 in. x 12 in. in cross section. Use FS = 4 and determine the allowable pullout capacity of the pile Solution Given cu = 850 lb/ft2 kN/m2 ’ = 0.9 – cu = 0.9 – ( )(40.73) = 0.645 Bina Nusantara
61
PULL OUT RESISTANCE OF PILES
Bina Nusantara
62
PULL OUT RESISTANCE OF PILES
For dry soils, the equation simplifies to Determine the value of Ku and from figure 9.36b and 9.36c. Where Tun(all) = allowable uplift capacity and FS is Factor of Safety (a value of 2 – 3 is recommended) Bina Nusantara
63
PULL OUT RESISTANCE OF PILES
EXAMPLE: a precast concrete pile with a cross section 350 mm x 350 mm is embedded in sand. The length of pile is 15 m. Assume that sand = 15.8 kN/m3, sand = 35o, and the relative density of sand = 70%. Estimate the allowable pullout capacity of the pile (FS = 4) Solution From figure 9.36, for = 35o and relative density = 70% Bina Nusantara
64
PILE DRIVING FORMULA Bina Nusantara
65
NEGATIVE SKIN FRICTION
Can occur under condition such as: If a fill of clay soil is placed over a granular soil layer into which a pile is driven, the fill will gradually consolidate. This consolidation process will exert a downward drag force on the pile during a period of consolidation If a fill of granular soil is placed over a layer of soft clay. It will induce the process of consolidation in the clay layer and thus exert a downward drag on the pile Bina Nusantara
66
NEGATIVE SKIN FRICTION
CLAY FILL OVER GRANULAR SOIL Bina Nusantara
67
NEGATIVE SKIN FRICTION
GRANULAR SOIL FILL OVER CLAY THE UNIT NEGATIVE SKIN FRICTION AT ANY DEPTH FROM z = 0 TO z = L1 Bina Nusantara
68
NEGATIVE SKIN FRICTION
Bina Nusantara
69
GROUP PILES SESSION 23 – 24 Topic: Bearing Capacity of Group Piles
Group Efficiency Piles in Rock Consolidation settlement of Group Piles Bina Nusantara
70
GROUP PILES Where: D = pile diameter
Lg = (n1 – 1)d + 2(D/2) Bg = (n2 – 1)d + 2(D/2) Where: D = pile diameter d = spacing of pile (center to center) Bina Nusantara
71
GROUP PILES Bina Nusantara
72
GROUP EFFICIENCY Where: = group efficiency
Qg(u) = ultimate load bearing capacity of the group pile Qu = ultimate load bearing capacity of each pile without the group effect Bina Nusantara
73
GROUP PILES IN SAND If < 1 Qg(u) = .Qu If 1 Qg(u) = Qu
Bina Nusantara
74
GROUP PILES IN SAND Bina Nusantara
75
GROUP PILES IN SAND Bina Nusantara
76
GROUP PILES IN SAND Bina Nusantara
77
GROUP PILES IN SAND Summary:
For driven group piles in sand with d 3D, Qu(g) may be taken to be Qu, which includes the frictional and the point bearing capacities of individual piles. For bored group piles in sand at conventional spacings (d 3D), Qg(u) may be taken to be 2/3 to 3/4 times Qu (frictional and point bearing capacities of individual piles) Bina Nusantara
78
GROUP PILES IN SATURATED CLAY
Bina Nusantara
79
GROUP PILES IN SATURATED CLAY
Calculation steps: Determine Qu = n1.n2 (Qp + Qs) where: QP = 9 . cu . Ap (ultimate end bearing capacity of single pile) QS = (.p.cu.L) (skin resistance of single pile) Determine the ultimate capacity by assuming that the piles in the group act as a block with dimensional Lg x Bg x L as follow : - end bearing capacity of the block QP’ = Ap . qp = Ap . cu . Nc* with Ap = Lg . Bg - Skin resistance of the block QS’= (pg.cu.L) = 2.(Lg+Bg).cu.L - Ultimate bearing capacity o pile group Qu = QP’ + QS’ Qu = (Lg . Bg) . cu . Nc* + 2.(Lg+Bg).cu.L Compare the values obtained in step 1 and 2 the lower of the two values is Qg(u) Bina Nusantara
80
GROUP PILES IN SATURATED CLAY
Bina Nusantara
81
GROUP PILES IN SATURATED CLAY
Problem: The section of a 3 x 4 group pile layered saturated clay. The piles are square in cross section (14 in. x 14 in.). The center to center spacing, d, of the piles is 35 in. Determine the allowable load bearing capacity of the pile group. USE FS = 4 Bina Nusantara
82
GROUP PILES IN SATURATED CLAY
Bina Nusantara
83
PILES IN ROCK For point bearing piles resting on rock, most building codes specify that Qq(u) = Qu, provided that the minimum center to center spacing of piles is D mm. For H-Piles and piles with square cross sections, the magnitude of D is equal to the diagonal dimension of the pile cross section. Bina Nusantara
84
CONSOLIDATION SETTLEMENT OF GROUP PILES
The Terzaghi formula is valid with some rules: The consolidation settlement is occurred from the depth of 2/3 of pile length. The stress increase caused at the middle of each soil layer by using 2:1 method Bina Nusantara
85
CONSOLIDATION SETTLEMENT OF GROUP PILES
sat = 18,9 kN/m3 Cc = 0,2 eo = 0,7 sat = 19 kN/m3 Cc = 0,25 eo = 0,75 Problem: A group pile with Lg = 3.3 m and Bg = 2.2 m as shown in the figure. Determine the consolidation settlement of the pile groups. All clays are normally consolidated. sat = 18 kN/m3 Cc = 0,3 eo = 0,82 Bina Nusantara
86
ELASTIC SETTLEMENT OF GROUP PILES
VESIC Bina Nusantara
87
ELASTIC SETTLEMENT OF GROUP PILES
MEYERHOF (Pile groups in sand and gravel) Bina Nusantara
88
ELASTIC SETTLEMENT OF GROUP PILES
PILE GROUP SETTLEMENT RELATED TO THE CONE PENETRATION RESISTANCE Bina Nusantara
89
UPLIFT CAPACITY OF GROUP PILES
Bina Nusantara
90
UPLIFT CAPACITY OF GROUP PILES
Bina Nusantara
91
PILE INSTALLATION AND LOADING TEST
SESSION 25 – 26 Topic: Installation Method of Driven Pile Installation Method of Bored Pile Loading Test by Static Method Loading Test by Dynamic Method Bina Nusantara
92
INSTALLATION METHOD Pile Installation Equipment
The primary tools used in the actual driving (installing) of piles are : Impact Hammers, Vibrator Driver / Extractors Special Hydraulic Presses Supporting Equipment – power sources, hoisting & material handling equipment, etc. Bina Nusantara
93
PILE INSTALLATION EQUIPMENTS
Types of Impact Hammers Impact Hammers are identified by their method of operation or the motive force employed. They are generally identified as : Drop Hammers Air or Steam Hammers Diesel Hammers Hydraulic Impact Hammers Bina Nusantara
94
PILE INSTALLATION EQUIPMENTS
Drop Hammers Bina Nusantara
95
PILE INSTALLATION EQUIPMENTS
Air (or Steam) Hammers Bina Nusantara
96
PILE INSTALLATION EQUIPMENTS
Air (or Steam) Hammers Bina Nusantara
97
PILE INSTALLATION EQUIPMENTS
Diesel Hammers Bina Nusantara
98
PILE INSTALLATION EQUIPMENTS
Diesel Hammers Bina Nusantara
99
PILE INSTALLATION EQUIPMENTS
Hydraulic Impact Hammers Bina Nusantara
100
PILE INSTALLATION EQUIPMENTS
Hydraulic Impact Hammers Bina Nusantara
101
PILE INSTALLATION EQUIPMENTS
Vibro Driver/Extractors Bina Nusantara
102
PILE INSTALLATION EQUIPMENTS
Vibro Driver/Extractors Bina Nusantara
103
PILE INSTALLATION EQUIPMENTS
Hydraulic Press Installer Bina Nusantara
104
PILE INSTALLATION EQUIPMENTS
Hydraulic Press Installer Bina Nusantara
105
PILE INSTALLATION EQUIPMENTS
Land Based Rigs Cantilever Fixed Lead Bina Nusantara (With Fixed Bottom Brace) (With Spotter)
106
PILE INSTALLATION EQUIPMENTS
Land Based Rigs Under slung Swinging Lead Bina Nusantara (With Fixed Bottom Brace) (With stabbing points)
107
PILE INSTALLATION EQUIPMENTS
Land Based Rigs European Style, Fixed Lead with Fixed Bottom Brace Bina Nusantara (Driving Aft Batter with Hydraulic Hammer)
108
PILE INSTALLATION EQUIPMENTS
Land Based Rigs European Style, Fixed Lead on Crawler Lower Bina Nusantara
109
DRIVEN PILE INSTALLATION
Bina Nusantara
110
BORED PILE INSTALLATION
Bina Nusantara
111
PILE QUALITY Two aspects of final quality of pile:
Structural integrity of pile. Pile ability to support external load, consist of strength of structure element and relationship load-settlement between pile and soil support Bina Nusantara
112
STATIC LOADING TEST TEST METHODS Use Static Load
The load is 200% of working load Preparation before testing Loading Measurement of pile movement Instrumentation Bina Nusantara
113
STATIC LOADING TEST Loading Methods
Standard Method of Loading‑SML, Monotonic Standard Method of Loading‑SML, cyclic Quick Load Test (Quick ML) Constant Rate of Penetration Method (CRP) Bina Nusantara Sumber : Manual Pondasi Tiang, GEC
114
Typical arrangements for axial compressive load test
Anchor Pile Dead Load Bina Nusantara
115
STATIC LOADING TEST Bina Nusantara
116
STATIC LOADING TEST Test load arrangement using kentledge
Bina Nusantara
117
DYNAMIC LOADING TEST PDA (Pile Driving Analyzer)
DLT (Dynamic Load Test), TNO Theory of wave propagation Bina Nusantara Sumber : Manual Pondasi Tiang, GEC
118
Strain gauge and accelerometer Interpretation of PDA result
PDA computer Strain gauge and accelerometer Interpretation of PDA result Bina Nusantara
119
PULL OUT TESTS Pullout load by using hydraulic jack between beam and reaction frame (ASTM D , 1989) Bina Nusantara Sumber : Manual Pondasi Tiang, GEC
120
PULL OUT TESTS Pullout load by using hydraulic jack, one at each end of the beam (ASTM D , 1989) Bina Nusantara
121
LATERAL LOADING TEST Bina Nusantara Sumber : Manual Pondasi Tiang, GEC
122
LATERAL LOADING TEST Bina Nusantara
123
PILE INTEGRITY TEST This test is needed to check the integrity of bored pile or driven pile. Some methods generally adopted is by using the principle of wave propagation. The test is carried out by applying vibration and evaluating its reflection. Through this test, the defect on pile will be able to detect. Bina Nusantara Sumber : Manual Pondasi Tiang, GEC
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.