Download presentation
Presentation is loading. Please wait.
Published byCathleen Lynch Modified over 9 years ago
1
PowerPoint Authors: Susan Coomer Galbreath, Ph.D., CPA Charles W. Caldwell, D.B.A., CMA Jon A. Booker, Ph.D., CPA, CIA Cynthia J. Rooney, Ph.D., CPA Copyright © 2012 by The McGraw-Hill Companies, Inc. All rights reserved. Standard Costs and Variances Chapter 10
2
10-2 Standard Costs Standards are benchmarks or “norms” for measuring performance. In managerial accounting, two types of standards are commonly used. Quantity standards specify how much of an input should be used to make a product or provide a service. Price standards specify how much should be paid for each unit of the input.
3
10-3 Standard Costs Direct Material Deviations from standards deemed significant are brought to the attention of management, a practice known as management by exception. Type of Product Cost Amount Direct Labor Manufacturing Overhead Standard
4
10-4 Variance Analysis Cycle
5
10-5 Setting Standard Costs Should we use ideal standards that require employees to work at 100 percent peak efficiency? Engineer Managerial Accountant I recommend using practical standards that are currently attainable with reasonable and efficient effort.
6
10-6 Using Standards in Flexible Budgets Standard costs per unit for direct materials, direct labor, and variable manufacturing overhead can be used to compute activity and spending variances. Spending variances become more useful by breaking them down into quantity and price variances.
7
10-7 A General Model for Variance Analysis Variance Analysis Price Variance Difference between actual price and standard price Quantity Variance Difference between actual quantity and standard quantity
8
10-8 Variance Analysis Materials price variance Labor rate variance VOH rate variance Materials quantity variance Labor efficiency variance VOH efficiency variance A General Model for Variance Analysis Quantity VariancePrice Variance
9
10-9 Price VarianceQuantity Variance Actual Quantity Actual Quantity Standard Quantity × × × Actual Price Standard Price Standard Price A General Model for Variance Analysis
10
10-10 Price VarianceQuantity Variance Actual Quantity Actual Quantity Standard Quantity × × × Actual Price Standard Price Standard Price A General Model for Variance Analysis Actual quantity is the amount of direct materials, direct labor, and variable manufacturing overhead actually used.
11
10-11 Price VarianceQuantity Variance Actual Quantity Actual Quantity Standard Quantity × × × Actual Price Standard Price Standard Price A General Model for Variance Analysis Standard quantity is the standard quantity allowed for the actual output of the period.
12
10-12 Price VarianceQuantity Variance Actual Quantity Actual Quantity Standard Quantity × × × Actual Price Standard Price Standard Price A General Model for Variance Analysis Actual price is the amount actually paid for the input used.
13
10-13 A General Model for Variance Analysis Standard price is the amount that should have been paid for the input used. Price VarianceQuantity Variance Actual Quantity Actual Quantity Standard Quantity × × × Actual Price Standard Price Standard Price
14
10-14 A General Model for Variance Analysis (AQ × AP) – (AQ × SP) (AQ × SP) – (SQ × SP) AQ = Actual Quantity SP = Standard Price AP = Actual Price SQ = Standard Quantity Price VarianceQuantity Variance Actual Quantity Actual Quantity Standard Quantity × × × Actual Price Standard Price Standard Price
15
10-15 Glacier Peak Outfitters has the following direct material standard for the fiberfill in its mountain parka. 0.1 kg. of fiberfill per parka at $5.00 per kg. Last month 210 kgs of fiberfill were purchased and used to make 2,000 parkas. The material cost a total of $1,029. Material Variances Example
16
10-16 210 kgs. 210 kgs. 200 kgs. × × × $4.90 per kg. $5.00 per kg. $5.00 per kg. = $1,029 = $1,050 = $1,000 Price variance $21 favorable Quantity variance $50 unfavorable Actual Quantity Actual Quantity Standard Quantity × × × Actual Price Standard Price Standard Price Material Variances Summary
17
10-17 210 kgs. 210 kgs. 200 kgs. × × × $4.90 per kg. $5.00 per kg. $5.00 per kg. = $1,029 = $1,050 = $1,000 Price variance $21 favorable Quantity variance $50 unfavorable Actual Quantity Actual Quantity Standard Quantity × × × Actual Price Standard Price Standard Price $1,029 210 kgs = $4.90 per kg Material Variances Summary
18
10-18 210 kgs. 210 kgs. 200 kgs. × × × $4.90 per kg. $5.00 per kg. $5.00 per kg. = $1,029 = $1,050 = $1,000 Price variance $21 favorable Quantity variance $50 unfavorable Actual Quantity Actual Quantity Standard Quantity × × × Actual Price Standard Price Standard Price 0.1 kg per parka 2,000 parkas = 200 kgs Material Variances Summary
19
10-19 Material Variances: Using the Factored Equations Materials price variance MPV = AQ (AP - SP) = 210 kgs ($4.90/kg - $5.00/kg) = 210 kgs (-$0.10/kg) = $21 F Materials quantity variance MQV = SP (AQ - SQ) = $5.00/kg (210 kgs-(0.1 kg/parka 2,000 parkas)) = $5.00/kg (210 kgs - 200 kgs) = $5.00/kg (10 kgs) = $50 U
20
10-20 Hanson Inc. has the following direct material standard to manufacture one Zippy: 1.5 pounds per Zippy at $4.00 per pound Last week, 1,700 pounds of material were purchased and used to make 1,000 Zippies. The material cost a total of $6,630. Zippy Quick Check
21
10-21 1,700 lbs. 1,700 lbs. 1,500 lbs. × × × $3.90 per lb. $4.00 per lb. $4.00 per lb. = $6,630 = $ 6,800 = $6,000 Price variance $170 favorable Quantity variance $800 unfavorable Actual Quantity Actual Quantity Standard Quantity × × × Actual Price Standard Price Standard Price Zippy Quick Check
22
10-22 Glacier Peak Outfitters has the following direct labor standard for its mountain parka. 1.2 standard hours per parka at $10.00 per hour Last month, employees actually worked 2,500 hours at a total labor cost of $26,250 to make 2,000 parkas. Labor Variances Example
23
10-23 2,500 hours 2,500 hours 2,400 hours × × × $10.50 per hour $10.00 per hour. $10.00 per hour = $26,250 = $25,000 = $24,000 Rate variance $1,250 unfavorable Efficiency variance $1,000 unfavorable Actual Hours Actual Hours Standard Hours × × × Actual Rate Standard Rate Standard Rate Labor Variances Summary
24
10-24 Labor Variances Summary 2,500 hours 2,500 hours 2,400 hours × × × $10.50 per hour $10.00 per hour. $10.00 per hour = $26,250 = $25,000 = $24,000 Actual Hours Actual Hours Standard Hours × × × Actual Rate Standard Rate Standard Rate $26,250 2,500 hours = $10.50 per hour Rate variance $1,250 unfavorable Efficiency variance $1,000 unfavorable
25
10-25 Labor Variances Summary 2,500 hours 2,500 hours 2,400 hours × × × $10.50 per hour $10.00 per hour. $10.00 per hour = $26,250 = $25,000 = $24,000 Actual Hours Actual Hours Standard Hours × × × Actual Rate Standard Rate Standard Rate 1.2 hours per parka 2,000 parkas = 2,400 hours Rate variance $1,250 unfavorable Efficiency variance $1,000 unfavorable
26
10-26 Labor Variances: Using the Factored Equations Labor rate variance LRV = AH (AR - SR) = 2,500 hours ($10.50 per hour – $10.00 per hour) = 2,500 hours ($0.50 per hour) = $1,250 unfavorable Labor efficiency variance LEV = SR (AH - SH) = $10.00 per hour (2,500 hours – 2,400 hours) = $10.00 per hour (100 hours) = $1,000 unfavorable
27
10-27 Hanson Inc. has the following direct labor standard to manufacture one Zippy: 1.5 standard hours per Zippy at $12.00 per direct labor hour Last week, 1,550 direct labor hours were worked at a total labor cost of $18,910 to make 1,000 Zippies. Zippy Quick Check
28
10-28 Actual Hours Actual Hours Standard Hours × × × Actual Rate Standard Rate Standard Rate Rate variance $310 unfavorable Efficiency variance $600 unfavorable 1,550 hours 1,550 hours 1,500 hours × × × $12.20 per hour $12.00 per hour $12.00 per hour = $18,910 = $18,600 = $18,000 Zippy Quick Check
29
10-29 Variance Analysis and Management by Exception How do I know which variances to investigate? Larger variances, in dollar amount or as a percentage of the standard, are investigated first.
30
10-30 A Statistical Control Chart 123456789 Variance Measurements Favorable Limit Unfavorable Limit Warning signals for investigation Desired Value
31
10-31 Advantages of Standard Costs Management by exception Advantages Promotes economy and efficiency Simplified bookkeeping Enhances responsibility accounting
32
10-32 Potential Problems Emphasis on negative may impact morale. Emphasizing standards may exclude other important objectives. Favorable variances may be misinterpreted. Continuous improvement may be more important than meeting standards. Standard cost reports may not be timely. Invalid assumptions about the relationship between labor cost and output. Potential Problems with Standard Costs
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.