1
1 Liverpool Production Status Week of 9 February 2007
2
9 Feb. 2006VELO Weekly Meeting2 Production Status Completion of Installed Modules Mid-term Review X-mas
3
9 Feb. 2006VELO Weekly Meeting3 Production Status (2) PA/Chip Gluing Beetle Bonding Sensors Full Modules Completed For Installed Modules
4
9 Feb. 2006VELO Weekly Meeting4 This Week 3 modules delivered this week 1 week behind schedule in steps 2 weeks behind schedule in module delivery Estimated delivery date of 42 nd module is now March 2 nd Step 16 (BE bonding) complete for installed modules with expected yields Constraint system installed
5
9 Feb. 2006VELO Weekly Meeting5 Thermal Studies Trying to reproduce potential cooling issue, we ran two special tests with non-production parts Over-temperature Ran hybrid up to 60 C, 65 C & 70 C Over-torquing Torqued cooling screws to 50 cNm using cookie shaped blanks In both cases, no change was seen in cooling performance Not sure what this proves
6
9 Feb. 2006VELO Weekly Meeting6 Next Week Potentially slow week (1-2 modules delivered) Multiple people out sick Multiple people on vacation (half-terms) A bonder needs service Will be able to make up any shortfall week after next