1
1 Liverpool Production Status Week of 02 March 2007
2
02 March 2006VELO Weekly Meeting2 Production Status Completion of Installed Modules Mid-term Review X-mas
3
02 March 2006VELO Weekly Meeting3 Production Status (2) PA/Chip Gluing Beetle Bonding Sensors Full Modules
4
02 March 2006VELO Weekly Meeting4 This Week 2 modules delivered this week Now 1 spare R and phi at CERN 1 week behind schedule in steps 1 week behind schedule in module delivery H138 rejected due to large p-stop problem over ~250 channels Thus any additional needed spares have to come from parts started this week PA/chip gluing processing well 2 back-end bonded Friday 2 more ready for back-end bonding Monday Best estimate now for next module with sensors attached/bonded/tested is March 9 th Still estimate 4 days to take module from this state to shipping to CERN