1IT Project Management, Third Edition Chapter 6 Chapter 6: Project Time Management.

Similar presentations


Presentation on theme: "1IT Project Management, Third Edition Chapter 6 Chapter 6: Project Time Management."— Presentation transcript:

1 1IT Project Management, Third Edition Chapter 6 Chapter 6: Project Time Management

2 2IT Project Management, Third Edition Chapter 6 Importance of Project Schedules Managers often cite delivering projects on time as one of their biggest challenges Average time overrun from 1995 CHAOS report was 222%; improved to 163% in 2001 study Time has the least amount of flexibility; it passes no matter what Schedule issues are the main reason for conflicts on projects, especially during the second half of projects

3 3IT Project Management, Third Edition Chapter 6 Project Time Management Processes Project time management involves: –Activity definition –Activity sequencing –Activity duration estimating –Schedule development –Schedule control

4 4IT Project Management, Third Edition Chapter 6 Activity Sequencing Involves reviewing activities and determining dependencies –Mandatory dependencies: inherent in the nature of the work; hard logic –Discretionary dependencies: defined by the project team; soft logic –External dependencies: involve relationships between project and non-project activities You must determine dependencies in order to use critical path analysis

5 5IT Project Management, Third Edition Chapter 6 Project Network Diagrams Project network diagrams are the preferred technique for showing activity sequencing A project network diagram is a schematic display of the logical relationships among, or sequencing of, project activities

6 6IT Project Management, Third Edition Chapter 6 Figure 6-2. Sample Activity-on-Arrow (AOA) Network Diagram for Project X

7 7IT Project Management, Third Edition Chapter 6 Figure 6-3. Task Dependency Types

8 8IT Project Management, Third Edition Chapter 6 Sample PDM Network Diagram

9 9IT Project Management, Third Edition Chapter 6 Activity Duration Estimating After defining activities and determining their sequence, the next step in time management is duration estimating Duration includes the actual amount of time worked on an activity plus elapsed time Effort is the number of workdays or work hours required to complete a task. Effort does not equal duration People doing the work should help create estimates, and an expert should review them

10 10IT Project Management, Third Edition Chapter 6 Schedule Development Schedule development uses results of the other time management processes to determine the start and end date of the project and its activities Ultimate goal is to create a realistic project schedule that provides a basis for monitoring project progress for the time dimension of the project Important tools and techniques include Gantt charts, PERT analysis, critical path analysis, and critical chain scheduling

11 11IT Project Management, Third Edition Chapter 6 Sample Tracking Gantt Chart

12 12IT Project Management, Third Edition Chapter 6 Critical Path Method (CPM) CPM is a project network analysis technique used to predict total project duration A critical path for a project is the series of activities that determines the earliest time by which the project can be completed The critical path is the longest path through the network diagram and has the least amount of slack or float

13 13IT Project Management, Third Edition Chapter 6 Simple Example of Determining the Critical Path Consider the following project network diagram. Assume all times are in days. a. How many paths are on this network diagram? b. How long is each path? c. Which is the critical path? d. What is the shortest amount of time needed to complete this project?

14 14IT Project Management, Third Edition Chapter 6 Figure 6-8. Determining the Critical Path for Project X

15 15IT Project Management, Third Edition Chapter 6 More on the Critical Path If one or more activities on the critical path takes longer than planned, the whole project schedule will slip unless corrective action is taken Misconceptions: –The critical path is not the one with all the critical activities; it only accounts for time. Remember the example of growing grass being on the critical path for Disney’s Animal Kingdom Park –There can be more than one critical path if the lengths of two or more paths are the same –The critical path can change as the project progresses

16 16IT Project Management, Third Edition Chapter 6 Using Critical Path Analysis to Make Schedule Trade-offs Knowing the critical path helps you make schedule trade- offs Free slack or free float is the amount of time an activity can be delayed without delaying the early start of any immediately following activities Total slack or total float is the amount of time an activity may be delayed from its early start without delaying the planned project finish date A forward pass through the network diagram determines the early start and finish dates A backward pass determines the late start and finish dates

17 17IT Project Management, Third Edition Chapter 6 Techniques for Shortening a Project Schedule Shorten durations of critical tasks by adding more resources or changing their scope Crashing tasks by obtaining the greatest amount of schedule compression for the least incremental cost Fast tracking tasks by doing them in parallel or overlapping them

18 18IT Project Management, Third Edition Chapter 6 Crashing and Fast Tracking

19 19IT Project Management, Third Edition Chapter 6 Many Horror Stories Related to Project Schedules Creating realistic schedules and sticking to them is a key challenge of project management Crashing and fast tracking often cause more problems, resulting in longer schedules Organizational issues often cause schedule problems.

20 20IT Project Management, Third Edition Chapter 6 Controlling Changes to the Project Schedule Perform reality checks on schedules Allow for contingencies Don’t plan for everyone to work at 100% capacity all the time Hold progress meetings with stakeholders and be clear and honest in communicating schedule issues


Download ppt "1IT Project Management, Third Edition Chapter 6 Chapter 6: Project Time Management."