Download presentation
Presentation is loading. Please wait.
Published byPhilippa Welch Modified over 9 years ago
1
Purpose of Work Shop Share Ohio’s experience with a full closure reconstruction: the rationale, challenges, implementation and benefit
2
Background Statewide interstate reconstruction effort underway in Ohio to rebuild aging, heavily traveled highways and make them safer for 21 st Century traffic. ODOT is looking for creative ways to repair these roads while minimizing the negative impact to our customers
3
Interstate 670 When originally built during the ’60s, the 1.7 mile stretch of urban highway was considered state of the art. However traffic long outgrew the original design making it difficult to navigate and a high-accident location
4
Map of SSI Projects
5
Project History I-670 segment one of 15 projects worth $225 million to rebuild and redesign the downtown Columbus innerbelt and complete the missing link in Ohio’s interstate system.
6
More History … The work stalled for decades due to environmental regulations, lawsuits and lack of funding. Work began on the projects during the early ’90s using operating-cost savings from ODOT. Today only two projects remain.
7
Benefit When the work is completed in the fall, motorists will be able to travel directly from the west to east side of Columbus on a newer, safer, wider highway.
8
Why Full Closure? Given the long history of the project, ODOT and Columbus eager to complete remaining projects quickly ODOT could cut construction schedule by more than half using full closure vs. part- width
9
Project Scope Reconstructing and building new 1.7 miles of urban freeway including 21 bridges and 10 ramps Cost: $50 million Highway tightly bordered by historic neighborhoods, convention center and emerging business and arena districts
10
Existing Condition Two narrow lanes in each direction with little shoulder area Geometric deficiencies: sharp curves, short merge areas and ramps spaced too close Disrepair: crumbling concrete on bridges, medians and shoulders, rough road surface
14
Pix disrepair
15
Why Full Closure on I-670 Cut Construction from 4 years to 18 months Reduce the potential for accidents Worker Safety (difference in elevation) Reduce Driver Confusion Better Quality and Reduced Cost Experience with Full Closure (SR 315)
17
Process To pursue a full-closure approach, ODOT had to gather the facts and “build the case,” then present the information to key decision makers for support.
18
Analysis Traffic – where will the traffic go? Can the system support it? User Delay Costs – closing vs. maintaining traffic Life-cycle costs
20
Building Support Once we gathered the data, we had to “sell” the idea to key decision-makers. Mayor and Local Public Officials ODOT Executive Leadership Public Support was relatively easy to come by given the clear benefits.
21
Implementation Enacting the closure was easy. One week of prep for signs One day to close (weekend) Two weeks of traffic monitoring (Field, TMC and LEOs)
22
Public Outreach The hardest part of the full closure is the outreach needed to prepare the public. This effort began about six months in advance and continued at a steady pace leading up to and after the closure. It also involved the public relations AND construction staff.
23
Key Audience Motorists Businesses Residents Public Officials/Opinion Leaders Emergency Responders Schools Media
24
Type of Communication Fact Sheets Custom Flyers for nearby businesses Web site (www.I-670.org)www.I-670.org Group and One-on-One Presentations Media (pitched various news angles) Government Channel E-mail Updates – progress reports and traffic info
26
Key Messages Benefits of work (new, safer, wider highway, direct connection, completes interstate, design enhancements) Efforts to minimize construction delays (4 yrs to 18 mos, incentives/disincentives) Alternate Routes and Commuting Strategies
27
Construction Progress Work is currently 2/3 complete and on-time thanks to: $20,000 per day Liquidated Savings High-community profile Contractor has unrestricted access to work site
32
Would you use the full closure again? Yes! ODOT’s experience has been positive and we would use a full closure again under the right conditions.
33
Right Conditions Small section of roadway Tight physical constraints Variety of good alternate routes Clear public benefit “Building the case” and communicating the benefits is key!
34
Future Contracting Innovation Increasing public demand for less work zone congestion and the success of innovative projects have given ODOT the courage to try new techniques. Innovative Contracting Policy Fast Track Bridge Construction
35
QUESTIONS?
Similar presentations
© 2024 SlidePlayer.com. Inc.
All rights reserved.