T-76.115 Project Review Tetrastone [Iteration 2] 12.02.2004
2
T-76.115 Project Review 2 Agenda Project status (5 min) Achieving the goals of the iteration Project metrics Problems Used work practices (3 min) Completed work (10 min) Presenting the iteration’s results Demo Plans for the next iteration (5 min)
3
T-76.115 Project Review 3 Status of planned goals of the iteration Deliverables: Updated Project Plan Updated Requirements Specification Updated Technical Specification Updated Test Cases Test report and test log Progress report User's manual Customer deliverables: Updated version of the GUI Rest of UC-06 functionality Use cases 07-11 Use case 14
4
T-76.115 Project Review 4 Status of planned deliverables of the iteration Updated Project Plan Hours updated I3 tasks added I3 goals updated Static risks moved from RMP into PP Updated Requirements Specification No major updates Technical specification Some updates done Updated Test cases Test cases updated from the Iteration 1 Test report and test log New test report and log created User guide First version created Will be moved into RosettaNet EUI in next iteration Will acts as an online help
5
T-76.115 Project Review 5 Status of planned deliverables of the iteration Customer deliverables: Documentation Generally OK New documents – User guide initial version Use case 01-05 Organization removal has to be added 5h of work Use case 06 : Add / Delete / Modify PIP Saving undone, rest of the functionality ok Use case 07 : Add Trading partner info Ok Use case 08 : Add / Delete / Modify PIP (org. specific) UI done Todo: Look&Feel, saving, view Use cases 09: Add / Modufy / Delete user account Ok
6
T-76.115 Project Review 6 Status of planned deliverables of the iteration Use case 10: initialize new PIP exchange Frame and view done Saving plus other features not done Use case 11: Unfortunately not implemented Implementation moved to I3 Use case 12: Browse sent received PIPs Done Maybe some filtering rules have to be added Use case 15: Send message Ok Use case 16: Receive message Ok More can be seen on Demo later!
7
T-76.115 Project Review 7 Working hours by person Realized hours by person: Plan in the beginning of this iteration MEMBERHOURSDIFF Anssi72,5-7,5 Hanna60-20 Henry72,5-7,5 Kimmo84,7+4,7 Kjell75,5-4,5 Mikko53,50-1,5 Mikael68,5-11,5 TOTAL487,2 Phase Mikko Kjell Anssi Kimmo Henry Mikael Hanna Total Real: PhaseMikkoKjellAnssiKimmoHenryMikaelHannaTotalReal: PP503520 3520200161,5 I1304555405040 300 317 I25580 535 440 I3303540 3540260 DE4510 105 Total210205 190200 1901400 Problems: Long iteration – a lot of hours! Holidays A lot of work to do!
8
T-76.115 Project Review 8 Changes to the project The group was not able to complete the UC 12 in this iteration The implementation was moved to next iteration No other major changes were made
9
T-76.115 Project Review 9 Risks At this stage almost all the risks have been mapped and almost no new risks have been identified Materialized risks? Time tracking & estimation – The iteration has been very long and there has been a lot of holidays during it, so there has been problems is time estimations.
10
T-76.115 Project Review 10 Work practices Code review This was experienced in one session during the I2 phase The manual code reading / ‘debugging’ was considered very useful, since tens of bugs and errors were found Number of lines in code inspected:500 Number of found major bugs:3 Number of found minor bugs:6 Number of improvement suggestions:15 But! Total hours used in code inspection: 10 So the manual inspection of code is very time consuming and can not be effectively applied into large amounts of code - at least if the schedule is tight.
11
T-76.115 Project Review 11 Example: Demo RosettaNet End-user Interface DEMO 2.0
12
T-76.115 Project Review 12 Plan for the next iteration Goals: Finalize and fine tune the started use cases Implement the few not started use cases Deliverables: Updated Project Plan Updated Requirements Specification Updated technical specification Updated test cases Test report and test log Peer test plans Peer test reports Updated User’s manual Progress report Customer deliverables: Updated version of the GUI Fixed version of use cases 01-15 Use cases 12-13
13
T-76.115 Project Review 13 Plan for the next iteration Will be updated when I get the tasks out of the Trapoli system!
14
T-76.115 Project Review 14 Plan for the next iteration Will be updated when I get the tasks out of the Trapoli system!