JINDEX Status Report Washington Integrated Justice Information Board September 20, 2005 Scott Bream Department of Information Services
2
Project is approximately 4 weeks behind revised schedule. Focus is moving toward JINDEX interfaces and improvement of timeliness, reliability and data accuracy. High level of effort and commitment dedicated toward project success. Project Status
3
The success of this project is dependent on the cohesive interoperation of many entities and technical elements JINDEX Interfaces
4
Weekly meetings with members of the JIN Technical Advisory Group Administrative Office of the Courts, Department of Information Services, Department of Licensing, King County, Law Enforcement Support Agency, City of Seattle, Washington State, Patrol, Yakima County Project Commitment Daily conference calls with the JINDEX technical team Technical staff from King and Yakima Counties 4 – 5 members from DIS 3 – 4 members form Online Business Systems
5
Continued commitment by contractor. Continued commitment and cooperation from partner agencies. Continuing project oversight. Critical Keys to Success
6
Questions? Scott Bream, DIS scott@dis.wa.gov (360) 902-3460