Download presentation
Presentation is loading. Please wait.
Published byJonas Campbell Modified over 9 years ago
1
G’Day! Stefan Hörnlund University of South Australia stefan.hornlund@unisa.edu.au
2
Planning ahead
3
Learning Objectives After this lecture you should be able to; explain why we need to plan for the completion of a building project break down a project into a number of activities prepare a chart (precedence diagram) showing how these activities relate to each other, i.e. that some must be completed in a certain order whilst others can be carried out independently list some of the many considerations that the planner must take into account
4
Why do project planning? To achieve a stated objective in the way best suited to the particular project. To estimate what resources, like materials and labour, are needed and when they are needed. To provide a method of measuring and comparing actual progress with what was planned. To foresee problems and prepare for them.
5
Planning versus Control Planning decisions set the objectives to be accomplished and an agreed program of the activities required to accomplish that objective. In other words - we must do A, B and C etc to achieve our objective. Control decisions check the accomplishment of the activities and the agreed procedure for further activities or even changes to the objective, if the outcome of each activity is not in accordance with the planning decisions already made.
6
Constructability Constructability is the optimum integration of construction knowledge and experience in planning, engineering, procurement and field operations to achieve overall project objectives. ( CII 1983 )
7
No Door?
8
List of activities for a ‘Project’ A. Getting up B. Going to the bathroom C. Getting dressed D. Making breakfast E. Collecting the newspaper F. Eating breakfast G. Reading the paper H. Washing up I. Get briefcase J. Leave and lock door
9
Precedence diagram A B C D E F G H I J
10
Who does the planning? Senior management Client organization Estimating department Design team Site management team Subcontractors
11
Construction Description or Work List -Describe your activities -State any assumptions made
12
Method statement Method study techniques
13
Erection of timber framed partitions in two-storey blocks of units. Framing material: Timber 35-45 x 90-120 mm. Activity content Starting point: Material in materials storage area Content: Transportation Erection of frame including bottom plate, studs, top plate and noggins. Finishing point: Frame ready for cladding Work time Accumulated work time (t) in hours/m2 for 5000 m2 wall area Average area (m2) of each panel 4 5 7 10 15 Transportation of materials 0.01 0.01 0.01 0.01 0.01 Erection of frames with studs at centres: 0.4 m 0.33 0.30 0.26 0.24 0.21 0.6 m 0.29 0.25 0.22 0.19 0.17 0.9 m 0.25 0.22 0.19 0.16 0.14 Quantity of work Correction factors for work time at different total quantity of work Quantity of work (m2) 500 1000 2000 5000 10000 Correction factor 1.27 1.18 1.10 1.00 0.93 Slower Faster
14
Learning curve Time/unit Number of units
15
Special considerations Small site Geotechnical problems Remote location etc
16
Activities networks Precedence network A B C D E F G Arrow & Node network 1 2 3 5 6 7 4
17
Barchart Activity 1 2 3 4 5 6 7 8 9 10 11 12 13 Day Excavation Formwork Reinforcing Concreting Curing Form stripping
18
Heartbeat diagram Activity 1 2 3 4 5 6 7 8 9 10 11 12 13 Day Excavation Formwork Reinforcing Concreting Curing Form stripping
19
Calendar 2007 March April 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 Activity M T W T F S S M T W T F S S M T W T F S S A H B O C L D I E D F A Y
20
Linked Barchart (Gantt chart) ABCDEABCDE
21
Activity Draw a bar chart based on the following information Activity Duration (days) Depends on -------------------------------------------------------------------- A 5 Can start immediately B 5 A C 12 A D 3 C E 6 B and 2/3 of C F 8 B and 2/3 of C G 14 A H 5 D, E, F and G
22
Solution 5 10 15 20 25 30 A B C D E F G H
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.