Balancing Agility and Discipline Chapter 4 Sharon Beall EECS 811 April 22, 2004
2
2 Agenda Lease Management Example Command Center Processing and Display System Replacement (CCPDS- R) Example Home Ground Charts Summary
3
3 Lease Management The Project Leasing industry 500 KLOC 30 developers 20 participants 1,000 story cards 18 months with traditional approach 36 months with XP
4
4 Lease Management Eight “Bad Smells” 1.Time to develop story card increased in later iterations Iteration length static Too much tacit knowledge required Stories subdivided to meet schedules
5
5 Lease Management Eight “Bad Smells” 2.Integrating functions problematic in later iterations Individual tests okay Failed integration with other functions High-level architectural plan developed
6
6 Lease Management Eight “Bad Smells” 3.Unit and system testing issues Tacit knowledge strain again Complex specialized functions Breaking tests, architecture High-level architectural plan assisted
7
7 Lease Management Eight “Bad Smells” 4.Customer complaints No complaints until later iterations Customer never understood real user needs Early coaching necessary
8
8 Lease Management Eight “Bad Smells” 5.Integration, Schedules, and Effort Misrepresented accomplishments Story cards taking extra effort than portrayed Created task list for each story Monitored by management
9
9 Lease Management Eight “Bad Smells” 6.Refactoring Never Done Developers knew refactoring was needed Busy doing assigned work Detailed work plans and task lists included refactoring
10
10 Lease Management Eight “Bad Smells” 7.Simple design and YAGNI drawbacks Developers continuously refactoring some modules High costs since future changes known for those modules Adopted a pattern for this module after some time (YAGNI – You Aren’t Going to Need It)
11
11 Lease Management Eight “Bad Smells” 8.Test drivers and re-use Normally simple design and YAGNI Due to size and number of objects, different tests with similar drivers for different object states Adopted a pattern for test drivers as well
12
12 Lease Management Lessons Learned Tacit knowledge is agile, however with large software projects, presents scaling problems To diverge from an agile process requires talented people to recognize and respond Simple design is risky on large projects with known change
13
13
14
14 Lease Management Extending XP High level architectural plans Definitions of milestones and completion criteria Usage of patterns and architectural solutions Authors note…scale agile processes as-needed and as-discovered!
15
15 CCPDS-R The Project Re-engineer command center for missile warning system 1 million lines of code 75 programmers 3 user sets 48 months
16
16 CCPDS-R Agile Manifesto Individuals and Interactions over Processes and Tools TRW versus DoD DoD milestone standards redefined to reflect stakeholder’s interest. Use of automated tools to verify software to specs. Contract award fees designated for personnel System architecture organized for developers’ skill levels
17
17 CCPDS-R Agile Manifesto Working Software over Comprehensive Documentation DoD requires Preliminary Design Review (PDR) with docs and charts TRW chose to put it off until software could be demonstrated Documentation generated for those who really really needed it
18
18 CCPDS-R Agile Manifesto Customer Collaboration over Contract Negotiation Win-win idea used to negotiate contracts Ada version of COCOMO used Allowed for savings via reuse (if Agile, would have been costs due to YAGNI and rework)
19
19 CCPDS-R Agile Manifesto Responding to Change over Following a Plan Plans and specs were machine processable Metrics tracked progress in identifying problems Allowed easy tracking and early fixes Easy adaptation of plans Advance work in software reuse amongst 3 customer sets
20
20
21
21 CCPDS-R Extending Plan-Driven Methods A win-win customer driven view can be combined with a process-document driven view Award fees generated for TRW developers
22
22 Summary Examples that hybrids can succeed Easily tailoring the process not published Taking parts of each method to complement a given project is not easy, but can be successful …Guidelines in the next chapter to do this!
23
23 Closing Questions? Comments?