WP3 Required interfaces for cryostat design / integration Patxi DUTHIL SPL 3 rd Collaboration Meeting, CERN, Geneva November 12 th 2009
2
November 12 th 2009 3 rd SPL meeting 2 Goals & Motivation (WP3 specifications) Goal Design and construct a full-scale cryomodule prototype (Part of the SPL Design Study for a Project Proposal in 2011-2012) Motivation Demonstrate the construction capability, CM with β=1 cavities and SC quadrupoles; Validate and improve design and construction features Learning of the critical assembly phases Enable RF testing on a multi-cavity assembly (in real operating conditions) Learning of the critical assembly phases; Validate operation issues, cryogenic cooling principles and acquire experience Estimate production costs
3
November 12 th 2009 3 rd SPL meeting 3 SPL project CNRS-IN2P3 Tasks: 1/ To design and integrate the cryostat and to provide cryostat components for one cryomodule prototype; 2/ To design and provide the supporting/guiding system for the string of cavities in the cryostat; The deliverables: Hardware components Design and calculation reports, drawing files and design models Fully documented industrial production files: Material spec. Designed calculations (construction codes) Production drawings Assembly procedures Quality assurance and safety records
4
November 12 th 2009 3 rd SPL meeting 4 CNRS/IN2P3 contribution statement CERN – CEA - CNRS/IN2P3 –> collaboration agreement signed 3rd SPL meeting, Since then, CNRS/IN2P3 taskforce (already) operational Work slightly began Conceptual design (biblio…) Vacuum vessel design But…
5
November 12 th 2009 3 rd SPL meeting 5 CNRS/IN2P3 Planning uncompressible
6
November 12 th 2009 3 rd SPL meeting 6 CNRS/IN2P3 needs for cryostat design on time …but Needs of general layout specifications Needs of interfaces specifications To: Start the design and integration study by the beginning of 2010 = NOW ! → Short Term need (ST) (by end of 2009) Carry out this detailed design → Mid Term need (MT) 3 rd SPL meeting (or conceptual design period): we should fix the Short Time needs
7
November 12 th 2009 3 rd SPL meeting 7 Machine layout Longitudinal layout: Pattern for string of cavities(Short Term) Sectorization (ST) cryostat (vacuum, cryogenics) beam (vacuum, diagnostic) Quadripoles(ST) Cold/Warm Cross sectional layout Cryostat supporting system(ST) Orientation of RF coupler (vertical): Top/bottom(ST) Cavity string supporting reference (GRP ?) (ST) 1/2
8
November 12 th 2009 3 rd SPL meeting 8 Cryogenic layout T°, pressures (ST) Elements types (valves…) and dimensions (pipes)(ST) Cooling down protocol (spec. )(ST) Machine layout 2/2
9
November 12 th 2009 3 rd SPL meeting 9 RF System Cavity Outer diameter (LHe vessel) (ST) Mass (order of) (ST) Alignment specifications (to be confirmed) (ST) Alignment outer reference (ST) String assembly procedure(ST) Supporting mech interface(MT) Tuner Type (geometry, motor position…)(ST) Volume(ST) Coupler Mech. Interface(MT) Cooling(MT)
10
November 12 th 2009 3 rd SPL meeting 10 Beam dynamics Quadripoles (if SC) Alignment specifications (ST) Expected mass and volume(ST)
11
November 12 th 2009 3 rd SPL meeting 11 Infrastructure Cryostat handling(MT) Out of and in the tunnel Alignment method (2, 3 points)(MT) CERN cryogenic test facility interface(MT)
12
November 12 th 2009 3 rd SPL meeting 12 Instrumentation Instrumentation needs (MT) Should not be neglected in cryostat integration Mostly known from users/partners Might be already specified (feedthroughs…)→ (ST)
13
November 12 th 2009 3 rd SPL meeting 13 THANK YOU